Albany Highway project updates Albany Highway project updates

Albany Highway north


2016


14 October

The Albany Highway north upgrade has been completed 6 months ahead of schedule. The new $40-million road has been opened this morning.

Read the media release: Albany Highway north upgrade completed early.

7 October 

This week we:

  • Continued topsoil completion on both sides of Albany Highway between Bush Road and Rosedale Road
  • Continued installation of the cycle lane greening between Bush Road and Albany Expressway
  • Continued final line marking on Albany Highway between Rosedale Road and Albany Expressway
  • Completed construction of the pedestrian speed table at the entrance to Wentworth Park
  • Continued planting works and mulching along Albany Highway
  • Completed installation of split footpath and cycleway on the western side of Albany Highway near Days Bridge
  • Continue underpass works at the northern abutment of Days Bridge
  • Completed preparation of shared footpath on the western side of Albany Highway between Settlers Retirement Village and Library Lane
  • Completed final asphalt surfacing along full length of Albany Highway except for minor works

Next week we will:

  • Continue topsoil completion on both sides of Albany Highway between Rosedale Road and Albany Expressway
  • Continue installation of cycle lane greening between Bush Road and Albany Expressway
  • Continue final line marking between Rosedale Road and Albany Expressway
  • Continue planting works and mulching along Albany Highway
  • Commission the traffic signals at both the Bass Road /Oaklands Road and Wharf Road / Eastbourne Road intersections
  • Remove the pedestrian traffic signals outside Secret Garden
  • Continue underpass works at the northern abutment of Days Bridge
  • Complete the shared footpath on the western side of Albany Highway between Settlers Retirement Village and Library Lane

Night works

  • Road repairs and line marking as required
  • Continue installation of the final line marking on Albany Highway
  • Minor asphalt works including Stone and Water World car park, weather permitting

Looking ahead we plan to:

  • Complete planting and landscaping in early October

30 September

This week we:

  • Continued topsoil completion on both sides of Albany Highway between Bush Road and Rosedale Road
  • Continued installation of the transit lane and cycle lane greening between Bush Road and Albany Expressway
  • Completed the majority of final line marking on Albany Highway between Rosedale Road and Albany Expressway
  • Continued construction of the pedestrian speed table at the entrance to Wentworth Park
  • Continued planting works and mulching along Albany Highway
  • Completed median island works

Next week we will:

  • Continue installation of the transit lane and cycle lane greening between Bush Road and Albany Expressway
  • Complete construction of the pedestrian speed table at the entrance to Wentworth Park
  • Continue planting works on the eastern side of Albany Highway between Princeton Parade and Oaklands Road
  • Commission the traffic signals at both the Bass Road /Oaklands Road and Wharf Road / Eastbourne Road intersections

Night works:

  • Road repairs and line marking as required
  • Laying of final asphalt surfacing on Albany Highway between Rosedale Road and Albany Expressway, Sunday 25 September through to Tuesday 4 October (nightly, Sunday to Thursday) weather permitting
  • Continue installation of the final line marking on Albany Highway

 

Looking ahead we plan to:

  • Complete planting and landscaping in early October
  • Complete final asphalt surfacing in October
  • Commission remaining signalised intersections in October

23 September

This week we

  • Continued topsoil on both sides of Albany Highway between Bush Road and Oaklands Road
  • Completed the majority of final line marking on Albany Highway between Rosedale Road and Princeton Parade
  • Commenced installation of the transit lane and cycle lane greening
  • Commenced construction of a pedestrian speed table at the entrance to Wentworth Park  
  • Completed planting works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade
  • Completed planting works on the western side of Albany Highway between Secret Garden and Bass Road
  • Completed footpath works between Wentworth Park and Princeton Parade
  • Completed footpath works on the NW corner of Bass Road
  • Continued laying final asphalt surfacing on Albany Highway between Bass Road and Days Bridge
  • Continued fence construction and planting on the western side of Albany Highway between Wharf Road and Days Bridge
  • Continued footpath preparation and installation on both sides of Albany Highway between Wharf Road and Albany Expressway
  • Completed topsoiling and grassing of the central median islands
  • Completed all kerbing works
  • Continued underpass works at Days Bridge

Next week we will 

  • Continue planting works on the western side of Albany Highway between Secret Garden and Bass Road
  • Continue installation of the transit lane and cycle lane greening
  • Continue construction of a pedestrian speed table at the entrance to Wentworth Park  
  • Complete fence construction and planting on the western side of Albany Highway between Wharf Road and Days Bridge
  • Commission the traffic signals at both the Bass Road /Oaklands Road and Wharf Road / Eastbourne Road intersections
  • Continue footpath preparation and installation on both sides of Albany Highway between Wharf Road and Albany Expressway
  • Continue underpass works at Days Bridge

Night works

  • Road repairs and line marking as required
  • Laying of final asphalt surfacing on Albany Highway between Rosedale Road and Albany Expressway, Sunday 25 September through to Tuesday 4 October (nightly, Sunday to Thursday) weather permitting
  • Continue installation of the final line marking on Albany Highway

Looking ahead we plan to

  • Complete remaining median islands in September
  • Complete planting and landscaping in September
  • Complete final asphalt surfacing in October
  • Commission remaining signalised intersections in October

16 September

This week we

  • Completed final road line marking on Albany Highway between Bush Road and Rosedale Road.

  • Commissioned the pedestrian signal crossings on Albany Highway near Appleby Road and Oak Manor Drive. 

  • Continued preparation and laying of final asphalt surfacing on Albany Highway between Rosedale Road and Albany Expressway.

  • Continued planting works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.

  • Completed raising manholes to finished road level on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.

  • Completed topsoil installation at the entrance to Oaklands Road.
    Completed footpath pours at the entrance to Oaklands Road.

  • Completed central island kerb installation between Wharf Road and Albany Expressway.

  • Completed all edge kerbing for the project. Continued footpath installation on both sides of Albany Highway between Wharf Road and Albany Expressway.

  • Commenced fence construction and planting on the western side of Albany Highway between Wharf Road and Days Bridge. 

  • Commenced underpass panel works at Days Bridge.


Next week we will

  • Continue laying of final asphalt surfacing on Albany Highway between Rosedale Road and Albany Expressway.

  • Commence construction of a pedestrian speed table at the entrance to Wentworth Park.

  • Continue planting works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.

  • Continue planting works on the western side of Albany Highway between Secret Garden and Bass Road.

  • Commission the Bass Road intersection traffic signals.
    Remove the existing signalised pedestrian crossing outside Norfolk Pines Apartments.

  • Continue fence construction and planting on the western side of Albany Highway between Wharf Road and Days Bridge. 

  • Continue footpath preparation and installation on both sides of Albany Highway between Wharf Road and Albany Expressway.
    Continue underpass panel works at Days Bridge.

Night works

  • Road repairs and line marking as required.

  • Laying of final asphalt surfacing on Albany Highway between Rosedale Road and Albany Expressway, Sunday 18 September through to Tuesday 4 October (nightly, Sunday to Thursday) weather permitting.

Looking ahead

We plan to

  • Complete central median islands in September.

  • Complete planting and landscaping in September.

  • Complete final asphalt surfacing in October.

  • Commission remaining signalised intersections in October.

9 September 


2 September

This week we

  • Completed driveway works on the western side of Albany Highway between Rothwell Ave and Schnapper Rock Road.
  • Continued reinstallation of the concrete pavers at the entrance to Oakway Drive. 
  • Completed central median island works between Kristin Gate Two and Albany Veterinary Hospital.
  • Completed footpath preparation and commenced cycle path concrete pour at the entrance to Oaklands Road. 
  • Completed raising manholes to finished level between Bass Road and Wharf Road.
  • Commenced construction of a pedestrian speed table at the entrance to Summerfield Lane. 
  • Poured cycle path and footpath on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commenced tree pit excavation in the central median island between Wharf Road and the gas plant.
  • Completed footpath preparation on the eastern side of Albany Highway between the gas plant and Albany Senior High School. 
  • Completed foam stabilising on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continued footpath preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.

Next week we will

  • Complete reinstallation of the concrete pavers at the entrance to Oakway Drive.
  • Commence lifting manholes on the eastern side of Albany Highway between Wentworth Park and Princeton Parade. 
  • Continue top soiling and planting at the Oaklands Road intersection.
  • Continue construction of a pedestrian speed table at the entrance to Summerfield Lane. 
  • Continue top soiling on the western side of Albany Highway between Wharf Road and Days Bridge and commence noise fence construction.
  • Continue tree pit excavation in the central median island between Wharf Road and the gas plant.
  • Continue footpath preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.

Night works

  • Road repairs and line marking as required.
  • Prepare and laying of final asphalt surfacing on Albany Highway between Rosedale Road and Albany Expressway, Tuesday 6 September through to Tuesday 4 October (nightly, Sunday to Thursday) weather permitting.


Looking ahead we plan to

  • Complete central median islands in September.
  • Complete planting and landscaping in September.
  • Complete final asphalt surfacing in October.
  • Commission pedestrian crossings in September and signalised intersections in October.

 1 September 

Night works on Albany Highway beginning Sunday 4 September

We will lay the final asphalt surface on Albany Highway between Rosedale Road and Albany Expressway.

Work will start at Rosedale Road and progress in a northerly direction towards Albany Expressway.  The work is scheduled to take up to 4 weeks to complete, weather permitting.

This work on Albany Highway must happen at night because traffic volumes are too high to work safely during the day. Night work hours are 7pm to 5am. If we are delayed, then work will roll to the next available night.

  • We will be laying the final asphalt surface as part of the pavement construction.
  • During this time, please expect nightly lane closures from 7pm (Sunday to Thursday). A single traffic lane in each direction will remain open on Albany Highway however at times there may be delays and/or restrictions to property access as the work progresses across driveways and side roads.
  • There will be some truck movements, vibrations and noise associated with this work and we do apologise for any disruption.

26 August

This week we

  • Completed final asphalt surfacing on Albany Highway between Bush Road and Rosedale Road.
  • Completed traffic signal detector loops at Oakway Drive intersection.
  • Completed driveway concrete pour behind the retaining wall on the western side of Albany Highway between Rothwell Ave and Schnapper Rock Road.
  • Commenced reinstallation of the concrete pavers at the entrance to Oakway Drive.
  • Commenced median island works between Wentworth Park and Princeton Parade.
  • Completed top soiling and tree planting on the western side of Albany Highway between Kristin Gate Two and Albany Veterinary Clinic.
  • Commenced central median island and tree pit excavation within the central median islands between Kristin Gate Two and Albany Veterinary Clinic.
  • Continued footpath preparation at the entrance to Oaklands Road.
  • Continued cycle path and footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued footpath preparation on the eastern side of Albany Highway between the gas plant and Albany Senior High School.
  • Commenced foam stabilizing on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continued footpath preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.

Next week we will

  • Complete reinstallation of the concrete pavers at the entrance to Oakway Drive.
  • Complete median island works between Wentworth Park and Princeton Parade.
  • Continue footpath preparation and concrete pour at the entrance to Oaklands Road.
  • Continue central median island and tree pit excavation between Kristin Gate Two and Albany Veterinary Hospital.
  • Commence raising manholes to finished level between Bass Road and Wharf Road.
  • Commence construction of a pedestrian speed table at the entrance to Summerfield Lane.
  • Continue cycle path, footpath and top soiling on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commence tree pit excavation in the central median island between  Wharf Road and the gas plant.
  • Continue footpath preparation on the eastern side of Albany Highway between the gas plant and Albany Senior High School.
  • Continue pavement stabilisation on the western side of Albany Highway between Albany Senior High School and Library Lane, weather permitting.
  • Continue footpath preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.

Night works

  • Road repairs and line marking as required.

Looking ahead

We plan to:

  • Complete all major pavement works between Wharf Road and Albany Expressway in September.
  • Complete central median islands in August.
  • Complete planting and landscaping in September.
  • Commission pedestrian crossings and signalised intersections in October

19 August

This week we

  • Commenced final paving works between Bush Road and Rosedale Road.
  • Commenced driveway concrete pour behind the retaining wall on the western side of Albany Highway between Rothwell Ave and Schnapper Rock Road.
  • Reactivated the traffic signals at the Oakway Drive intersection.
  • Continued planting works on the eastern side of Albany Highway between Timberworld and Appleby Road.
  • Completed top soiling and tree planting on the western side of Albany Highway between Kristin Gate Two and Albany Veterinary Clinic.
  • Continued footpath preparation and completed pavement preparation at the entrance to Oaklands Road.
  • Continued earthworks, cycle path and footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commenced footpath works on the eastern side of Days Bridge.
  • Continued footpath preparation on the eastern side of Albany Highway between the gas plant and Albany Senior High School.
  • Continued pavement construction on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continued footpath preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.

Next week we will

  • Complete driveway concrete pour behind the retaining wall on the western side of Albany Highway between Rothwell Ave and Schnapper Rock Road
  • Commence reinstallation of the concrete pavers after final surfacing at the entrance to Oakway Drive. The exit will be shut from Tuesday 23 August with detours in place
  • Commence tree pit installation and central median island construction between Kristin Gate Two and Albany Veterinary Clinic
  • Continue footpath preparation and concrete pour at the entrance to Oaklands Road
  • Continue earthworks, cycle path and footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge
  • Continue footpath works on the eastern side of Days Bridge
  • Continue footpath preparation on the eastern side of Albany Highway between the gas plant and Albany Senior High School
  • Continue footpath preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village

Night works

  • Road repairs and line marking as required.
  • Complete the laying of final asphalt surfacing on Albany Highway between Bush Road and Rosedale Road on Sunday 21 August, weather permitting.
  • Carry out pavement stabilisation and chip sealing works Sunday 21 to Thursday 25 August from Albany Senior High School to Library Lane, weather permitting.

Looking ahead

We plan to:

  • Complete all major pavement works between Wharf Road and Albany Expressway in August.
  • Complete central median islands in August.
  • Complete planting and landscaping in September.
  • Commission pedestrian crossings and signalised intersections in October.

18 August

AT have finished the final asphalt surfacing in the intersection at Oakway Drive. We are now scheduled to reinstate the concrete pavers at the entrance to Oakway Drive.

This work will begin on Tuesday 23 August and take up to 3 weeks to complete, weather permitting.

  • Oakway Drive will be available for inbound traffic only.
  • All outbound traffic will be on diversion via Schnapper Rock Road (please see attached map).
  • Pedestrian access will remain available at all times.

The hours of work are 7am - 7pm, Monday to Friday, but some activities might require night and / or Saturday work.

Map showing exit and entry points around Oakway Drive

Albany Highway Upgrade Oakway Drive Paving Stones


22 July

This week we

  • Continued driveway reinstatement and drainage works behind the retaining wall between Rothwell Ave and Schnapper Rock Road.
  • Continued central median island works between Rothwell Ave and Oak Manor Drive.
  • Continued construction of a pedestrian speed table at the entrance to Appleby Road.
  • Raised manhole covers to their final level on Albany Highway between Rosedale Road and Wharf Road.
  • Continued footpath works on the western side of Albany Highway between Kristin Gate Two and Secret Garden.
  • Continue kerb and channel, pavement and footpath preparation at the entrance to Oaklands Road.
  • Completed reinstatement of bollards and Massey University footpath tie in south of Eastbourne Road.
  • Continued earthworks, cycle path and footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commenced scour protection and underpass works underneath Days Bridge.
  • Continued footpath, kerb and channel preparation on the eastern side of Albany Highway between the gas plant and Albany Senior High School.
  • Commenced pavement preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.

Next week we will

  • Continue planting preparation work on the eastern side of Albany Highway between Timberworld and Knights Road.
  • Continue central median island and planting works between Rothwell Ave and Oak Manor Drive.
  • Complete construction of a pedestrian speed table at the entrance to Appleby Road.
  • Continue footpath and driveway works on western side of Albany Highway between Kristin Gate Two and Secret Garden.
  • Continue kerb and channel, pavement and footpath preparation at the entrance to Oaklands Road.
  • Continue mulching and planting on the western side of Albany Highway between Bass Road and Wharf Road.
  • Continue earthworks, cycle path and footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commence balustrade installation on the eastern side of Days Bridge.
  • Continue footpath, kerb and channel preparation on the eastern side of Albany Highway between the gas plant and Albany Senior High School.
  • Commence earthworks on the eastern side of the Albany Highway between the gas plant and opposite Albany Senior High School.
  • Commence footpath preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.

Night works

  • Road repairs and line marking as required.
  • Lay a temporary road surface at the Oakway Drive intersection Sunday 24 July (weather permitting).
  • Asphalt western side of Albany Highway at the Bass Road intersection Sunday 24 July (weather permitting).

Looking ahead we plan to

  • Complete all major pavement works between Bush Road and Rosedale Road in July.
  • Complete all major pavement works between Wharf Road and Albany Expressway in August.
  • Central Islands to be completed in August.
  • Complete planting and landscaping in September.
  • Commission pedestrian crossings and signalised intersections in October.

15 July

This week we

  • Commenced driveway reinstatement works behind the retaining wall between Rothwell Ave and Schnapper Rock Road.
  • Continued central median island works between Rothwell Ave and Oak Manor Drive.
  • Commenced construction of a pedestrian speed table at the entrance to Appleby Road.
  • Completed construction of a pedestrian speed table at the entrance to Oak Manor Drive.
  • Continued footpath works on the western side of Albany Highway between Kristin Gate Two and Secret Garden.
  • Completed Vector services work at the Bass Road intersection.
  • Continued earthworks, cycle path and footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Completed foam stabilising on the western side of Albany Highway between Wharf Road and Albany Senior High School.
  • Completed chip sealing on the western side of Albany Highway between Wharf Road and Albany Senior High School.
  • Traffic switch re-aligning cars to centre of Days Bridge.
  • Commenced kerb and channel preparation on the eastern side of Albany Highway between the gas plant and Albany Senior High School.
  • Continued kerb and channel preparation on the western side of Albany Highway between Settlers Retirement Village and Library Lane.

Next week we will

  • Continue driveway reinstatement works behind the retaining wall between Rothwell Ave and Schnapper Rock Road.
  • Continue central median island works between Rothwell Ave and Oak Manor Drive.
  • Continue construction of a pedestrian speed table at the entrance to Appleby Road.
  • Continue footpath and driveway works on western side of Albany Highway between Kristin Gate Two and Secret Garden.
  • Commence kerb and channel, pavement and footpath preparation at the entrance to Oaklands Road.
  • Continue earthworks, cycle path and footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue kerb and channel preparation on the eastern side of Albany Highway between gas plant and Albany Senior High school.
  • Commence footpath prep from Albany Senior High school Gym to Settlers.

Night works

  • Road repairs and line marking as required.
  • Lay a temporary road surface at the Oakway Drive intersection Sunday 17 July (weather permitting).
  • Asphalt western side of Albany Highway at the Bass Road intersection Sunday 17 July (weather permitting).
  • Raise manhole covers on Albany Highway between Rosedale Road and Wharf Road Sunday 17 July through to Thursday 21 July.

Looking ahead we plan to

  • Complete all major pavement works between Bush Road and Rosedale Road in July.
  • Complete all major pavement works between Wharf Road and Albany Expressway in August.
  • Central Islands to be completed in August.
  • Complete planting and landscaping in September.
  • Commission pedestrian crossings and signalised intersections in October.

8 July

This week we

  • Stabilised the foam bitumen on the eastern side of Albany Highway between Rothwell Avenue and Schnapper Rock Road and the Oakway Drive intersection.
  • Continued central median island works between Rothwell Ave and Oakway Drive.
  • Continued central median island works between Appleby Road and Oak Manor Drive.
  • Continued construction of a pedestrian speed table at the entrance to Oak Manor Drive.
  • Continued footpath works on the western side of Albany Highway between Kristin Gate Two and Secret Garden.
  • Continued Vector services work at the Bass Road intersection.
  • Continued planting works on the western side of Albany Highway between Secret Garden and Wharf Road.
  • Completed lowering the bulk watermain at the entrance to Oaklands Road.
  • Continued planting works on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continued earthworks, cycle path and footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued pavement construction works on either side of Days Bridge.
  • Commenced foam stabilising on the western side of Albany Highway between Wharf Road and Albany Senior High School.
  • Continued kerb and channel preparation on the western side of Albany Highway between Settlers Retirement Village and Library Lane.

Next week we will

  • Continue central median island works between Rothwell Ave and Oakway Drive.
  • Commence construction of a pedestrian speed table at the entrance to Appleby Road.
  • Continue central median island works between Appleby Road and Oak Manor Drive.
  • Complete construction of a pedestrian speed table at the entrance to Oak Manor Drive.
  • Continue footpath and driveway works on western side of Albany Highway between Kristin Gate Two and Secret Garden.
  • Continue planting works on the western side of Albany Highway between Secret Garden and Wharf Road.
  • Commence pavement and footpath preparation at the entrance to Oaklands Road.
  • Continue Vector services work at the Bass Road intersection.
  • Continue earthworks, cycle path and footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commence final scour protection works on Days Stream.
  • Continue pavement construction works on either side of Days Bridge.
  • Commence footpath preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village

Night works

  • Road repairs and line marking as required.
  • Chipseal western side of Albany Highway between Wharf Road and Albany Senior High School Sunday 10 July (weather permitting).

Looking ahead

  • We plan to complete all major pavement works between Bush Road and Rosedale Road in July.
  • Complete all major pavement works between Wharf Road and Albany Expressway in August.


 1 July

This week we

  • Continued central median island works between Rothwell Ave and Oakway Drive.
  • Commenced central median island works between Appleby Road and Oak Manor Drive.
  • Continued construction of a pedestrian speed table at the entrance to Oak Manor Drive.
  • Continued footpath, site clearance and ducting works on the western side of Albany Highway between Kristin Gate Two and Secret Garden.
  • Continued planting works on the western side of Albany Highway between Secret Garden and Wharf Road.
  • Completed lowering the bulk watermain at the entrance to Oaklands Road.
  • Continued planting works on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continued earthworks, cycle path, footpath, kerb and channel preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued pavement construction works on either side of Days Bridge.
  • Completed kerb and channel installation on the western side of Albany Highway between Wharf Road and Settlers Retirement Village.
  • Continued kerb and channel preparation on the western side of Albany Highway between Settlers Retirement Village to Library Lane.

Next week we will

  • Continue central median island works between Rothwell Ave and Oakway Drive.
  • Continue central median island works between Appleby Road and Oak Manor Drive.
  • Continue construction of a pedestrian speed table at the entrance to Oak Manor Drive.
  • Continue footpath works on western side of Albany Highway between Kristin School Gate Two and Secret Garden.
  • Continue planting works on the western side of Albany Highway between Secret Garden and Wharf Road.
  • Commence pavement and footpath preparation at the entrance to Oaklands Road.
  • Complete planting works on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continue earthworks, cycle path, footpath preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue kerb and channel preparation on the western side of Albany Highway between Settlers Retirement Village to Library Lane.
  • Continue pavement construction works on either side of Days Bridge.

Night works

  • Road repairs and line marking as required.
  • Foam stabilise on the eastern side of Albany Highway between Rothwell Avenue and Schnapper Rock Road, and at the Oakway Drive intersection - Sunday 3, Monday 4, and Wednesday 6 July (weather permitting).

3 June

This week we

  • Continued planting works on both sides of Albany Highway between Bush Road and Wentworth Park.
  • Continued retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continued pavement and footpath works on western side of Albany Highway between Kristin Gate Two and Albany Veterinary Hospital.
  • Continued lowering bulk watermain at the entrance to Oaklands Road.
  • Continued placing topsoil on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Commenced tree planting on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continued cycle path, footpath, kerb and channel preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued earthworks on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued pavement construction works on either side of Days Bridge.
  • Completed bridge barrier works at Days Bridge.
  • Continued retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continued kerb and channel preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.

Next week we will

  • Continue planting works on both sides of Albany Highway between Bush Road and Wentworth Park.
  • Commence median island planting works between Rothwell and Oakway Drive (traffic switch required).
  • Continue retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continue pavement and footpath works on western side of Albany Highway between Kristin Gate Two and Albany Veterinary Hospital.
  • Continue lowering bulk watermain at the entrance to Oaklands Road.
  • Continue cycle path, footpath, kerb and channel preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue earthworks on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue pavement construction works on either side of Days Bridge.
  • Commence balustrade installation works on the western edge of Days Bridge.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continue kerb and channel preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.

Night works

  • Road repairs and line marking as required.
  • Deep lift asphalt on the western side of Albany Highway between Kristin Gate Two and Secret Garden, Wednesday 8 and Thursday 9 June, 8pm to 5am weather permitting.

Looking ahead

We plan to:

  • Complete all major pavement works between Bush Road and Rosedale Road in June.
  • Complete all major pavement works between Rosedale Road and Bass Road in June.

13 May

This week we

  • Commenced planting preparation works on both sides of Albany Highway between Bush Road and Wentworth Park Continued retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Completed footpath concrete works at the Oakway Drive/Albany Highway Intersection.
  • Continued kerb and channel, drainage, pavement and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Prepared and poured footpath on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continued earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued barrier preparation works and installation on Days Bridge.
  • Commenced barrier footing works on Days Bridge.
  • Continued service cutovers across Days Bridge.
  • Commenced kerb and channel preparation on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.
  • Continued retaining wall works on the western side of Albany Highway between Albany Senior High School and Library Lane.

 Next week we will

  • Continue planting preparation works on both sides of Albany Highway between Bush Road and Wentworth Park
  • Continue retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continue kerb and channel, drainage, pavement and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Install topsoil on the eastern side of Albany Highway between Princeton Parade and Norfolk Pines Apartments.
  • Traffic switch to the eastern side of Albany Highway between Princeton Parade and Norfolk Pines Apartments.
  • Prepare and pour footpath on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continue earthworks on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commence cyclepath, footpath, kerb and channel preparation on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue barrier footing works at Days Bridge.
  • Commence settlement slab works at Days Bridge.
  • Continue service cutovers across Days Bridge.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.

Night works

  • Road repairs and line marking as required.

Looking ahead

We plan to:

  • Complete all major pavement works between Bush Road and Rosedale Road in May.
  • Complete all major pavement works between Rosedale Road and Bass Road in June.

6 May

This week we

  • Continued footpath and pavement works at the Oakway Drive/Albany Highway intersection.
  • Continued kerb and channel, drainage, pavement and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Continued preparing for and pouring concrete footpaths on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Foam stabilised and chip sealed on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continued earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Completed stage 2 deck works on Days Bridge.
  • Commenced barrier installation on Days Bridge.
  • Continued retaining wall works on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Completed Albany Expressway intersection pavement works.

 Next week we will

  • Continue retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock RoadComplete footpath works at the Oakway Drive/Albany Highway Intersection.
  • Continue kerb and channel, drainage, pavement and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Continue placing topsoil on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue preparing for and pouring concrete footpath on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue earthworks on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue barrier installation works on Days Bridge.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.

Night works

  • Road repairs and line marking as required.

Looking ahead

We plan to:

  • Complete all major pavement works between Bush Road and Rosedale Road in May.
  • Complete all major pavement works between Rosedale Road and Bass Road in June.

29 April

This week we

  • Continued retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continued footpath and pavement works at the Oakway Drive/Albany Highway Intersection.
  • Continued kerb and channel, drainage, pavement and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Placed topsoil on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continued preparing for and pouring concrete footpath on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Continued earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Completed Albany Senior High School exit signal ducting upgrades.
  • Commence Albany Expressway intersection pavement works during weekend closure. 

Next week we will

  • Continue retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continue footpath and pavement works at the Oakway Drive/Albany Highway Intersection.
  • Continue kerb and channel, drainage, pavement and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Continue placing topsoil on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue preparing for and pouring concrete footpath on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Foam stabilise and chipseal on the eastern side of Albany Highway between Bass Road and Eastbourne Road.
  • Continue earthworks on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue Albany Senior High School exit signal ducting upgrades.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane. 

Night works

  • Road repairs and line marking as required.
  • On the night of Friday 29 April, we will pour concrete on Days Bridge to ‘stitch’ the two sections together. 
  • From Friday 29 April through to Monday 2 May, we will be undertaking pavement reconstruction including stabilising and asphalting at the Albany Expressway intersection. Due to the amount of work which is required to be completed this operation will continue in shifts for the majority of the closure period.
  • On the night of Sunday 1 May and Monday 2 May we will be stabilising between Wharf Road and Bass Road.
  • On the night of Wednesday 4 May we will be chipsealing the newly stabilised sections of pavement.

Looking ahead

We plan to

  • Complete all major pavement works between Bush Road and Rosedale Road in May.
  • Complete all major pavement works between Rosedale Road and Bass Road in June.

22 April

This week we

  • Completed stabilising and chipsealing on the western side of Albany Highway between 206 Albany Highway and Schnapper Rock Road North.
  • Continued retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continued driveway and footpath works at the Oakway Drive/Albany Highway Intersection.
  • Completed footpaths and driveway works on the eastern side between Wentworth Park and Princeton Parade.
  • Switched traffic and continued kerb and channel, driveway, speed table and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Reopened the entrance to Princeton Parade.
  • Continued drainage work on the eastern side of Albany Highway between Princeton Parade and Oaklands Road
  • Completed tree pit installations and continued pouring footpaths on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Continued earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commenced electrical cable cut-overs at Days Bridge. 
  • Installed kerb and channel and a new drive at the Albany Senior High School Gymnasium.
  • Continued retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Commenced and installed a cycle ramp at the north east corner of Albany Highway and Albany Expressway.

Next week we will

  • Continue retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continue footpath and pavement works at the Oakway Drive/Albany Highway Intersection.
  • Continue kerb and channel, drainage, pavement and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Place topsoil on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue footpath work on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Continue earthworks on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue electrical cable cut-overs at Days Bridge. 
  • Commence Albany Senior High School exit signal ducting upgrades.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.

Night works

  • Road repairs and line marking as required.


Looking ahead

We plan to:

  • Complete all major pavement works between Bush Road and Rosedale Road in May. 

15 April

This week we
  • Commenced stabilising and chipsealing on the western side of Albany Highway between 206 Albany Highway and Schnapper Rock Road North.
  • Continued retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continued driveway and footpath works on the south west corner and eastern side of the Oakway Drive/Albany Highway Intersection.
  • Completed a traffic switch to allow work to continue on footpath and pavement works on the north west corner of Oakway Drive/Albany Highway intersection.
  • Commenced kerb and channel, driveway, speed table and footpath works on the western side of Albany Highway at Kristin Gate Two.
  • Continued to prepare and pour concrete footpath and driveways on the eastern side of Albany Highway between Wentworth Park and Oaklands Road.
  • Completed speed table works at the entrance to Princeton Parade.
  • Continued installing a common service trench on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued headwall and corbel works on the north and south abutments of Days Bridge.
  • Completed installation of new service duct on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continued retaining wall works on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Completed footpath installation on the western side of Albany Highway between Library Lane and Albany Expressway.
  • Continued new street light installation on the western side of Albany Highway between Library Lane and Albany Expressway.
Next week we will
  • Continue retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continue driveway and footpath works at the Oakway Drive/Albany Highway Intersection.
  • Switch traffic and continue kerb and channel, driveway, speed table and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Continue to prepare and pour concrete footpath and driveways on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Pour headwall and corbel on the north and south abutments of Days Bridge.
  • Commence electrical cable cut-overs at Days Bridge new service ducting.
  • Commence kerb and channel preparation between Albany Senior High School and Settlers Retirement Village.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.
Night works
  • Road repairs and line marking as required.
  • Chipsealing on the western side of Albany Highway between 206 Albany Highway and Schnapper Rock Road,  17 April weather permitting.
Looking ahead we plan to
  • Complete all major pavement works between Bush Road and Rosedale Road in April.
  • Days Bridge deck stitch pour, end of April.

8 April

This week we
  • Continued drainage works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Recommenced retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Reopened Schnapper Rock Road in its final left in, left out configuration.
  • Continued kerb and channel, driveway and footpath works on the south west corner and eastern side of the Oakway Drive/Albany Highway Intersection.
  • Commenced installing tree pits on the eastern side of Albany Highway between Oak Manor Drive and Rosedale Road.
  • Continued to prepare and pour concrete footpath and driveways on the eastern side of Albany Highway between Wentworth Park and Oaklands Road.
  • Commenced speed table works at the entrance to Princeton Parade.
  • Continued power and telecom relocation works on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continued installing a common service trench on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued with headwall works at the south abutment of Days Bridge.
  • Recommenced installation of new service ducting on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continued retaining wall works on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continued footpath installation on the western side of Albany Highway between Library Lane and Albany Expressway.
  • Commenced new street light installation on the western side of Albany Highway between Library Lane and Albany Expressway
Next week we will
  • Continue retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continue driveway and footpath works on the south west corner and eastern side of the Oakway Drive/Albany Highway Intersection.
  • Commence kerb and channel, driveway, speed table and footpath works on the western side of Albany Highway between Kristin Gate Two and Princeton Parade.
  • Continue to prepare and pour concrete footpath and driveways on the eastern side of Albany Highway between Wentworth Park and Oaklands Road.
  • Continue speed table works at the entrance to Princeton Parade.
  • Complete power and telecom relocations on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue headwall works on the south and north abutments of Days Bridge.
  • Continue footpath and kerb and channel preparation on the eastern corner of Albany Highway and Albany Expressway.
  • Continue ducting and kerb & channel preparation on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.
Night works
  • Road repairs and line marking as required.
  • Stabilising and chipsealing on the eastern side of Albany Highway between 452 Albany Highway and Eastbourne Road, 11 to 13 April, weather permitting.
  • Stabilising and chipsealing on the western side of Albany Highway between 206 Albany Highway and Schnapper Rock Road, 13 to 17 April, weather permitting.
Looking ahead we plan to
  • Complete all major pavement works between Bush Road and Rosedale Road in April.
  • Days Bridge deck stitch pour, end of April.

1 April 

This week we
  • Commenced drainage works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continued kerb and channel, driveway and footpath works on the south west corner and eastern side of the Oakway Drive/Albany Highway Intersection.
  • Continued preparing and pouring concrete footpath and driveways on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Completed deep lift asphalt works on the eastern side of Albany Highway between Wentworth Park and Oaklands Road.
  • Completed kerb installation between Princeton Parade and Norfolk Pine Apartments.
  • Continued installing ducts and drainage work on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continued preparing and pouring concrete footpath and driveways on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continued installing a common service trench on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Completed Stage 2 beam placement on Days Bridge.
  • Continued retaining wall works on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continued footpath installation on the western side of Albany Highway between Library Lane and Albany Expressway.
  • Commenced new street light installation on the western side of Albany Highway between Library Lane and Albany Expressway.
  • Re-commenced installation of new service ducting on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.
Next week we will
  • Continue drainage works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Recommence retaining wall works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continue kerb and channel, driveway and footpath works on the south west corner and eastern side of the Oakway Drive/Albany Highway Intersection.
  • Continue footpath preparation works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Commence speed table works at the entrance to Princeton Parade.
  • Continue installing ducts and drainage work on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue to prepare and pour concrete footpath and driveways on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commence headwall works on the north and south sides of Days Bridge.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Library Lane.
  • Continue ducting and kerb & channel preparation on the western side of Albany Highway between Albany Senior High School and Library Lane.
Night works
  • Road repairs and line marking as required.
  • Raising fire hydrants April 5th on the eastern side of the Albany Highway adjacent to Appleby Road and Oak Manor Drive.
  • Stabilising and chipsealing on the eastern side of Albany Highway between 452 Albany Highway and Eastbourne Road, April 10th to 13th weather permitting.
  • Stabilising and chipsealing on the western side of Albany Highway between 206 Albany Highway and Schnapper Rock Road, April 12th to 17th weather permitting.
Looking ahead we plan to 
  • Re-open Schnapper Rock Road north in its final configuration in mid-April.
  • Complete all major works between Bush Road and Rosedale Road in mid-April.

24 March

This week we
  • Commenced kerb and channel, driveway and footpath works on the south west corner of Oakway Drive/Albany Highway intersection.
  • Continued footpath and driveway preparation works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Completed kerb installation on the eastern side of Albany Highway between Wentworth Park and Princeton Parade. 
  • Commenced deep lift asphalt works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Continued kerb installation on the eastern side of Albany Highway between Princeton Parade and Norfolk Pine Apartments.
  • Continued installing ducts and drainage works on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Completed pavement excavation on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Continued installing a common service trench on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued site set-up and detailing for beam placement on Days Bridge.
  • Continued underpass works on the north side of Days Bridge.
  • Continued retaining wall works on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.
  • Installed new kerb and channel and speed table at the entrance to Library Lane.
  • Commenced footpath excavation on the western side of Albany Highway between Library Lane and Albany Expressway.
Next week we will
  • Recommence retaining wall works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Commence drainage works on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continue kerb and channel, driveway and footpath works on the south west corner of Oakway Drive/Albany Highway Intersection.
  • Continue footpath and driveway preparation works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Continue deep lift asphalt works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade. 
  • Complete kerb installation on the eastern side of Albany Highway between Princeton Parade and Norfolk Pine Apartments.
  • Continue installing ducts on the eastern side of Albany highway between Princeton Parade and Oaklands Road. 
  • Continue footpath and driveway preparation works on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road. 
  • Continue drainage work on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continue earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.
  • Install a new footpath on the western side of Albany Highway between Library Lane and Albany Expressway.
  • Continue ducting and kerb & channel preparation on the western side of Albany Highway between Albany Senior High School and Library Lane.
Night works
  • Road repairs and line marking as required.
  • Deep lift asphalt on the eastern side of Albany Highway between Wentworth Park and Norfolk Pine Apartments, March 29th and 30th. 
  • Install the new Days Bridge beam sections, March 30th. This requires a full night closure.
  • Stabilising and chipsealing on the eastern side of Albany Highway between 452 Albany Highway and Eastbourne Road, April 10th to 13th weather permitting.
  • Stabilising and chipsealing on the western side of Albany Highway between 206 Albany Highway and Schnapper Rock Road, April 12th to 17th weather permitting.
Looking ahead we plan to
  • Complete all major works between Bush Road and Rosedale Road in mid-April.
  • Re-open Schnapper Rock Road north in its final configuration in mid-April.

18 March

This week we

  • Continued retaining wall works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continued driveway and footpath works on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Commenced kerb and channel, driveway and footpath works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Continued pavement excavation on the eastern side of Albany Highway between Wentworth Park and Oaklands Road.
  • Completed concrete sub-base on the eastern side of Albany Highway between Princeton Parade and 419 Albany Highway.
  • Installed kerb and channel on the eastern side of Albany Highway between Princeton Parade and Norfolk Pine Apartments.
  • Continued installing ducts and drainage work on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continued pavement excavation on the eastern side of Albany highway between Princeton Parade and Eastbourne Road.
  • Prepared and poured concrete footpath on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Commenced installing a common service trench on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Completed abutment works on the southern side of Days Bridge.
  • Continued retaining wall works on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.
  • Commenced service duct installation and kerb preparation on the western side of Albany Highway between Settlers Retirement Village and Library Lane.

Next week we will

  • Continue retaining wall works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Commence kerb and channel, driveway and footpath works on the south west corner of Oakway Drive.
  • Continue footpath and driveway preparation works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Continue installing concrete sub base, kerb and channel on the eastern side of Albany Highway between Princeton Parade and Norfolk Pine Apartments.
  • Continue installing ducts on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue pavement excavation on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Continue drainage work and concrete footpath on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continue earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue abutment works on the northern side of Days Bridge.
  • Commence site set-up and detailing for beam placement on Days Bridge.
  • Continue retaining wall work on the western side of Albany Highway between Albany Senior High School and Settlers Retirement Village.
  • Continue ducting and kerb and channel preparation on the western side of Albany Highway between Albany Senior High School and Library Lane.

Night works

  • Road repairs and line marking as required.
  • Deep lift asphalt on the eastern side of Albany Highway between Wentworth Park and Princeton Parade, 22 and 23 March.
  • Stabilising and chipsealing on the eastern side of Albany Highway between 452 Albany Highway and Eastbourne Road, 21 to 23 March.
  • Stabilising and chipsealing on the eastern side of Albany Highway between 206 Albany Highway and Schnapper Rock Road, 23 and 29 March.
  • Install the new Days Bridge beam sections, 30 March.

Looking ahead, we plan to

  • Complete all major works between Bush Road and Rosedale Road in mid-April.
  • Re-open Schnapper Rock Road north in its final configuration in mid-April.

11 March 

This week we

  • Continued retaining wall works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continued driveway and footpath works on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Continued pavement works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Installed concrete sub base on the eastern side of Albany Highway between Wentworth Park and 419 Albany Highway.
  • Continued installing service ducts and drainage works on the eastern aside of Albany Highway between Princeton Parade and Oaklands Road.
  • Continued pavement excavation on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continued abutment works on the southern side of Days Bridge.
  • Completed site clearance works on the western side of Albany Highway between Albany Senior High School and Albany Expressway.
  • Commenced service duct installation and kerb preparation on the western side of Albany Highway between Settlers Retirement Village and Library Lane.
  • Continued work on the retaining wall between Albany Senior High School and Settlers Retirement Village.
  • Completed enabling works for construction of a retaining wall between Settlers Retirement Village and Library Lane.
  • Completed all main drainage lines for the project.


Next week we will

  • Continue retaining wall works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continue driveway and footpath works on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Continue pavement works on the eastern side of Albany Highway between Wentworth Park and Oaklands Road.
  • Commence kerb and channel, driveway and footpath works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Install concrete kerb and channel on the eastern side of Albany highway between Princeton Parade and Norfolk Pine Apartments.
  • Continue pavement excavation on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continue installing ducts and drainage work on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Commence pavement excavation on the eastern side of Albany Highway at the Eastbourne Road intersection.
  • Continue earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue abutment works on the northern side of Days Bridge.
  • Continue ducting and kerb and channel preparation on the western side of Albany Highway between Albany Senior High school and Library Lane.
  • Continue work on the retaining wall between Albany Senior High School and Settlers Retirement Village.


Night works

  • Road repairs and line marking as required.


Looking ahead, we plan to

  • Complete all major works between Bush Road and Rosedale Road in mid-April.
  • Re-open Schnapper Rock Road north in its final configuration in early April.
  • Install the new Days Bridge beam sections at the end of March.

4 March

This week we
  • Continued retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Commenced kerb and channel, driveway and footpath works on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Completed milling and paving on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Continued pavement works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Continued drainage work on the western side of Albany Highway at the Princeton Parade/Albany Highway intersection.
  • Commenced concrete sub base on the eastern side of Albany Highway between Princeton Parade and 419 Albany Highway.
  • Continued installing ducts on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continued pavement excavation on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Completed concrete sub base on the eastern side of Albany Highway between Norfolk Pine Apartments and 452 Albany Highway.
  • Completed milling and paving on the eastern side of Albany Highway between Norfolk Pine Apartments and 452 Albany Highway.
  • Completed drainage work on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continued earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued abutment works on the southern side of Days Bridge.
  • Commenced stonestrong retaining works on the northern side of Days Bridge.
  • Commenced site clearance works on the western side of Albany Highway between Albany Senior High School and Albany Expressway.
  • Commenced enabling works for construction of a retaining wall between Settlers Retirement Village and Library Lane.
Next week we will
  • Continue retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continue driveway and footpath works on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Continue pavement works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Commence pavement excavation on Albany Highway at the Princeton Parade/Albany Highway intersection.
  • Continue concrete sub base on the eastern side of Albany Highway between Princeton Parade and 419 Albany Highway.
  • Continue drainage work and installing ducts on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue pavement excavation between Princeton Parade and Eastbourne Road.
  • Continue earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commence abutment works on the northern side of Days Bridge.
  • Continue enabling works for construction of a retaining wall between Settlers Retirement Village and Library Lane.
Night works
  • Road repairs and line marking as required.
Looking ahead

We plan to:

  • Complete all major works between Bush Road and Rosedale Road in early March.
  • Complete all main drainage lines for the project in early March.
  • Re-open Schnapper Rock Road north in its final configuration in late March.
  • Install the new Days Bridge beam sections in early April.

26 February

This week we
  • Continued retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continued pavement widening works on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Commenced site clearance and pavement widening works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Continued drainage work on the western side of Albany Highway outside Kristin Gate 2.
  • Continued drainage work on the eastern side of Albany Highway at the intersection of Princeton Parade.
  • Continued installing utility ducts on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Completed concrete sub base on the eastern side of Albany Highway between Norfolk Apartments and 452 Albany Highway.
  • Completed drainage work on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continued pavement excavation on the eastern side of Albany highway between Princeton Parade and Eastbourne Road.
  • Continued piling works on the northern side of Days Bridge.
  • Commenced abutment works on the northern side of Days Bridge.
  • Continued earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commenced site clearance and service investigation works on the western side of Albany Highway between Albany Senior High School and Albany Expressway.
Next week we will
  • Continue retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continue pavement works on eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Commence kerb and channel, driveway and footpath works on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Continue drainage work on the eastern side of Albany Highway at the Princeton Parade intersection.
  • Continue drainage work, pavement excavations and installing ducts on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Install concrete subbase on the eastern side of Albany Highway between Princeton Parade and 419 Albany Highway.
  • Continue earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue abutment works on the southern & northern side of Days Bridge.
  • Continue site clearance and service investigation works on the western side of Albany Highway between Albany Senior High School and Albany Expressway.
  • Begin enabling works for construction of a retaining wall between Settlers Retirement Village and Library Lane.
Night works
  • Road repairs and line marking as required.
  • Continue nightly drainage work on the western side of Albany Highway between Rosedale Road and the Institute of Golf.
  • Mill and lay asphalt on the eastern side of Albany Highway between Oakway Drive and Knights Road, Monday 29 February and Tuesday 1 March.
  • Mill and lay asphalt between Norfolk Apartments and 452 Albany Highway, Monday 29 February and Tuesday 1 March.
  • Catchpit relocations at the Oakway Drive roundabout Wednesday 2 and Thursday 3 March.
Looking ahead

We plan to:

  • Re-open Schnapper Rock Road north in its final configuration in early March.
  • Complete all major works between Bush Road and Rosedale Road in early March.
  • Complete all main drainage lines for the project in early March.
  • Install the new Days Bridge beam sections in mid-March.

19 February

This week we
  • Continued retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continued pavement widening works on the eastern side of Albany Highway between Oakway Drive to Knights Road.
  • Commenced site clearance and pavement works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Continued drainage work on the eastern side of Albany Highway at Princeton Parade intersection.
  • Continued installing ducts on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continued drainage work on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Continued drainage work on the western side of Albany Highway outside Kristin Gate 2.
  • Continued pavement excavation on the eastern side of Albany Highway between 419 Albany Highway and Eastbourne Road.
  • Poured concrete sub base on the eastern side of Albany Highway between Oaklands Road and 452 Albany Highway.
  • Continued earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Commenced piling on the northern side of Days Bridge.
  • Continued footpath works on the eastern side of Albany Highway between the Presbyterian Church and Albany Expressway.
  • Completed foam stabilisation and chip sealed the eastern side of Albany Highway between the Presbyterian Church and Albany Expressway.
  • Switched traffic to the eastern side of Albany Highway between the Presbyterian Church and Albany Expressway.
  • Commenced site clearance and service investigation works on the western side of Albany Highway between Albany Senior High School and Albany Expressway.
Next week we will
  • Continue retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continue pavement widening works on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Continue pavement works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Continue drainage work on the eastern side of Albany Highway at Princeton Parade intersection.
  • Continue drainage work on the western side of Albany Highway outside Kristin Gate 2.
  • Continue installing ducts on the eastern side of Albany Highway between Princeton Parade and Oaklands Road.
  • Continue drainage work on the eastern side of Albany Highway between Princeton Parade and Eastbourne Road.
  • Complete concrete sub base on the eastern side of Albany Highway between 419 Albany Highway and Oaklands Road.
  • Install kerb and channel on the eastern side of Albany Highway between 419 Albany Highway and Eastbourne Road.
  • Continue pavement excavation on the eastern side of Albany Highway between Oaklands Road and Eastbourne Road.
  • Continue earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continue piling on the northern side of Days Bridge.
  • Continue site clearance and service investigation works on the western side of Albany Highway between Albany Senior High School and Albany Expressway.
  • Begin enabling works for construction of a retaining wall between Settlers Retirement Village and Library Lane.
Night works
  • Road repairs and line marking as required.
Looking ahead
  • Re-open Schnapper Rock Road north in its final configuration in early March.
  • Complete all major works between Bush Road and Rosedale Road in early March.
  • Complete all main drainage lines for the project in early March.
  • Install the new Days Bridge beam sections in mid-March.

5 February

This week we
  • Continued retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Poured new kerb and channel on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • Continued footpath preparation works on the western side of Albany Highway between Oakway Drive and Albany Junior High School.
  • Continue vehicle crossing and footpath works on the eastern side of Albany Highway between Knights Road and Rosedale Road.
  • Continued drainage work at Princeton Parade/Albany Highway intersection.
  • Continued pavement excavation between Oaklands Road and 419 Albany Highway.
  • Continued drainage work between Princeton Parade and Oaklands Road.
  • Continued installing ducts between Princeton Parade and Oaklands Road.
  • Commenced pavement excavation between Oaklands Road and Eastbourne Road.
  • Continued earthworks and ducting on the western side of Albany Highway between Wharf Road and Days Bridge.
  • Continued earthworks, pavement widening and footpath works on the eastern side of Albany Highway between the Presbyterian Church and Albany Expressway.
Next week we will
  • Continue retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Remove the traffic signals and islands at Oakway intersection and install a temporary roundabout.
  • Commence pavement widening works on the eastern side from Oakway Drive to Knights Rd.
  • Commence site clearance and road widening works on the eastern side of Albany Highway between Wentworth Park and Princeton Parade.
  • Continue drainage work at the Princeton Parade/Albany Highway intersection.
  • Continue drainage work between Princeton Parade and Oaklands Road.
  • Pour the concrete sub base between Oaklands Road and 419 Albany Highway.
  • Continue pavement excavation between Oaklands Road and Eastbourne Road.
  • Continue earthworks, pavement widening and footpath works between Wharf Road and Days Bridge.
  • Continue earthworks, pavement widening, pouring driveways and footpath works between the Presbyterian Church and Albany Expressway.
  • Undertake road stabilisation on the eastern side of Albany Highway between the Presbyterian Church and Albany Expressway
Night works
  • Road repairs and line marking as required.
  • Switch Oakway Drive intersection from traffic lights to roundabout, Monday 8 February.
  • Commence kerb and channel and pavement works on the eastern side of Albany Highway between Oakway Drive and Knights Road.
  • Stabilise the road on the eastern side of Albany Highway between the Presbyterian Church and Albany Expressway, Tuesday 9 to Thursday 11 February, weather depending.
  • Lay chip seal on the eastern side of Albany Highway between the Presbyterian Church and Albany Expressway, Sunday 14 February., weather depending.

Looking ahead

We plan to:

  • Switch traffic to the eastern side of Albany Highway by Settlers Village mid-February.
  • Re-open Schnapper Rock Road north in its final configuration in late February.
  • Complete all major works between Bush Road and Rosedale Road in early March.
  • Install the new Days Bridge beam sections in mid-March.
  • Complete all main drainage lines for the project in early March.

22 January

This week we
  • Installed new kerb and channel on western side of Albany Highway between Bush Road and 206 Albany Highway.
  • Continued retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continued pavement widening on the western side of Albany Highway between Oakway Drive and Knights Road.
  • Continued vehicle crossing and footpath works on the eastern side of Albany Highway between Knights Road and Rosedale Road.
  • Started drainage work at the Albany Highway / Princeton Parade intersection.
  • Completed removal of the kerb and channel between 419 Albany Highway and Oaklands Road.
  • Started pavement excavation between the Casa Bella Apartments and Bass Road.
  • Completed top soiling around the Bass Road intersection.
  • Poured footpaths and a driveway on both corners of Bass Road.
  • Completed tree removal between Oaklands Road and Eastbourne Road.
  • Completed footpath and kerb and channel removal between Oaklands Road and Eastbourne Road.
  • Started topsoil stripping and installing service ducts between Oaklands Road and Eastbourne Road.
  • Continued embankment fill on the southern and northern sides of Days Bridge.
  • Commenced piling for the south abutment of Days Bridge.
  • Continued earthworks, pavement widening and footpath works between the Presbyterian Church and Albany Expressway.
Next week we will
  • Continue retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • New kerb and channel on the western side of Albany Highway between Rothwell Avenue and Schnapper Rock Road.
  • New kerb and channel on the western side of Albany Highway between Oakway Drive and Albany Junior High School.
  • Continue pavement widening on the western side of Albany Highway between Oakway Drive and Knights Road.
  • Continue vehicle crossing and footpath works on the eastern side of Albany Highway between Knights Road and Rosedale Road.
  • Continue drainage work at the Albany Highway/Princeton Parade intersection.
  • Continue pavement excavation between 419 Albany Highway and Oaklands Road.
  • Continue stripping topsoil and installing service ducts between Oaklands Road and Eastbourne Road.
  • Begin earthworks, pavement widening and footpath works between Wharf Road and Days Bridge.
  • Continue the embankment fill on the north side of Days Bridge.
  • Continue piling for Days Bridge.
  • Continue earthworks, pavement widening, pouring driveways and footpath works between the Presbyterian Church and Albany Expressway.
Night works
  • Road repairs and line marking as required.
  • Road stabilisation on the eastern side of Albany Highway between the Presbyterian Church and Albany Expressway Wednesday and Thursday nights, weather permitting.
Looking ahead

We plan to:

  • Re-open Schnapper Rock Road North in its final configuration in late February.
  • Switch traffic to the eastern side of Albany Highway by Settlers Village in late February.
  • Complete all major works between Bush Road and Rosedale Road in early March.
  • Install the new Days Bridge beam sections in early March.
  • Complete all main drainage lines for the project in early March.

15 January 

This week we
  • Continued retaining wall, footpath and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive, with drainage works commencing between Bush Rd and Rothwell Ave.
  • Continued pavement widening on the western side of Albany Highway between Oakway Drive and Knights Road.
  • Continued vehicle crossing and footpath works on the eastern side of Albany Highway between Rosedale Road and Knights Road.
  • Poured the footpath and cycle path on both corners of Bass Road.
  • Setup fencing between Eastbourne Road and Oaklands Road.
  • Removed trees between Eastbourne Road and Oaklands Road.
  • Removed footpath and kerb and channel between Eastbourne Road and Oaklands Road.
  • Continued embankment fill for the south side of Days Bridge.
  • Continued earthworks, pavement widening and footpath works between the Presbyterian Church and Albany Expressway.
Next week we will
  • Continue retaining wall, footpath, drainage and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive, including kerb and channel prep between Bush Rd and Rothwell Ave.
  • Continue pavement widening on the western side of Albany Highway between Oakway Drive and Knights Road.
  • Continue vehicle crossing and footpath works on the eastern side of Albany Highway between Rosedale Road and Knights Road.
  • Pour the driveway at 2 Bass Road.
  • Remove footpath and kerb and channel between Oaklands Road and Princeton Parade.
  • Strip topsoil and commence installing ducting between Eastbourne Road and Oaklands Road.
  • Continue the embankment fill for the south side of Days Bridge.
  • Start the embankment fill for the north side of Days Bridge.
  • Continue earthworks, pavement widening and footpath works between the Presbyterian Church and Albany Expressway.
Night works
  • Road repairs and line marking as required.
Looking ahead we plan to
  • Re-open Schnapper Rock Rd North in its final configuration in early February.
  • Switch traffic to the eastern side of Albany Highway by Settlers Village in late February.
  • Complete all major works between Bush Road and Rosedale Rd in early March.
  • Install the new Days Bridge beam sections in early March.
  • Complete all main drainage lines for the project in early March.

8 January

This week we
  • Continued pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.
  • Continued prepping the footpath on the north corner of Bass Road.
  • Setup fencing between Eastbourne Road and Oaklands Road
  • Commenced removing footpath and kerb and channel between Eastbourne Road and Oaklands Road.
  • Continued with the retaining wall north of Wharf Road.
  • Commenced embankment preparation for the south side of Days Bridge.
  • Continued earthworks, pavement widening and footpath works between the Presbyterian Church and Albany Expressway.
Next week we will
  • Continue retaining wall, footpath and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive
  • Begin the embankment fill for the south side of Days Bridge
  • Continue footpath and pavement widening on the western side of Albany Highway between Oakway Drive and Knights Road .
  • Continue vehicle crossing and footpath works on the eastern side of Albany Highway between Rosedale Road and Knights Road.
  • Continue prepping and pouring the footpath/cycle path on both sides of Bass Road.
  • Setup fencing between Oaklands Road and Princeton Parade.
  • Remove footpath and kerb and channel between Oaklands Road and Princeton Parade.
  • Remove trees and vegetation between Eastbourne Road and Oaklands Road.
  • Continue removing footpath and kerb and channel between Eastbourne Road and Oaklands Road.
  • Continue earthworks, pavement widening and footpath works between the Presbyterian Church and Albany Expressway.
Night works
  • Road repairs and line marking as required.
Looking ahead

We plan to:

  • Re-open Schnapper Rock Rd North in its final configuration in early February.
  • Complete all major works between Bush Road and Rosedale Rd in early March.
  • Install the new Days Bridge beam sections in early March.
  • Complete all main drainage lines for the project in early March.

2015


18 December


The Albany Highway work teams will suspend work for Christmas on Wednesday 23 December and a smaller crew will recommence work on Tuesday 5 January 2016. All works will resume by 12 January 2016.

This week we

Continued retaining wall, footpath and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.

Continued pavement, vehicle crossing and footpath works on the eastern side of Albany Highway between Rosedale Road and Knights Road.

Continued footpath and pavement widening works on the western side of Albany Highway between Oakway Drive and Knights Road.

Carried out pavement stabilising and chip sealing works on the western side of Albany Highway between Schnapper Rock Road and Oakway Drive.

Completed concreting footpath and driveways south of Bass Road.

Completed pavement widening works to the north and south of Bass Road.

Continued preparing footpath and driveways for concreting on the north side of Bass Road.

Completed pavement construction at the Wharf Road intersection.

Completed topsoil to berms between Wharf Road and Bass Road.

Continued pavement construction at the Bass Road intersection.

Started top soiling to berms between Bass Road and 416 Albany Highway.

Continued with the old Days Bridge demolition.

Continued with the retaining wall south of Days Bridge.

Began the retaining wall north of Wharf Road.

Continued with pavement construction from the Presbyterian Church to the Albany Expressway.

Continued pavement widening and installation of kerb and channel opposite Settlers Village heading towards the Albany Expressway.

Next week we will

Continue retaining wall, footpath and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive. 

Continue pavement, vehicle crossing and footpath works on the eastern side of Albany Highway between Rosedale Road and Knights Road.

Continue footpath and pavement widening on the western side of Albany Highway between Oakway Drive and Knights Road.

Continue concreting footpaths north of Bass Road. 

Start establishing a new works site on the eastern side of Albany Highway between the Wharf Road intersection and Princeton Parade. 

Start tree clearance work between Eastbourne Road and Oaklands Road.

Continue retaining wall construction south of Days Bridge.

Continue with the old Days Bridge demolition.

Continue earthworks, pavement widening and footpath works between the Presbyterian Church and Albany Expressway.

Night work

Over the coming week we plan to carry out pavement works at the Bass Road intersection, weather permitting.

On Sunday 20 December we plan to install new line marking and switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road, weather permitting.

Looking ahead

On Saturday 19 December, from 6am, weather permitting; we will be pouring concrete within the Bass Rd Intersection. Traffic management will be in place, however all roads will remain open to traffic.

Complete the retaining wall for the slip lane 234 – 246 Albany Highway by Christmas.

Complete the demolition of the old Days Bridge by Christmas.


11 December


This week we

Completed paving from Rosedale Road to Knights Road on the eastern side.

Continued retaining wall, footpath and pavement widening works on the western side of Albany Highway between Bush Road and Oakway Drive.

Continued vehicle crossing and footpath works on the eastern side of the road from Rosedale Road to Knights Road.

Continued preparing and concreting footpath and driveways south of Bass Road.

Completed driveways at 418 Albany Highway.

Continued top soiling berm areas between Wharf Road and Bass Road.

Completed pavement widening works to the north and south of Bass Road.

Continued pavement construction at the Bass Road and Wharf Road intersections.

Continued preparing footpath and driveways for concreting on the north side of Bass Road.

Continued retaining wall block installation south of Days Bridge.

Continued demolition works at the original Days Bridge.

Continued pavement widening and preparation for kerb and channel outside the Presbyterian Church and cemetery heading towards the expressway.

Started timber retaining wall installation opposite Settlers Village.

Next week we will

Continue retaining wall, footpath and pavement widening works on the western side of the road between Bush Road and Oakway Drive.

Continue pavement, vehicle crossing and footpath works on the eastern side of the road from Rosedale Road to Knights Road.

Continue concreting footpaths north and south of Bass Road.

Continue preparing footpaths for concreting on the north side of Bass Road.

Continue top soiling to berm areas between Wharf Road and Bass Road.

Continue pavement construction at the Bass Road and Wharf Road intersections.

Start top soiling to berm areas between Bass Road and 416 Albany Highway.

Continue retaining wall construction south of Days Bridge.

Continue demolition works at the original Days Bridge.

Continue earthworks, pavement widening and footpath works between the Presbyterian Church and Albany Expressway.

Night works

Over the coming week we plan to carry out pavement works at the Wharf Road and Bass Road intersections.

Looking ahead

On Saturday 12 December, (weather permitting) we will be pouring concrete within the Bass Road Intersection. Traffic management and detours will be in place, however all roads will remain open to traffic.

Complete the retaining wall for the slip lane 234 – 246 Albany Highway by Christmas.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by mid-December.

Complete the demolition of the old Days Bridge by Christmas.


4 December


This week we

Continued retaining wall, footpath and pavement widening works on the western side of the road between Bush Road and Oakway Drive.

Continued pavement and footpath works on the eastern side of the highway from Rosedale Road to Knights Road, continuing with the concrete pours for the vehicle crossings in this section and continuing preparation for footpaths.

Started constructing the centre median island between Schnapper Rock Road and Oakway Drive.

Carried out maintenance surfacing work from Oakway Drive to Rothwell Avenue.

Carried out pavement works opposite Appleby Road.

Milled the eastern side of Albany Highway between Rosedale Road and Knights Road.

Carried out drainage works outside 265 Albany Highway.

Continued preparing footpath and driveways for concreting south of Bass Road.

Concreted driveways at 418 Albany Highway.

Continued top soiling berm areas between Wharf Road and Bass Road.

Continued pavement widening works to the north and south of Bass Road.

Continued pavement construction at the Bass Road and Wharf Road intersections.

Started preparing footpath and driveways for concreting on the north side of Bass Road.

Poured kerb and channel on the north side of Bass Road and Wharf Road.

Continued retaining wall block installation south of Days Bridge.

Continued demolition works at the original Days Bridge including beam lifts of the central span.

Continued pavement widening and preparation for kerb and channel outside the Presbyterian Church and cemetery heading towards the expressway.

Next week we will

Continue retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue pavement, vehicle crossing and footpath works on the eastern side of the road from Rosedale Road to Knights Road.

Continue preparing footpath for concreting south of Bass Road.

Continue preparing footpath and driveways for concreting on north side of Bass Road.

Continue top soiling to berm areas between Wharf Road and Bass Road.

Continue pavement construction at the Bass Road and Wharf Road intersections.

Continue retaining wall construction south of Days Bridge.

Continue demolition works at the original Days Bridge.

Continue earthworks, pavement widening and footpath works between the Presbyterian Church and Albany Expressway.

Night works

Over the coming week we plan to carry out pavement works at the Wharf Road and Bass Road intersections.

From Sunday 6 to Tuesday 8 December, we will pave from Rosedale Road to Knights Road on the eastern side.

Road repairs and line marking as required – weather dependent.

Looking ahead

Complete the retaining wall for the slip lane 234–246 Albany Highway by Christmas.

Complete the footpath and pavement works on the eastern side of the highway between Knights Road and Rosedale Road by Christmas.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by mid-December.

Complete the demolition of the old Days Bridge by Christmas.


27 November


This week we 

Continued retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continued pavement and footpath works on the eastern side of the highway from Rosedale Rd to Knights Rd, continuing with the concrete pours for the vehicle crossings in this section and starting preparing for footpaths.

Completed the footpath reinstatement on Rosedale Rd and down Princeton Pde.

Continued preparing footpath and driveways for concreting south of Bass Rd.

Concreted driveways at 418 Albany Highway.

Continued top soiling to berm areas between Wharf Rd and Bass Rd.

Reinstated the berm on the north side of Bass Rd.

Continued pavement widening works to the north and south of Bass Rd.

Continued retaining wall footing installation south of Days Bridge.

Continued demolition works at the original Days Bridge.

Continued pavement widening and preparation for kerb and channel outside the Presbyterian Church and cemetery.

Next week we will

Continue retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue pavement, vehicle crossing and footpath works on the eastern side of the road from Rosedale Rd to Knights Rd.

Continue footpath construction south of Bass Rd.

Install new kerb and channel on the north sides of Bass Rd and Wharf Rd.

Continue retaining wall construction south of Days Bridge.

Continue demolition works at the original Days Bridge.

Continue earthworks, pavement widening and footpath works between the Presbyterian Church and Albany Expressway.

Night works

On Monday 30 November and Tuesday 1 December we plan to excavate and lay a concrete sub base at three locations on Albany Highway, near Rosedale Road, near Appleby Road and at Knights Road.

On Wednesday 2 December and Thursday 3 December we plan to lay asphalt from Rothwell Avenue to Oakway Drive on the eastern side of the road.

Over two weeks from Sunday 29th November we plan to carry out pavement works at the Wharf and Bass Intersections.

Road repairs and line marking as required – weather dependent.

Looking ahead

Complete the retaining wall for the slip lane 234 – 246 Albany Highway by Christmas.

Complete the footpath and pavement works on the eastern side of the highway between Knights Road and Rosedale Road by Christmas.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by mid-December.

Complete the demolition of the old Days Bridge by Christmas.


20 November


This week we

Continued retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continued pavement and footpath works on the eastern side of the road from Rosedale Rd south towards Oakway Dr having started the concrete pours for the vehicle crossings in this section.

Continued preparing footpath for concreting south of Bass Rd.

Continued footpath preparation and concreting between Wharf Rd and Bass Rd.

Carried out sealing to stabilised area between Wharf Rd and Bass Rd.

Continued retaining wall footing preparation south of Days Bridge.

Continued demolition works at the original Days Bridge.

Continued stormwater works south of Days Bridge and between the Presbyterian Church and the Albany Expressway.

Continued earthworks for pavement widening and footpaths outside the Presbyterian Church and cemetery.

 Next week we will

Continue retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue pavement vehicle crossing and footpath works on the eastern side of the road from Rosedale Rd south towards Oakway Dr.

Continue footpath and driveway construction south of Bass Rd.

Install new kerb and channel on the north side of Bass Rd and Wharf Rd.

Continue construction and concreting of footpaths between Wharf Rd and Bass Rd.

Begin pavement widening to the north side of Wharf Rd.

Continue demolition works at the original Days Bridge.

Continue stormwater works between Wharf Rd and Days Bridge.

Continue earthworks, pavement widening and footpath works outside the Presbyterian Church and cemetery.

 Night works

Road repairs and line marking as required – weather dependent.

 Looking ahead

Complete the retaining wall for the slip lane 234–246 Albany Highway by Christmas.

Complete the footpath and pavement works on the eastern side of the highway between Knights Road and Rosedale Road by Christmas.

Complete the demolition of the old Days Bridge by Christmas.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by December.


13 November


This week we

Continued retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continued pavement and footpath works on the eastern side of the road from Rosedale Rd south towards Oakway Dr having completed the kerb and channel works this week.

Continued preparing footpath for concreting south of Bass Rd.

Continued pavement widening works on Bass Rd.

Continued footpath preparation between Wharf Rd and Bass Rd.

Continued final driveway shape preparation and concreting between Wharf Rd and Bass Rd.

Carried out pavement stabilisation between Wharf Rd and Bass Rd.

Continued retaining wall preparation south of Days Bridge.

Continued demolition works at the original Days Bridge.

Continued stormwater works south of Days Bridge and between the Presbyterian Church and the Albany Expressway.

Continued earthworks for pavement widening and footpaths outside the Presbyterian Church and cemetery.

Next week we will

Continue retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue pavement and footpath works on the eastern side of the road from Rosedale Rd south towards Oakway Dr including the installation of new vehicle crossings between Rosedale Rd and Knights Rd.

Continue footpath and driveway construction south of Bass Rd.

Continue pavement widening works south of Bass Rd.

Install new kerb and channel on the north side of Bass Rd and Wharf Rd.

Continue pavement widening works on Bass Rd.

Continue construction and concreting of footpaths between Wharf Rd and Bass Rd.

Begin pavement widening to the north side of Wharf Rd.

Continue demolition works at the original Days Bridge.

Continue stormwater works between the Presbyterian Church and the Albany Expressway.

Continue earthworks for pavement widening and footpaths outside the Presbyterian Church and cemetery.

Night works

Road repairs and line marking as required – weather dependent.

Looking ahead

Complete the retaining wall for the slip lane 234–246 Albany Highway by Christmas.

Complete the footpath and pavement works on the eastern side of the highway between Knights Road and Rosedale Road by Christmas.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by December.

Complete the demolition of the old Days Bridge in November.


6 November


The AT contractor for the Albany Highway project, Fulton Hogan has now spent 1 year on site so far. The project is significantly ahead of the 2.5 year programme and the contractor hopes to deliver the project by late 2016.

This week we

Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continued pavement and footpath works on the eastern side of the road from Rosedale Rd south towards Oakway Dr.

Completed joining service ducts on Albany Highway between Wentworth Park and Princeton Parade.

Completed the installation of the manholes on the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Installed new kerb and channel south of Bass Rd .

Continued pavement widening works on Bass Rd.

Continued footpath preparation between Wharf Rd and Bass Rd.

Continued final driveway shape preparation and concreting between Wharf Rd and Bass Rd.

Continued earthworks between Wharf Rd and Days Bridge.

Continued demolition works at the original Days Bridge.

Continued stormwater works between Presbyterian Church and the Albany Expressway.

Commenced earthworks for pavement widening and footpath outside the Presbyterian Church and cemetery.

Next week we will

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue pavement, drainage and footpath works on the eastern side of the road from Rosedale Rd south towards Oakway Dr including the installation of kerb and channel between Rosedale Rd and Knights Rd.

Continue footpath and driveway construction south of Bass Rd.

Continue pavement widening works south of Bass Rd.

Install new kerb and channel on the north side of Bass Rd.

Continue pavement widening works on Bass Rd.

Continue construction and concreting of driveways between Wharf Rd and Bass Rd.

Begin pavement widening to the north side of Wharf Rd.

Continue demolition works at the original Days Bridge.

Continue stormwater works between Presbyterian Church and the Albany Expressway.

Continue earthworks for pavement widening and footpaths outside the Presbyterian Church and cemetery.

Night works

Road repairs as required – weather dependent.

Looking ahead

Complete the demolition of the old Days Bridge in November.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by December.

Complete the retaining wall for the slip lane 234 – 246 Albany Highway by Christmas.


30 October


This week we

Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continued subsoil drainage and pavement works on the eastern side of the road from Rosedale Rd south towards Oakway Dr.

Completed drilling for services on Albany Highway between Wentworth Park and Princeton Parade on both sides of the highway.

Continued the installation of the manholes on the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continued pavement widening works south of Bass Rd.

Continued pavement widening works on Bass Rd.

Continued footpath preparation between Wharf Rd and Bass Rd.

Continued final driveway shape preparation and concreting between Wharf Rd and Bass Rd.

Continued earthworks between Wharf Rd and Days Bridge.

Continued demolition works at the original Days Bridge.

Continued stormwater works between Days Bridge and the Albany Expressway.

Next week we will

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue pavement, drainage and footpath works on the eastern side of the road from Rosedale Rd south towards Oakway Dr.

Install new kerb and channel between Schnapper Rock Rd North and Oakway Dr.

Complete the installation of the manholes on the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continue pavement widening works south of Bass Rd.

Install new kerb and channel south of Bass Rd.

Continue pavement widening works on Bass Rd.

Continue construction and concreting of driveways between Wharf Rd and Bass Rd.

Continue earthworks between Wharf Rd and Days Bridge.

Continue demolition works at the original Days Bridge.

Continue stormwater works between Days Bridge and the Albany Expressway.

Commence earthworks for pavement widening and footpath outside the Presbyterian church and cemetery.

Night works

Road repairs as required.

Drainage works at Bass Rd and Wharf Rd are scheduled to take place over the next 2 weeks:

  • Sunday or Monday to Thursday, 7pm to 5am, depending on the weather.

Looking ahead

Complete the demolition of the old Days Bridge in November.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by December.

Complete the retaining wall for the slip lane 234 – 246 Albany Highway by Christmas.


23 October 


This week we

Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continued work on the eastern side of the road from Rosedale Rd south towards Knights Rd, stripping topsoil, removing old concrete and carrying out service investigations and pavement works.

Continued drilling for services on Albany Highway between Wentworth Park and Princeton Parade on both sides of the highway.

Completed drilling the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade and started the manhole installation on this line.

Continued service connections at the Bass Rd intersection.

Continued catch pit installation south of Bass Rd.

Continued pavement widening works south of Bass Rd.

Continued final driveway shape preparation and concreting between Wharf Rd and Bass Rd.

Continued site clearance and earthworks south of Days Bridge.

Continued demolition works at the original Days Bridge.

Continued stormwater works between Days Bridge and the Albany Expressway including laying a stormwater line across the Albany Senior High School South entrance.

Next week we will

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue pavement, drainage and footpath works on the eastern side of the road from Rosedale Rd south towards Oakway Dr.

Continued installing manholes on the directionally drilled stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continue pavement widening works south of Bass Rd.

Continue pavement widening works between Bass Rd and Wharf Rd.

Continue construction and concreting of driveways between Wharf Rd and Bass Rd.

Continue earthworks north of Wharf Rd.

Continue demolition works at the original Days Bridge.

Continue stormwater works between Days Bridge and the Albany Expressway.

Night Works

Road repairs as required.

Looking ahead

Complete the demolition of the old Days Bridge in November.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by December.

Complete the retaining wall for the slip lane 234 – 246 Albany Highway by Christmas.


16 October


This week we

Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Completed topsoil works between Oakway Dr and Oak Manor Dr, shifted all the traffic to the western side of the road and opened the new footpaths to pedestrians and cyclists.

Continued work on the eastern side of the road from Rosedale Rd south towards Knights Rd, stripping topsoil, removing old concrete and carrying out service investigations and pavement works.

Continued drilling services on Albany Highway between Wentworth Park and Princeton Parade on both sides of the highway.

Continue drilling the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continued service connections on the southern corner of Bass Rd.

Continued catchpit installation south of Bass Rd.

Continued pavement widening works between Bass Rd and Wharf Rd.

Commenced earthworks for pavement widening south of Bass Rd.

Continued final driveway shape preparation between Wharf Rd and Bass Rd.

Continued excavation around services in preparation work for a retaining wall north of Wharf Rd.

Continued demolition works at the original Days Bridge.

Continued stormwater works between Days Bridge and the Albany Expressway.

Next week we will

On Saturday 17 and Sunday 18 Vector will be working at the Bass Rd Intersection installing a new power pole in preparation for undergrounding a section of the overhead power lines. They will advise residents and businesses directly if there will be any power outage.

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue works on the eastern side of the road from Rosedale Rd south towards Knights Rd.

Complete drilling services on Albany Highway between Wentworth Park and Princeton Parade.

Complete directional drilling of the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade, and start installing manholes on this new line.

Continue pavement widening works south of Bass Rd.

Continue pavement widening works between Bass Rd and Wharf Rd.

Continue construction and concreting of driveways between Wharf Rd and Bass Rd.

Continue site clearance and service duct installation works north of Wharf Rd.

Continue demolition works at the original Days Bridge.

Lay a stormwater line across the southern entrance to Albany Senior High School. Vehicle access will be maintained with one lane in each direction.

Continue stormwater works between Days Bridge and the Albany Expressway.

Night Works

Line marking works as required throughout the site.

Looking ahead

Complete the demolition of the old Days Bridge by November.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by December.

Complete the retaining wall for the slip lane 234 – 246 Albany Highway by Christmas.


9 October

This week we


Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Completed pouring the concrete paths between Oakway Dr and Oak Manor Dr.

Completed pavement works as far as we are going at this stage towards the Oakway Dr intersection.

Continued work on the eastern side of the road from Rosedale Rd south towards Knights Rd, stripping topsoil and carrying out service investigations.

Completed the concrete path and top soiling between Rosedale Rd and Wentworth Park, excluding the corner section at Wentworth.

Continued drilling services on Albany Highway between Wentworth Park and Princeton Parade on both sides of the highway.

Complete the next section of drainage line works past Kristin School Gate 2.

Established the drilling rig for the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continued services connections on Southern corner of Bass Rd.

Installed tree planting pits south of Summerfield Lane.

Continued pavement widening works between Bass Rd and Wharf Rd.

Completed kerb installation between Wharf and Bass Rd.

Continued excavation around services in preparation work for a retaining wall north of Wharf Rd.

Continued demolition works at the original Days Bridge.

Continued stormwater works between Days Bridge and the Albany Expressway.

Continued retaining wall works outside the cemetery.

Continued clearing works between the cemetery and Albany Expressway.

Completed vegetation clearance between Wharf Rd and Days Bridge.

Next week we will

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Spreading topsoil between Oakway Dr and Oak Manor Dr and shift all the traffic to the western side of the road and open the new footpaths to pedestrians.

Continue works on the eastern side of the road from Rosedale Rd south towards Knights Rd.

Continue drilling services on Albany Highway between Wentworth Park and Princeton Parade.

Commence directional drilling of the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Begin earthworks for pavement widening south of Bass Rd.

Continue pavement widening works between Bass Rd and Wharf Rd.

Continue construction of driveways between Wharf Rd and Bass Rd.

Continued excavation around services in preparation work for a retaining wall north of Wharf Rd.

Continue demolition works at the original Days Bridge.

Continue stormwater works between Days Bridge and the Albany Expressway.

Continued clearing works between the cemetery and Albany Expressway.

Night Works

Line marking works as required throughout the site.

Looking ahead

Complete the demolition of the old Days Bridge by November.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by December.

Complete the retaining wall for the slip lane 234 – 246 Albany Highway by Christmas.


2 October


This week we

Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Commenced pouring the concrete paths between Oakway Dr and Oak Manor Dr.

Continued pavement works towards the Oakway Dr intersection.

Completed tree pit installation between Appleby Rd and Oak Manor Dr.

Completed the concrete paths and top soiling between Oak Manor Dr and Rosedale Rd on the western side and this area is now open for pedestrians.

Commenced work on the eastern side of the road from Rosedale Rd south towards Knights Rd, stripping topsoil and carrying out service investigations.

Continued pouring the concrete path and top soiling between Rosedale Rd and Wentworth Park.

Continued drilling services on Albany Highway between Wentworth Park and Princeton Parade on both sides of the highway.

Recommenced drainage line works between Kristin School and Princeton Parade.

Completed service investigations for the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade ready for the directional drilling rig to set up.

Completed watermain connection works at the Bass Rd intersection.

Installed tree planting pits south of Bass Rd.

Continued pavement widening works between Bass Rd and Wharf Rd.

Prepared for forming kerbs between Bass Rd and Wharf Rd.

Removed redundant light poles on both sides of Days Bridge.

Commenced excavation and preparation work for a retaining wall north of Wharf Rd.

Continued demolition works at the original Days Bridge.

Continued stormwater works between Days Bridge and the Albany Expressway.

Completed moving of the power and telecom cables on the west side of Days Bridge.

Next week we will

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue pouring concrete paths between Oakway Dr and Oak Manor Dr.

Continue pavement works towards the Oakway Dr intersection.

Complete the concrete paths and top soiling between Appleby Rd and Oak Manor Dr.

Continue works on the eastern side of the road from Rosedale Rd south towards Knights Rd.

Continue drilling services on Albany Highway between Wentworth Park and Princeton Parade.

Continue drainage line works between Kristin School and Princeton Parade.

Start directionally drilling the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Complete service ducting installation to the south side of the Bass Rd intersection.

Continue earthworks for pavement widening between Wharf Rd and Bass Rd.

Begin construction of the retaining wall north of Wharf Rd.

Commence vegetation clearance between Wharf Rd and Days Bridge.

Continue demolition works at the original Days Bridge.

Continue stormwater works between Days Bridge and the Albany Expressway.

Night Works

Line marking works as required throughout the site.

Looking ahead

Complete the demolition of the old Days Bridge by November.

Switch traffic to the western side of Albany Highway between Princeton Parade and Wharf Road by December.

Complete the retaining wall for the slip lane 234 – 246 Albany Highway by Christmas.


25 September


This week we

Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Finished footpath preparation works between Oakway Dr and Appleby Rd ready for concrete to be poured.

Finished footpath preparation works between Appleby Rd and Oak Manor Dr ready for concrete to be poured and started the installation of tree pits.

Completed paving of the western side of the new road layout between Oak Manor Dr and Oakway Dr.

Continued pouring the concrete paths between Oak Manor Dr and Rosedale Rd.

Continued pouring the concrete path between Rosedale Rd and Wentworth Park.

Continued service investigations and started drilling for services on Albany Highway near Princeton Parade.

Continued service investigations for the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continued watermain connection works at the Bass Rd intersection.

Continued temporary footpath preparation south of Bass Rd.

Continued pavement widening works between Bass Rd and Wharf Rd.

Prepared for kerbing between Wharf Rd and Summerfield Lane.

Removed redundant barriers on both sides of Days Bridge.

Commenced excavation and preparation work for a retaining wall north of Wharf Rd.

Commenced demolition preparation works at the original Days Bridge.

Commenced stormwater works between Days Bridge and the Albany Expressway.

Switched traffic onto Stage 1 of the new Days Bridge.

Moved pedestrians to alternative access past the construction area either side of Days Bridge.

Next week we will

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr including pouring the first 3 vehicle crossings in this section.

Continue pouring concrete paths between Oakway Dr and Rosedale Rd on the western side of the road.

Commence service investigations and setup works on the eastern side of Albany Highway between Rosedale Rd and Knights Rd.

Continue directional drilling for services on Albany Highway.

Complete service investigations and start setting up the drilling rig for the stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Complete watermain connection works at the Bass Rd intersection.

Continue earthworks for pavement widening between Wharf and Bass Rd.

Continue footpath construction south of Bass Rd and move pedestrians to a temporary path.

Commence vegetation clearance between Wharf Rd and Days Bridge.

Continue demolition works at the original Days Bridge.

Continue stormwater works between Days Bridge and the Albany Expressway.

Begin footpath preparation north of the Albany Presbyterian Church

Night works

From 8pm Saturday 26 to 11am Sunday 27 September, Vector plans to relocate services to a temporary platform on the western side of Days Bridge. This will also include working on the transformer and power poles on the northwest corner of Bass Rd. Please note that works are weather dependent and will roll to the next fine weekend if delayed.

On Monday 28 September, we will be line marking the road at the Appleby and Oak Manor Drive intersections.

Looking ahead

Between Oakway Dr and Rosedale Rd, we are planning to switch traffic onto the newly built western side of Albany Highway in early October.


18 September

This week we

Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Closed the Schnapper Rock Rd North vehicle access to Albany Highway to allow construction works to occur. Detours are in place utilising the signalised intersections at Bush Rd/Schnapper Rock Rd South and Oakway Drive. Pedestrian access will remain open. The intersection will reopen in its final configuration in March 2016 with vehicles restricted to left turn in and left turn out.

Continued footpath preparation works between Oakway Dr and Appleby Rd ready for concrete to be poured.

Continued paving of the western side of the new road layout between Oak Manor Dr and Oakway Dr.

Commenced the pouring the concrete paths between Oak Manor Dr and Rosedale Rd.

Continued the footpath preparation between Rosedale Rd and Wentworth Park.

Commenced setup and service investigations in preparation for drilling a common service trench on Albany Highway and a stormwater line. between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continued watermain connection works at the Bass Rd intersection.

Continued temporary footpath preparation south of Bass Rd.

Completed stage 1 of pavement construction between Eastbourne Rd and the Albany Presbyterian Church.

Continued berm reinstatement works between Eastbourne Rd and the Albany Presbyterian Church.

Completed temporary footpath construction to both sides of Days Bridge.

Installed a guardrail south of Days Bridge.

Completed pram crossings at the Albany Senior High School southern entrance.

Next week we will

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue pouring concrete paths between Oakway Dr and Rosedale Rd.

Commence service investigations and setup works on the eastern side of Albany Highway between Rosedale Rd and Knights Rd.

Pour the footpaths between Rosedale Rd and Wentworth Park.

Continue service investigations in preparation for drilling a common services trench on Albany Highway and a stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continue watermain works at the Bass Rd intersection.

Continue earthworks for pavement widening between Wharf and Bass Rd.

Continue footpath construction south of Bass Rd.

Open the new footpath detour route between the Eastbourne/Wharf intersection and the north side of Days Bridge.

Commence demolition preparation works at the original Days Bridge.

Begin footpath preparation north of the Albany Presbyterian Church.

Night Works

From 8pm,Saturday 19 to 11am, Sunday 20 September, Vector plans to be relocating services to a temporary platform on the western side of Days Bridge. This will also include working on the transformer and power poles on the northwest corner of Bass Rd.

On Sunday 20 September we plan to switch traffic and pedestrians onto the newly built eastern side of Albany Highway between Eastbourne Rd and the Albany Presbyterian Church. Pedestrian detours will be in place for approximately 6 months. Following the traffic switch we will clear vegetation along the Highway by Widdison Pl and Oaklands Rd, and begin the demolition of the original Days Bridge.

Please note that all works are weather dependent and will roll to the next fine night if delayed.

Looking ahead

Between Oakway Dr and Rosedale Rd we are planning to switch traffic onto the newly built western side of Albany Highway in early October. 


11 September


Albany Highway north zone progress

As this is a sizeable project, the area has been broken into five work zones, to allow Fulton Hogan to more easily manage construction and traffic control, and minimise disturbances to the local community. The following updates work across the five zones and overviews work scheduled to take place on the highway over the next few months.

Albany Highway north zone progress map

Zone 1

Eastern-side works largely completed with pedestrian access opened on that side from Oakway Drive to Bush Road

Road carriageway construction underway on western side

Several retaining walls on the western side to be constructed in the lead up to Christmas to allow the remaining road widening to be completed in early 2016.

Zone 2

Undergrounding of services and stormwater construction works due for completion this month.

New footpaths and cycleways on western side due for completion in October.

Road carriageway work has commenced and the western half of the road is programmed for completion in September.

Zone 3

Drainage works, including a drilled drainage line, are due to start down Princeton Parade shortly.

New service ducting is programmed for installation before the end of 2015 with footpath and road widening works programmed for the summer of 2016.

Zone 4

Pavement widening works due to begin through the western side of the carriageway followed by construction of footpaths and berms.

Upon completion of the western side, the current traffic lanes will be switched and construction works will occupy the eastern side of the road by the end of the year.

Zone 5

Stage 1 Days Bridge construction works now complete with a traffic switch scheduled for this month.

Deconstruction of the “old” Days Bridge will begin after the traffic switch followed by construction of Stage 2 (western side) of the “new” bridge.

Construction of the retaining walls between Wharf Rd and Days Bridge along with stormwater.


Father and son promote road safety

Father And SonAlbany Highway construction worker Nick Cain and his young son Ryder have become the focus of the road safety message during the major works there. The two, who live on the North Shore, feature on this road safety sign encouraging motorists to keep speed down through the construction zone.

Police too are urging motorists to abide by the current 30kph speed limit along the Highway, having already issued hundreds of tickets for incidents of high-risk driving through the work. 

“Poor driving behaviour is putting the safety of road-workers and the public at risk,” says Senior Sergeant Brett Campbell-Howard of Waitemata police.

“It only takes one mishap at high speed and someone could be injured or killed. The people working here are simply earning a living and they shouldn’t be put at unnecessary risk just because someone is running late, is annoyed at the road works, or simply chooses to ignore the lowered speed limit”.

“Recently, we issued 39 speed infringement notices in just two hours in that area. We caught someone who was driving at 79kph through
the 30kph zone”.


10 September


This week we

Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continued streetlight installation footpath preparation works between Oakway Dr and Rosedale Rd.

Continued pavement works through the Appleby Rd intersection.

Continued kerb and channel works at Oak Manor Dr and Appleby Rd intersections.

Commenced service investigations in preparation for drilling a stormwater line between  382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continued watermain connection works at the Bass Rd intersection.

Completed the new watermain and hydrant connection between Summerfield and Bass Rd.

Continued temporary footpath preparation between Wharf Rd and Bass Rd.

Continued pavement construction between Eastbourne Rd and the Albany Presbyterian Church.

Continued berm reinstatement works between Eastbourne Rd and Days Bridge.

 Next week we will

Oakway Drive Closure AlbanyContinue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Close the Schnapper Rock Rd North vehicle access to Albany Highway (see map) to allow construction works to occur.  Detours will be in place utilising the signalised intersections at Bush Rd/Schnapper Rock Rd South and Oakway Drive. Pedestrian access will remain open. The intersection will reopen in its final configuration in March 2016 with vehicles restricted to left turn in and left turn out.

Complete footpath preparation works between Oakway Dr and Appleby Rd ready for concrete to be poured.

Continue the paving of the western side of the new road layout between Oak Manor Dr and Oakway Dr.

Complete footpath works between Oak Manor Dr and Rosedale Rd.

Complete the footpath preparation between Rosedale Rd and Wentworth Park.

Continue setup and service investigations in preparation for drilling a stormwater line between  382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continue watermain works at the Bass Rd intersection.

Continue earthworks for pavement widening between Wharf and Bass Rd.

Continue footpath construction south of Bass Rd.

Continue pavement preparation between Eastbourne Road and the Albany Presbyterian Church.

Begin footpath preparation north of the Albany Presbyterian Church.

Night Works

On Tuesday 15 to Thursday 17 September we plan to be paving the western side of Albany Highway between Oak Manor Dr and Oakway Dr and also the Rothwell Ave/Albany Highway intersection.

From 8pm Saturday 12 to 11am, Sunday 13 September, Vector plans to be relocating services to a temporary platform on the western side of Days Bridge. This will also include working on the transformer and power poles on the northwest corner of Bass Rd.

From 2pm Sunday 13 to 5am Monday 14 September we plan to be carrying out stabilisation works between Eastbourne Rd and Days Bridge.

Please note that all works are weather dependent and will roll to the next fine night if delayed.

Looking ahead

At Days Bridge we are planning to switch traffic and pedestrians onto the newly built eastern side of Albany Highway in mid to late September.  Following the traffic switch we will clear vegetation along the highway by Widdison Pl and Oaklands Rd, and begin the demolition of the original Days Bridge.

Between Oakway Dr and Rosedale Rd we are planning to switch traffic onto the newly built western side of Albany Highway at the end of September.


4 September


This week we

Continued drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr. 

Continued footpath preparation works between Oakway Dr and Appleby Rd.

Completed pavement widening works and kerb and channel construction between Appleby Rd and Oak Manor Dr.

Completed pavement works through the Oak Manor Dr intersection under stop/go operations.

Continued footpath preparation works between Oak Manor Dr and Rosedale Rd.

Completed paving operations on the western side of the road between Oak Manor Dr and Rosedale Rd.

Continued watermain connection works at the Bass Rd intersection.

Continued berm reinstatement north of Summerfield Lane.

Continued temporary footpath preparation between Wharf Rd and Bass Rd.

Continued footpath and pavement preparation between Eastbourne Rd and Days Bridge.

Continued pavement preparation between Days Bridge and the Albany Presbyterian Church.

Next week we will

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Complete footpath preparation works between Oakway Dr and Appleby Rd ready for concrete to be poured.

Complete kerb and channel works at Oak Manor Dr and Appleby Rd intersections.

Complete footpath works between Oak Manor Dr and Rosedale Rd.

Continue the footpath preparation between Rosedale Rd and Wentworth Park.

Commence service investigations in preparation for drilling a stormwater line between 382 Albany Highway and the Albany Scenic Reserve in Princeton Parade.

Continue watermain works at the Bass Rd intersection.

Continue footpath preparation and berm reinstatement north of Summerfield Lane.

Continue footpath construction between Eastbourne Rd and Days Bridge.

Continue pavement preparation between Eastbourne Road and the Albany Presbyterian Church.

Night Works

Reinstatement of median islands on Albany Highway by Library Ln.

New hydrant connection and other watermain works between Summerfield Ln and Bass Rd.

Road repair opposite 232 Albany Highway.

Albany Highway Closure September 2015Looking ahead

At Days Bridge we are planning to switch traffic and pedestrians onto the newly built eastern side of Albany Highway in mid to late September (See map).  Following the traffic switch we will clear vegetation along the highway by Widdison Pl and Oaklands Rd, and begin the demolition of the original Days Bridge.

Between Oakway Dr and Rosedale Rd we are planning to switch traffic onto the newly built western side of Albany Highway at the end of September.

On 14 September we plan to close the Schnapper Rock Rd North vehicle access to Albany Highway to allow construction works to occur. Detours will be in place utilising the signalised intersections at Bush Rd/Schnapper Rock Rd South and Oakway Drive. Pedestrian access will remain. open. The intersection will reopen in its final configuration in March 2016 with vehicles restricted to left turn in and left turn out.


28 August 


This week we

Completed vegetation clearing works and commenced drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continued with footpath preparation works between Oak Way Dr and Appleby Rd.

Continued pavement widening works and kerb and channel construction between Appleby Rd and Oak Manor Dr.

Commenced footpath preparation works between Oak Manor Dr and Rosedale Rd.

Continued the footpath preparation between Rosedale Rd and Wentworth Park.

Completed fence construction at Secret Garden childcare south of Bass Rd.

Completed fencing work at the Summerfield Ln retaining wall.

Continued boundary fencing between Summerfield Ln and Bass Rd.

Continued footpath and pavement preparation between Eastbourne Rd and Days Bridge.

Continued watermain connection works at the Bass Rd intersection.

Completed Stage 1 Bridge works at Days Bridge.

Continued berm reinstatement north of Summerfield Lane.

Continued pavement preparation between Days Bridge and the Presbyterian Church.

Next week we will

Continue drainage, retaining wall, footpath and pavement widening works on the western side of the road between Bush Rd and Oakway Dr.

Continue with footpath preparation works between Oak Way Dr and Appleby Rd.

Complete pavement widening works and kerb and channel construction between Appleby Rd and Oak Manor Dr.

Commence pavement works through the Oak Manor Dr intersection under stop/go operations.

Continue footpath preparation works between Oak Manor Dr and Rosedale Rd.

Complete paving operations on the western side of the road between Oak Manor Dr and Rosedale Rd.

Continue the footpath preparation between Rosedale Rd and Wentworth Park.

Continue watermain works at the Bass Rd intersection.

Continue footpath construction between Eastbourne Rd and Days Bridge.

Continue pavement preparation between the Albany Presbyterian Church and Eastbourne Road.

Continue footpath preparation and berm reinstatement north of Summerfield Lane.

Night Works

Paving between Oak Manor Dr and Rosedale Rd on the western side of the road on Monday 31 August, weather permitting.

Relocating power and telecom services on the western side of Days Bridge between Sunday 30 August and Thursday 3 September.

Trenching across Albany Highway for the watermain at Bass Rd on Wednesday 2 September.

Looking ahead

At Days Bridge we are planning to switch traffic and pedestrians onto the newly built eastern side of Albany Highway in mid to late September.

Between Oakway Dr and Rosedale Rd we are planning to switch traffic onto the newly built western side of Albany Highway at the end of September.

On September 14th we are planning to close the Schnapper Rock Rd North vehicle access to Albany Highway to allow construction works to occur. Detours will be in place utilising the signalised intersections at Bush Rd/Schnapper Rock Rd South and Oakway Drive. Pedestrian access will remain open. The intersection will reopen in its final configuration in March 2016 with vehicles restricted to left turn in and left turn out.


21 August


This week we

Commenced set up and vegetation clearing for works on the western side of the road between Bush Rd and Oakway Dr.

Continued with footpath preparation works between Appleby Rd and Oak Manor Dr.

Continued pavement widening works between Oak Manor Dr and Rosedale Rd.

Started the tidy up after the watermain work and completed the footpath prep between Rosedale Rd and Wentworth Park.

Continued fence construction at Secret Garden childcare south of Bass Rd.

Continued common service trenching south of Bass Rd.

Continued boundary fencing between Summerfield Ln and Bass Rd.

Continued footpath and pavement preparation between Eastbourne Rd and Days Bridge.

Completed watermain reinstatement at the north west corner of Wharf Rd.

Commenced watermain connection works at the Bass Rd intersection.

Continued Stage 1 Bridge works at Days Bridge.

Continued retaining wall construction outside the Albany Presbyterian Church.

Next week we will

Continue works on the western side of the road between Bush Rd and Oakway Dr.

Continue with footpath preparation works between Appleby Rd and Oak Manor Dr.

Continue pavement widening and footpath works between Oak Manor Dr and Rosedale Rd.

Continue footpath prep between Rosedale Rd and Wentworth Park.

Complete fence construction at Secret Garden childcare south of Bass Rd.

Complete fencing work at the Summerfield Ln retaining wall.

Continue watermain works at the Bass Rd intersection.

Continue footpath construction between Eastbourne Rd and Days Bridge.

Continue Stage 1 Bridge works at Days Bridge.

Continue pavement preparation between the Albany Presbyterian Church and Eastbourne Road.


Night Work

Paving between Oak Manor Dr and Rosedale Rd on the western side of the road.

Relocating power and telecom services on the western side of Days Bridge.

Looking ahead

At Days Bridge we are planning to switch traffic and pedestrians onto the newly built eastern side of Albany Highway in mid to late-September.

Between Oakway Dr and Rosedale Rd we are planning to switch traffic onto the newly built western side of Albany Highway at the end of September.

In mid-September we are planning to close the Schnapper Rock Rd North access to Albany Highway to allow construction works to occur. Detours will be in place utilising the signalised intersections at Bush Rd/Schnapper Rock Rd South and Oakway Drive. The intersection will reopen in its final configuration in March 2016 with vehicles restricted to left turn in and left turn out.


14 August 


This week we

Completed stabilising, pavement and footpath works from 221 Albany Highway to Oakway Dr.

Continued with footpath preparation works between Oak Manor Dr and Appleby Rd.

Continued pavement widening works between Oak Manor Dr and Kristin School.

Continued the North Shore Golf Club pond access road works.

Completed the installation of a new watermain in the verge on the south side of Wentworth Park.

Continued pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continued boundary fencing between Summerfield Ln and Bass Rd.

Continued common service trenching south of Bass Rd.

Continued footpath and pavement preparation between Eastbourne Rd and Days Bridge.

Continued watermain works at the north west corner of Wharf Rd.

Continued Stage 1 Bridge works at Days Bridge.

Completed connections for the 33kVa Vector power tie-ins north and south of Days Bridge.

Continued retaining wall construction outside the Albany Presbyterian Church.

Next week we will

Commence works on the western side of the road between Bush Rd and Oakway Dr.

Continue with footpath preparation works between Oak Manor Dr and Appleby Rd.

Continue pavement widening and footpath works between Oak Manor Dr and Kristin School.

Tidy up after the watermain work and complete the footpath prep between Rosedale Rd and Wentworth Park.

Continue common services trenching work south of Bass Rd.

Continue fence construction at Secret Garden childcare south of Bass Rd.

Continue fencing work, pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continue landscaping works near the Summerfield slip lane.

Continue watermain works at the north west corner of Wharf Rd.

Continue footpath, pavement preparation between Eastbourne Rd and Days Bridge.

Continue Stage 1 bridge works at Days Bridge.

Continue retaining wall construction outside the Albany Presbyterian Church.

Continue pavement preparation between the Albany Presbyterian Church and Days Bridge.

Install scaffolding to the west side of Days Bridge for temporary services transfer.

Night work

Two traffic signal road duct crossings between Appleby Rd and Rosedale Rd mid next week.

Paving late next week between Oak Manor Dr and Rosedale Rd on the western side of the road, weather permitting.

Looking ahead

At Days Bridge we are planning to switch traffic and pedestrians onto the newly built eastern side of Albany Highway in early to mid-September.

Between Oakway Dr and Rosedale Rd we are planning to switch traffic onto the newly built western side of Albany Highway at the end of September.

In mid-September we are planning to close the Schnapper Rock Rd North access to Albany Highway to allow construction works to occur.  Signed detours will be in place utilising the signalised intersections at Bush Rd/Schnapper Rock Rd South and Oakway Drive. The intersection will reopen in its final configuration in March 2016 ie left in, left out. 


7 August 


This week we

Continued pavement and footpath works from 221 Albany Highway to Oakway Dr.

Commenced stabilising works from 221 Albany Highway to Oakway Dr.

Continued with footpath preparation works between Oak Manor Dr and Appleby Rd.

Commenced pavement widening works between Oak Manor Dr and Kristin School.

Commenced the North Shore Golf Club pond access road works.

Continued the installation of a new watermain in the verge on the south side of Wentworth Park.

Continued fencing work, pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continued boundary fencing between Summerfield Ln and Bass Rd.

Continued common service trenching south of Bass Rd.

Continued footpath, pavement preparation and common services trenching between Eastbourne Rd and Days Bridge.

Continued watermain works at the north west corner of Wharf Rd.

Continued Stage 1 Bridge works at Days Bridge.

Continued connections for the Vector 33kVa power tie-ins north and south of Days Bridge.

Continued pavement preparation between the Albany Presbyterian Church and Days Bridge.

Continued retaining wall construction outside the Albany Presbyterian Church.

Completed slip lane and private property access construction near Summerfield Ln.

Completed road crossings near Library Ln.

Completed common service trenching from the Albany Presbyterian Church towards the Albany Expressway.

Next week we will

Continue pavement and footpath works from 221 Albany Highway to Appleby Rd including stabilising and chip sealing the road from Bush Rd to Oakway Dr if weather permits.

Continue with footpath preparation works between Oak Manor Dr and Appleby Rd.

Continue pavement widening works between Oak Manor Dr and Kristin School.

Complete the North Shore Golf Club pond access road works.

Complete the new watermain in the verge on the south side of Wentworth Park.

Continue common services trenching work south of Bass Rd.

Begin fence construction at Secret Garden childcare south of Bass Rd.

Continue fencing work, pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continue landscaping works near the Summerfield slip lane.

Continue watermain works at the north west corner of Wharf Rd.

Continue footpath, pavement preparation and common services trenching between Eastbourne Rd and Days Bridge.

Continue connections for the Vector 33kVa power tie-ins north and south of Days Bridge.

Continue Stage 1 bridge works at Days Bridge.

Continue retaining wall construction outside the Albany Presbyterian Church.

Continue pavement preparation between the Albany Presbyterian Church and Days Bridge.

Continue reinstating pavement where the islands were removed near Library Ln.

Night works

On August 9 and 10, weather permitting, we will commence rescheduled stabilising and chip sealing the eastern side of Albany Highway between Bush Rd and Oakway Dr:

One-way detour and road closure on the nights of Sunday 9 August and Monday 10 August: Albany Highway will be reduced to a single southbound lane between Oakway Dr and the Bush Rd intersection. Northbound traffic will be diverted at Bush Rd. During these works Rothwell Ave will be closed at the Albany Highway intersection.

On Tuesday 11 August, weather permitting, we will lay chip seal on the newly stabilised road. Albany Highway will be open to traffic in both directions. If delayed, this work will be done on the next available night.

Looking ahead

Between Bush Rd and Schnapper Rock Rd we are planning to switch traffic onto the eastern side of Albany Highway on Wednesday August 12 2015, weather permitting.

At Days Bridge we are planning to switch traffic and pedestrians onto the eastern side of Albany Highway in September.


31 July


This week we

Installed subsoil drainage in the road near 211 Albany Highway.

Continued pavement and footpath works from 221 Albany Highway to Oakway Dr.

Completed the vehicle crossing for 265 Albany Highway.

Completed watermain works between Oakway Dr and Appleby Rd.

Continued with footpath preparation works between Oak Manor Dr and Appleby Rd.

Continued the installation of a new watermain in the verge on the south side of Wentworth Park.

Continue fencing work, pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continued common service trenching south of Bass Rd.

Installed catch pits between Wharf Rd and Bass Rd.

Continued boundary fencing between Summerfield Lane and Bass Rd.

Continue slip lane access near Summerfield Lane.

Completed the timber edging wall north of Eastbourne Rd.

Continued Stage 1 Bridge works at Days Bridge.

Continued footpath/pavement preparation and common services trenching between Eastbourne Rd and Days Bridge.

Continued stormwater installation to the south side of Days Bridge.

Continued watermain works around the NW corner of Wharf Rd.

Continue excavation for 33kVa tie-in points near the entrance to Albany Senior High School.

Continued pavement preparation between the Albany Presbyterian Church and Days Bridge.

Continued retaining wall construction outside the Albany Presbyterian Church.

Continued common service trenching from the Albany Presbyterian Church towards the Albany Expressway.

Completed new bulk supply watermain at Days Bridge.

Next week we will

Continue pavement and footpath works from 221 Albany Highway to Appleby Rd including stabilising and chip sealing the road from Bush Rd to Oakway Dr.

Continue pavement and footpath works between the Albany Family Medical Centre and Oak Manor Dr.

Complete the new watermain in the verge on the south side of Wentworth Park.

Continue fence construction at Secret Garden childcare.

Continue common services trenching work south of Bass Rd.

Continue fencing work, pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continue footpath/pavement preparation and common services trenching between Eastbourne Rd and Days Bridge.

Continue Stage 1 bridge works at Days Bridge.

Continue Pavement preparation between the Albany Presbyterian Church and Days Bridge.

Continue watermain works around the north western corner of Wharf road.

Continue excavation for 33kVa tie-in points near the entrance to Albany Senior High School.

Continue retaining wall construction outside the Albany Presbyterian Church.

Continue common services trenching from the Albany Presbyterian Church towards Albany Expressway.

Night works

From Sunday 2 August, we plan to trench for services across Eastbourne Rd, weather permitting.

Sunday 2 August (weather permitting), we will continue traffic island removal works at Library Lane near the Albany Expressway.

On 5 and 6 August, we will commence stabilising and chip sealing the eastern side of Albany Highway between Bush Rd and Oakway Dr. One-way detour and road closure on the night of Wednesday 5 August; Albany Highway will be reduced to a single southbound lane between Oakway Drive and the Bush Road intersection. Northbound traffic will be diverted at Bush Road. During these works, Rothwell Avenue will be closed at the Albany Highway intersection.

On Thursday 6 August (weather permitting), we will lay chip seal on the newly stabilised road. Albany Highway will be open to traffic in both directions. If delayed, this work will roll to the following week.

Looking ahead

Between Bush Rd and Schnapper Rock Rd, we are planning to switch traffic onto the eastern side of Albany Highway on Sunday 9 August, weather permitting.

At Days Bridge, we are planning to switch traffic and pedestrians onto the eastern side of Albany Highway in September.


24 July


This week we:

Completed footpath works leading into the Rosedale Rd / Albany Highway intersection. 

Continued pavement and footpath works from 221 Albany Highway to Oakway Dr.

Completed construction of the kerb on the eastern side from 221 Albany Highway to Oakway Dr.

Completed the road sub base between Oakway Dr and Appleby Rd.

Completed common service trenching and continued with footpath preparation works between Oak Manor Dr and Appleby Rd.

Completed drainage works between Oak Manor Dr and Appleby Rd. 

Commenced installation of new watermains in the verge on the south side of Wentworth Park.

Continued fencing work, pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continued common service trenching south of Bass Rd.

Continued Stage 1 Bridge works at Days Bridge.

Continued boundary fencing between Summerfield Ln and Bass Rd.

Continued retaining wall construction outside the Albany Presbyterian Church.

Continued common service trenching from the Albany Presbyterian Church towards the Albany Expressway.

Continued footpath/pavement preparation and common services trenching between Eastbourne Rd and Days Bridge.

Continued stormwater installation to the south side of Days bridge.

Continued construction of the timber edging wall north of Eastbourne Rd.

Continued watermain installation on the northwest corner of Wharf Rd.

Commenced enabling works to construct pavement between the Albany Presbyterian Church and Days Bridge.

Installed catch pits between Wharf Rd and Bass Rd.

Next week we will:

Continue pavement and footpath works from 221 Albany Highway to Appleby Rd. 

Continue pavement and footpath works between Albany Medical Centre and Oak Manor Dr.

Continue Stage 1 bridge works at Days Bridge.

Continue common services trenching work on the southern side of Bass Rd.

Continue fencing work, pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continue retaining wall construction outside the Albany Presbyterian Church.

Continue common services trenching from the Albany Presbyterian Church towards Albany Expressway.

Continue footpath/pavement preparation and common services trenching between Eastbourne Rd and Days Bridge.

Continue stormwater installation to the south side of Days bridge.

Continue construction of the timber edging wall north of Eastbourne Rd.

Continue enabling works for construction of pavement between the Albany Presbyterian Church and Days Bridge.

Continue installation of a new fence at Secret Garden 4 Kids Daycare.

Night works:

Installing sub soil drainage across Albany Highway near the Visy / Hasbro vehicle crossing north of Rothwell Av.

Watercare is planning to complete water main commissioning works at several locations along Albany Highway including at the intersections of Oak Manor Dr and Appleby Rd and on the northwest corner of Wharf Rd.

Removing the traffic islands at north end of Albany Highway near Albany Expressway and opposite Library Ln.

Installing Vector power ducts across Albany Highway at Library Ln.

Completing the common service trenching across Albany Highway north of Wharf Rd.

Looking ahead:

Between Bush Rd and Schnapper Rock Rd we are planning to switch traffic onto the western side of Albany Highway in early August.

At Days Bridge we are planning to switch traffic and pedestrians onto the eastern side of Albany Highway in September.


17 July


This week we:

Completed pavement works and the installation of underground traffic signal sensors at the Albany Highway / Rosedale Rd intersection. The Rosedale Road/Albany Highway intersection is now operating as a signalised intersection. We urge motorists to continue to drive with care while adapting to the changing conditions. We would like to thank everyone for their patience as these important works were completed.

Continued pavement and footpath works from 221 Albany Highway to Oakway Dr.

Commenced constructing the road sub base between Oakway Dr and Appleby Rd.

Continued common service trenching and footpath preparation works between Oak Manor Dr and Appleby Rd.

Completed drainage works between Oak Manor Dr and Appleby Rd. 

Continued footpath preparation between Wharf Rd and Bass Rd.

Continued common service trenching south of Bass Rd.

Continued Stage 1 bridge works at Days Bridge.

Continued welding and installing the new gas main for diversion to the new section of Days Bridge.

Continued construction of the new bulk watermain to the north side of Days Bridge.

Continued boundary fencing and retaining wall construction between Summerfield Ln and Bass Rd.

Continued retaining wall construction outside the Albany Presbyterian Church.

Continued common service trenching from the Albany Presbyterian Church towards the Albany Expressway.

Continued footpath preparation between Eastbourne Rd and Days Bridge.

Continued the installation of new stormwater services to the south side of Days bridge.

Completed works modifying the kerb alignment near the south entrance to Albany Senior High School.

Next week we will:

Continue pavement and footpath works from 221 Albany Highway to Oakway Dr.

Pour a new footpath north of Rothwell Ave.

Install kerb and channel opposite Schnapper Rock Rd through to Oakway Dr.

Install kerb and channel between Oakway Dr and Appleby Rd.

Complete the common services trenching between Oak Manor Dr and Appleby Rd.

Complete footpath works near the Albany Highway / Rosedale Rd intersection.

Continue Stage 1 bridge works at Days Bridge.

Continue clearing and common services trenching work on the southern side of Bass Rd.

Continue with commissioning of gas main through days bridge.

Continue fencing work, pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continue construction of the retaining wall south of Summerfield Ln.

Continue construction of the new bulk watermain north of Days Bridge.

Continue retaining wall construction outside the Albany Presbyterian Church.

Continue common services trenching from the Albany Presbyterian Church towards Albany Expressway.

Continue footpath preparation between Eastbourne Rd and Days Bridge.

Continue stormwater installation to the South side of Days bridge.

Night Works:

Watercare is planning to complete water main commissioning works at several locations along Albany Highway including at the intersections of Oak Manor Dr and Appleby Rd and on the northwest corner of Wharf Rd.

We are planning removal of the traffic islands at north end of Albany Highway near Albany Expressway and opposite Library Ln.

Looking ahead:

Between Bush Rd and Schnapper Rock Rd we are planning to switch traffic onto the western side of Albany Highway in August.

At Days Bridge we are planning to switch traffic onto the eastern side of Albany Highway in September.

We are planning to construct watermains in the verge on the south side of Wentworth Park from Albany Highway for 25m. Pedestrian access will be maintained via an alternate footpath.


13 July

The road closure at the Rosedale Road/Albany Highway intersection over the weekend has now been lifted.  Thanks to all. Full signalisation of the intersection is scheduled for later this week, weather permitting. Please continue to drive with care.

10 July

This week we: 

Continued works at the Albany Highway/Rosedale Rd intersection, including completing another section of asphalt. 

Continued drainage works and commenced footpath works between Oak Manor Dr and Appleby Rd. 

Continued pavement and footpath works from 221 Albany Highway to Oakway Drive.

Continued footpath preparation between Wharf Rd and Bass Rd.

Continued common service trenching south of Bass Rd.

Continued Stage 1 Bridge works at Days Bridge.

Continued welding the new gas main for diversion to the new section of Days Bridge.

Continued construction of the new bulk watermain between Eastbourne Rd and Days Bridge.

Completed enabling works and began construction of the retaining wall south of Summerfield Ln.

Continued boundary fencing and retaining wall construction between Summerfield Ln and Bass Rd.

Continued retaining wall construction and constructed a new vehicle crossing outside the Albany Presbyterian Church.

Continued common service trenching from the Albany Presbyterian Church towards the Albany Expressway.

Continued footpath preparation between Eastbourne Rd and Days Bridge.

Next week we will:

Complete pavement works at the Albany Highway/Rosedale Rd intersection; 6pm Friday 10 July – 5am Monday 13 Jul, weather permitting 

Install underground traffic signal sensors at the Rosedale Rd/Albany Highway intersection. 

Continue drainage and footpath works between Oak Manor Dr and Appleby Rd.

Continue pavement and footpath works from 221 Albany Highway to Oakway Drive.

Continue Stage 1 bridge works at Days Bridge.

Continue clearing and common services trenching work on the southern side of Bass Rd.

Continue welding and installing the new gas main for diversion to the new section of Days Bridge.

Continue fencing work, pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Continue construction of the retaining wall south of Summerfield Ln.

Continue construction of the new bulk watermain between Eastbourne Rd and Days Bridge.

Continue works modifying the kerb alignment near the south entrance to Albany Senior High School.

Continue retaining wall construction outside the Albany Presbyterian Church.

Continue common services trenching from the Albany Presbyterian Church towards Albany Expressway.

Continue footpath preparation between Eastbourne Rd and Days Bridge.

Night work:

At Rosedale Rd / Albany Highway roundabout, weather permitting, we will complete weekend day and night works involving a road closure affecting the Albany Highway end of Rosedale Rd between William Pickering Dr and Albany Highway from 6pm Friday 10 July – 5am Monday 13 July. Businesses at the corner of William Pickering Dr and Rosedale Rd will be accessible and open, pedestrian and cycle access will be available along Rosedale Rd and Albany Highway will remain open to traffic at all times.

Night works are scheduled for next week the 13-17 July to install underground traffic signal sensors at the Rosedale Rd/Albany Highway intersection, if weather allows. This will lead to a planned activation of the traffic signals at the intersection.

Watercare is planning to complete water main commissioning works at several locations along Albany Highway including opposite Schnapper Rock Rd, at the intersections of Oak Manor Dr and Appleby Rd, on the northwest corner of Wharf Rd and outside Albany Senior High School.

Looking ahead:

Between Bush Rd and Schnapper Rock Rd we are planning to switch traffic onto the western side of Albany Highway in August.

At Days Bridge we are planning to switch traffic onto the eastern side of Albany Highway in September.

We are planning to construct watermains in the verge on the south side of Wentworth Park from Albany Highway for 25m. Pedestrian access will be maintained via an alternate footpath.


3 July


This week we:

Continued works at the Albany Highway/Rosedale Rd intersection.

Continued drainage works and commenced footpath works between Oak Manor Dr and Appleby Rd. 

Continued pavement and footpath works from 221 Albany Highway to Oakway Drive.

Completed service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Completed new vehicle crossing fill to entranceway at 265 Albany Highway.

Continued footpath preparation between Wharf Rd and Bass Rd.

Continued common service trenching South of Bass Rd.

Continued construction of footpaths opposite Albany Senior High School.

Continued Stage 1 Bridge works at Days Bridge.

Continued welding the new gas main for diversion to the new bridge.

Continued construction of the new bulk watermain between Eastbourne Rd and Days Bridge.

Continued retaining wall enabling works outside the Presbyterian church.

Commenced excavation for retaining wall south of Summerfield Lane.

Commenced boundary fencing and retaining wall construction between Summerfield Lane and Bass Rd.

Next week we will:

Continue works at the Albany Highway/Rosedale Rd intersection in preparation for the weekend closure of Rosedale Rd (6pm Friday 10 July – 5am Monday 13 July).

Continue drainage works and footpath works between Oak Manor Dr and Appleby Rd.

Continue pavement and footpath works from 221 Albany Highway to Oakway Drive.

Continue Stage 1 bridge works at Days Bridge.

Continue clearing and common services trenching work on the southern side of Bass Rd.

Continue welding and installing the new gas main for diversion to the new bridge.

Continue fencing work between Wharf and Bass Rd.

Continue pavement widening and footpath preparation from Wharf Rd to Bass Rd.

Commence construction of the retaining wall south of Summerfield Lane.

Continue construction of the new bulk watermain between Eastbourne Rd and Days Bridge.

Modify the kerb alignment near the south entrance to Albany Senior High School.

Construct new vehicle crossings outside the Presbyterian church.

Continue retaining wall construction outside the Presbyterian church.

Night works:

We will continue with stormwater lines across Albany Highway between Rosedale Rd and Appleby Rd until Thursday 9 July.

We will lay stormwater lines across Albany Highway and Summerfield Ln, Albany Highway and Wharf Rd, and outside the Albany Senior High School between Sunday 5 July and Thursday 9 July.

Enabling paving works at the Rosedale Rd intersection on Monday 6 July, weather permitting.

Ongoing works:

Works completed at North Shore Golf Club Pond.

Looking ahead:

At Rosedale Rd / Albany Highway Roundabout, weather permitting, we are planning works involving a road closure affecting the Albany Highway end of Rosedale Rd from 6pm Friday 10 July – 5am Monday 13 July. Albany Highway will remain open to traffic at all times.

Night works are scheduled for the week of 13-17 July for installing underground traffic signal sensors at the Rosedale Rd/Albany Highway intersection, if weather allows. This will lead to a planned activation of the traffic signals on the intersection.

Between Bush Rd and Rothwell Ave we are planning to switch traffic onto the western side of Albany Highway in August.

At Days Bridge we are planning to switch traffic onto the eastern side of Albany Highway in September.


29 June


Rosedale Road closure 10 - 13 July 2015

A section of Rosedale Road - from Albany Highway to William Pickering Drive - will be closed from 6pm Friday 10 July to 5am Monday 13 July 2015 (weather permitting).  

This road closure allows for completion of major works, including the reconstruction and completion of the Albany Highway/Rosedale Road intersection. The traffic signals will be activated during July.

Detours will be in place to redirect traffic via:

Albany Expressway,

Rothwell Avenue,

Bush Road.

 

All businesses in the area will remain open during their normal business hours, and pedestrian and cycle access will be available along Rosedale Road. Albany Highway will remain open to traffic at all times.

Vehicles needing to enter or exit properties in the affected zone during the closure should discuss their needs with traffic staff on site, who will assist.

Map showing the temporary road closure for Rosedale Road and detours

Temporary Road Closure Rosedale Road July 2015


26 June


This week we:

Completed pavement investigations on Albany Highway between Oakway Dr and Wharf Rd a week early.

Continued works at the Albany Highway/Rosedale Rd intersection.

Continued drainage works between Oak Manor Dr and Appleby Rd.

Continued pavement and footpath works from 221 Albany Highway to Schnapper Rock Rd.

Continued service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Completed retaining wall construction at 265 Albany Highway.

Completed watermain cut-in works at 265 Albany Highway.

Installed splay catchpits between Eastbourne Road and the Presbyterian church.

Began footpath preparation between Wharf Rd and Bass Rd.

Began common service trenching South of Bass Rd.

Continued preparation of footpaths for concreting opposite Albany Senior High School.

Continued Stage 1 Bridge works at Days Bridge.

Continued new services connections to properties between Wharf and Bass Rd.

Continued welding the new gas main for diversion to the new bridge.

Continued construction of the new bulk watermain between Eastbourne Rd and Days Bridge.

Completed the first stage of backfill to Days bridge abutments.

Continued retaining wall enabling works outside the Presbyterian church.

Photo of the Days Bridge lift

Albany Highway north upgrade: Days Bridge Lift

Four large steel-reinforced concrete beams, each weighing about 60 tonnes, were lifted into place at Days Bridge, a 300 tonne and 400 tonne crane working in tandem.

The lifts took place on a Sunday night to minimise traffic disruption and the cranes were set up on the road. 

Next week we will:

Continue works at the Albany Highway/Rosedale Rd intersection.

Continue drainage works between Oak Manor Dr and Appleby Rd.

Continue pavement and footpath works from 221 Albany Highway to Schnapper Rock Rd.

Continue service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Continue Stage 1 bridge works at Days Bridge.

Continue stormwater cesspit connections between Bass Rd and Wharf Rd. 

Continue clearing and common services trenching work on southern side of Bass Rd.

Continue welding and installing the new gas main for diversion to the new bridge.

Continue fencing work between Wharf and Bass Rd.

Continue pavement widening & footpath preparation from Wharf Rd to Bass Rd.

Continue construction of the new bulk watermain between Eastbourne Rd and Days Bridge.

Night Works:

Stormwater lines across Albany Highway between Rosedale Rd and Appleby Rd between Sunday 28 June and Thursday 9 July.

Construction of the driveway for 265 Albany Highway between Sunday 28 June and Thursday 9 July.

Ongoing works:

Planting around the pond in the North Shore Golf Club grounds.

Looking ahead:

At Rosedale Rd / Albany Highway Roundabout we are planning major works involving a road closure affecting the Albany Highway end of Rosedale Rd, over the weekend of 11 and 12 July.

Between Bush Rd and Rothwell Ave we are planning to switch traffic onto the western side of Albany Highway in August.

At Days Bridge we are planning to switch traffic onto the eastern side of Albany Highway in September.


19 June


This week we:

Continued works at the Albany Highway/Rosedale Rd intersection.

Continued drainage works between Oak Manor Dr and Appleby Rd.

Continued pavement and footpath works from 221 Albany Highway to Schnapper Rock Rd.

Continued service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Commenced retaining wall construction at 265 Albany Highway.

Completed stormwater pond earthworks in the NSGC.

Continued stormwater cesspit connections between Bass Rd and Wharf Rd.

Continued clearing, property mitigation and common services trenching work between Wharf Rd and Bass Rd.

Continued Stage 1 Bridge works at Days Bridge.

Continued construction of the new service lane north of Summerfield Ln.

Continued welding the new gas main for diversion to the new bridge.

Commenced construction of a new bulk watermain between Eastbourne Rd and Days Bridge.

Installed streetlight poles between Bass Rd and Library Ln.

Next week we will:

Continue works at the Albany Highway/Rosedale Rd intersection.

Continue drainage works between Oak Manor Dr and Appleby Rd.

Continue pavement and footpath works from 221 Albany Highway to Schnapper Rock Rd.

Continue service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Complete retaining wall construction at 265 Albany Highway.

Continue Stage 1 bridge works at Days Bridge.

Continue stormwater cesspit connections between Bass Rd and Wharf Rd. 

Continue clearing and common services trenching work on Southern Side of Bass Rd.

Continue first stage of fill to the Days Bridge abutment.

Continue welding and installing the new gas main for diversion to the new bridge.

Continue fencing work between Wharf and Bass Rd.

Continue pavement widening preparation from Wharf to Bass Rd.

Continue construction of new bulk watermain between Eastbourne Rd and Days Bridge.

Prepare footpaths for concreting opposite Albany Senior High School.

Night work:

Regular road surface maintenance checks on Albany Highway each Thursday and Sunday.

Pavement investigations on Albany Highway between Oakway Dr and Wharf Rd between Sunday 21 and Thursday 25 June.

Stormwater lines across Albany Highway between Rosedale Rd and Appleby Rd between Sunday 28 June and Thursday 9 July.

Construction of the driveway for 265 Albany Highway.

Ongoing works:

Planting around the pond in the North Shore Golf Club grounds.

Looking ahead:

At Rosedale Rd / Albany Highway Roundabout we have scheduled major works involving a road closure affecting the Albany Highway end of Rosedale Rd over the weekend of 11 and 12 July.

Between Bush Rd and Rothwell Ave we plan to switch traffic onto the western side of Albany Highway in August.

At Days Bridge we plan to switch traffic onto the eastern side of Albany Highway in September.


15 June


This week we:

Continued works at the Albany Highway/Rosedale Rd intersection.

Continued drainage works between Oak Manor Dr and Appleby Rd.

Continued pavement and footpath works from 221 Albany Highway to Schnapper Rock Rd.

Continued service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Completed common services installation from Appleby Rd to Rosedale Rd on the eastern side.

Continued stormwater cesspit connections between Bass Rd and Wharf Rd.

Continued clearing, property mitigation and common services trenching work between Wharf Rd and Bass Rd.

Continued Stage 1 Bridge works at Days Bridge.

Continued earthworks to the berm between Eastbourne Rd and Days Bridge.

Constructed a watermain connection point at Bass Road.

Continued construction of the new service lane north of Summerfield Ln.

Continued welding the new gas main for diversion to the new bridge.

Next week we will:

Continue pavement and footpath works from 221 Albany Highway to Schnapper Rock Rd.

Continue service relocation and watermain works between Appleby Rd and Rothwell Ave.

Continue drainage works between Oak Manor Dr and Appleby Rd heading south.

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement construction on the eastern side of Albany Highway.

Continue Stage 1 bridge works at Days Bridge.

Continue stormwater cesspit connections between Bass Rd and Wharf Rd. 

Continue clearing and common services trenching work on Southern Side of Bass Rd.

Continue first stage of fill to the Days Bridge abutment.

Continue welding and installing the new gas main for diversion to the new bridge.

Continue fencing work between Wharf and Bass Rd.

Continue pavement widening preparation from Wharf to Bass Rd.

Commence construction of a new bulk watermain between Eastbourne Rd and Days Bridge.

Night works:

Regular road surface maintenance checks on the Highway each Thursday and Sunday.

Pavement investigations between Oakway Dr and Wharf Rd between Sunday 14 and Thursday 18 June.

Ongoing works:

Work in the North Shore Golf Club grounds.

Looking ahead:

Between Bush Rd and Rothwell Ave we are planning to switch traffic onto the western side of Albany Highway in August.

At Rosedale Rd / Albany Highway Roundabout we are planning to move traffic to allow access to the north eastern quarter of the intersection in June.

At Days Bridge we are planning to switch traffic onto the eastern side of Albany Highway in September.

At Rosedale Rd / Albany Highway Roundabout we are planning major works involving a road closure affecting the Albany Highway end of Rosedale Rd, over 11 - 12 July 2015.


June


This week we:

Continued works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Continued drainage works from Kristin School Gate 1 heading south toward Appleby Rd, across Oak Manor Dr.

Continued pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continued service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Continued common services installation from Appleby Rd to Rosedale Rd on the eastern side.

Installed and turned on new lighting from Schnapper Rock to 221 Albany Highway.

Continued stormwater works between Bass Rd and Princeton Pde.

Continued clearing, property mitigation and common services trenching work between Wharf Rd and Bass Rd.

Continued Stage 1 Bridge works at Days Bridge.

Continued first stage of fill to Days Bridge abutment.

Pressure tested the new watermain between Bass Rd and Wharf Rd.

Commenced construction of the new service lane north of Summerfield Ln.

Continued welding the new gas main for diversion to the new bridge.

Next week we will:

Continue pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continue service relocation and watermain works between Appleby Rd and Rothwell Ave.

Continue drainage works from Kristin School Gate 1 heading south.

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement. construction on the eastern side of Albany Highway.

Complete common services installation from Appleby Rd to Rosedale Rd on the eastern side.

Continue Stage 1 bridge works at Days Bridge.

Continue stormwater works between Bass Rd and Princeton Pde.

Continue clearing and common services trenching work at Bass Rd.

Continue first stage of fill to the Days Bridge abutment.

Continue construction of the new service lane north of Summerfield Ln.

Continue welding a new gas main for diversion to the new bridge.

Night works:

Regular road surface maintenance checks on the Highway each Thursday and Sunday.

Multiple trenching for services across Albany Highway between Princeton Parade and Wharf Rd over the next two weeks, weather and World Cup games permitting.

Ongoing works:

Work in the North Shore Golf Club grounds.

Looking ahead:

Between Bush Rd and Rothwell Ave we are planning to switch traffic onto the western side of Albany Highway in August.

At Rosedale Rd / Albany Highway Roundabout we are planning to move traffic to allow access to the north eastern quarter of the intersection in June.

At Days Bridge we are planning to switch traffic onto the eastern side of Albany Highway in September.

At Rosedale Rd / Albany Highway Roundabout we are planning major works involving a road closure affecting the Albany Highway end of Rosedale Rd, over the weekend from 11 - 12 July.


29 May


This week we:

Continued works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Continued drainage works from Kristin School Gate 1 heading south toward Appleby Rd, across Oak Manor Dr.

Continued pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continued service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Completed power pole removal works from Schnapper Rock Road to Appleby Rd.

Continued stormwater works between Bass Rd and Princeton Pde.

Continued clearing, property mitigation and common services trenching work between Wharf Rd and Bass Rd.

Continued Stage 1 Bridge works at Days Bridge including placing the new bridge beams.

Continued earthworks and footpath preparation between Eastbourne Rd and Albany Presbyterian Church.

Continued first stage of fill to Days Bridge abutment.

Connected a new gas pipe between Wharf Rd and Bass Rd.

Next week we will:

Continue pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continue service relocation and watermain works between Appleby Rd and Rothwell Ave.

Continue drainage works from Kristin School Gate 1 heading south.

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement construction on the eastern side of Albany Highway.

Continue Stage 1 bridge works at Days Bridge.

Continue stormwater works between Bass Rd and Princeton Pde.

Continue clearing and common services trenching work between Wharf Rd and Bass Rd.

Continue earthworks and footpath preparation between Eastbourne Rd and Albany Presbyterian Church.

Continue first stage of fill to Days bridge abutment.

Install street light poles opposite the Albany Senior School and North of Eastbourne Rd.

Excavate and lay a drainage line across Oak Manor Drive near the Albany Highway intersection. Vehicle access will be maintained in both directions.

Night works:

We will be working at night digging multiple service trenches across Albany Highway between 416 Albany Highway and 1 Wharf Road from Monday 1 June to Thursday 4 June and Sunday 7 June to Thursday 11 June (weather permitting).

We will be carrying out road repairs and line-marking as required throughout the site.

Ongoing works:

Work in the North Shore Golf Club grounds.

Looking ahead:

Between Bush Rd and Rothwell Ave we are planning to switch traffic onto the western side of Albany Highway in August.

At Rosedale Rd / Albany Highway Roundabout we are planning to move traffic to allow access to the north eastern quarter of the intersection in June.

At Days Bridge we are planning to switch traffic onto the eastern side of Albany Highway in July.

At Rosedale Rd / Albany Highway Roundabout we are planning major works involving a road closure over the weekend of 11 and 12 July.


22 May


This week we:

Continued works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Continued drainage works from Kristin School Gate 1 heading south toward Appleby Rd.

Continued pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continued service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Continued power pole removal works Schnapper Rock Road to Appleby Rd.

Completed asphalt for the Visy/Hasbro vehicle crossing.

Continued stormwater works between Wharf Rd and Princeton Pde.

Continued clearing, property mitigation and common services trenching work between Wharf Rd and Bass Rd.

Continued Stage 1 Bridge works at Days Bridge.

Continued earthworks and footpath preparation between Eastbourne Rd and Days Bridge.

Continued footpath preparation between Days Bridge and the Albany Presbyterian Church.

Installed new signal poles between Eastbourne Rd and Albany Presbyterian Church.

Completed installation of the liner to the pond in the North Shore Golf Course.

Next week we will:

Continue works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Continue pavement works from 221 Albany Highway to Schnapper Rock Rd.

Complete power pole removal between 221 and 317 Albany Highway.

Continue service relocation and watermain works between Appleby Rd and Rothwell Ave.

Continue drainage works from Kristin School Gate 1 heading south.

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement construction.

Continue Stage 1 bridge works at Days Bridge.

Continue stormwater works between Bass Rd and Princeton Pde.

Continue clearing and common services trenching work between Wharf Rd and Bass Rd.

Continue earthworks and footpath preparation between Eastbourne Rd and Albany Presbyterian Church.

Continue first stage of fill to Days bridge abutment.

Night works:

A full road closure is planned at Days Bridge on Albany Highway between Wharf Rd and Library Lane between 3pm Sunday 24 May and 5am Monday 25 May. This will enable us to place four large beams for the new bridge adjacent to the existing bridge. The traffic detour route is Rosedale Rd/Bush Rd/Albany Expressway and will add about 7 minutes to your journey so please plan to leave a little earlier when travelling during this time. We apologise for any disruption. Access for residents will be maintained.

We will be carrying out road repairs and line marking as required throughout the site.

Ongoing works:

Work in the North Shore Golf Club grounds.

Looking ahead:

Between Bush Rd and Rothwell Ave we are planning to switch traffic onto the western side of Albany Highway in August.

At Rosedale Rd / Albany Highway Roundabout we are planning to move traffic to allow access to the north eastern quarter of the intersection in June.

At Days Bridge we are planning to switch traffic onto the eastern side of Albany Highway in July.

At Rosedale Rd / Albany Highway Roundabout we are planning major works involving a road closure over the weekend of July 11th and 12th.


20 May


Temporary road closures: Albany Highway - northern section

Albany Highway will be closed to through traffic between Wharf Road and Albany Expressway, from 3pm Sunday 24 May to 5am Monday 25 May 2015.

Detours will be in place to redirect traffic via Rosedale Road, Bush Road and Albany Expressway (see the temporary road closure map below).

Vehicles needing access to properties in the affected zone should enter from the north (Albany Expressway) and staff on site will assist.

This road closure allows for bridge beams to be lowered into place for the Days Bridge construction.

Albany Highway - northern section temporary road closure map


15 May


Be prepared: A full road closure is coming on 24-25 May. Make plans.

This week we:

Continued works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Continued drainage works from Kristin School Gate 1 heading south toward Appleby Rd.

Continued pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continued service relocation and new watermain works between 317 Albany Highway and Rothwell Ave.

Commenced power pole removal works from Rothwell Avenue to Schnapper Rock Road.

Completed the reconstruction of the Visy/Hasbro vehicle crossing and prepare the tie in ramp for asphalting.

Continued stormwater works between Wharf Rd and Princeton Pde.

Continued clearing, property mitigation and common services trenching work between Wharf Rd and Bass Rd.

Continued Stage 1 Bridge works at Days Bridge.

Continued earthworks and pavement construction between Eastbourne Rd and Days Bridge.

Continued pavement works between Days Bridge and the Albany Presbyterian Church.

Prepared for kerbing between Eastbourne and the Albany Presbyterian Church.

Next week we will:

Continue works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Continue pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continue power pole removal between 221 and 317 Albany Highway.

Continue service relocation and watermain works between Appleby Rd and Rothwell Ave.

Continue drainage works from Kristin School Gate 1 heading south.

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement construction.

Continue Stage 1 bridge works at Days Bridge and prepare for delivery of bridge beams.

Continue stormwater works between Bass Rd and Princeton Pde.

Continue clearing and common services trenching work between Wharf Rd and Bass Rd.

Continue earthworks and pavement construction between Eastbourne Rd and Days Bridge.

Continue pavement works between Days Bridge and the Albany Presbyterian Church.

Commence first stage of fill to Days bridge abutment.

Install new signal poles between Eastbourne Rd and Albany Presbyterian Church. 

Night works:

A full road closure is planned at Days Bridge on Albany Highway between Wharf Rd and Library Lane between 3pm Sunday 24 May and 5am Monday 25 May. This will enable us to place four large beams for the new bridge adjacent to the existing bridge. The traffic detour route is Rosedale Rd/Bush Rd/Albany. Expressway and will add about 7 minutes to your journey so please plan to leave a little earlier when travelling during this time. We apologise for any disruption.

We plan to move barriers and install site screens south of Days Bridge from Sunday 17 May. This is expected to take up to three nights.

We plan to excavate the driveway at Lollipops Educare on the corner of Rosedale Rd and Albany Highway after 6pm on Tuesday 19 May. Kerb will be laid later in the week.

We will be working at night carrying out road repairs and line marking as required.

Ongoing works:

Work in the North Shore Golf Club grounds.

Looking ahead:

Between Bush Rd and Rothwell Ave we are planning to switch traffic onto the western side of Albany Highway in July.

At Rosedale Rd / Albany Highway Roundabout we are planning to move traffic to allow access to the north eastern quarter of the intersection in June.

At Days Bridge we are planning to switch traffic onto the eastern side of Albany Highway in July.


8 May


This week we:

Continued works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Continued drainage works from Kristin School Gate 1 heading south toward Appleby Rd.

Continued pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continued service relocation works from Appleby Rd to Rothwell Ave.

Continued excavating and reconstructing the Visy/Hasbro vehicle crossing.

Continued stormwater works between Wharf Rd and Bass Rd.

Continued clearing, property mitigation and common services trenching work between Wharf Rd and Bass Rd.

Continued Stage 1 bridge works at Days Bridge.

Continued earthworks and pavement construction between Eastbourne Rd and Days Bridge.

Continued pavement works between Days Bridge and the Albany Presbyterian Church.

Commenced stormwater works through the Bass Rd intersection.

Next week we will:

Continue works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Continue pavement works from 221 Albany Highway to Schnapper Rock Rd.

Commence power pole removal from Rothwell Avenue to Schnapper Rock Road.

Continue service relocation works from Appleby Rd to Rothwell Ave.

Continue drainage works from Kristin School Gate 1 heading south.

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement construction.

Continue Stage 1 bridge works at Days Bridge.

Continue stormwater works between Bass Rd and Princeton Pde.

Continue clearing and common services trenching work between Wharf Rd and Bass Rd.

Continue earthworks and pavement construction between Eastbourne Rd and Days Bridge.

Continue pavement works between Days Bridge and the Albany Presbyterian Church.

Commence first stage of fill to Days bridge abutment.


Night works:

We will be working at night on Monday May 11 to Thursday May 14 completing stormwater works at the Bass Rd intersection, 7pm -5am.


Ongoing works:

Work in the North Shore Golf Club grounds.


Looking ahead:

Between Bush Rd and Rothwell Ave we are planning to switch traffic onto the western side of Albany Highway in July.

At Days Bridge we are planning to install beams for the new bridge in late May and switch traffic onto the eastern side of Albany Highway in July.


1 May


This week we:

Continued works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Recommenced drainage works from Kristin School Gate 1 heading south toward Appleby Rd.

Completed drainage works from Oakway Drive to Appleby Rd on the western side of Albany Highway.

Commenced pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continued service relocation works from Appleby Rd to Rothwell Ave.

Completed retaining wall construction outside Hasbro, Caffé Cucina and the Stihl Shop.

Continued excavating and reconstructing the Visy/Hasbro vehicle crossing.

Completed the cut-in for the watermain outside Kristin School – Phase 2 of 3.

Continued Stormwater works between Wharf Rd and Bass Rd.

Continued clearing, property mitigation and common services trenching work between Summerfield Ln and Bass Rd.

Continued stage 1 bridge works at Days Bridge.

Continued earthworks and pavement construction between Eastbourne Rd and Days Bridge.

Recommenced pavement works between Days Bridge and the Albany Presbyterian Church.

Next week we will:

Continue works at the Rosedale Rd intersection on the eastern side of Albany Highway.

Continue pavement works from 221 Albany Highway to Schnapper Rock Rd.

Continue service relocation works from Appleby Rd to Rothwell Ave.

Continue drainage works from Kristin School Gate 1 heading south.

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement construction.

Continue Stage 1 bridge works at Days Bridge.

Continue Stormwater works between Wharf Rd and Bass Rd.

Continue clearing and common services trenching work between Wharf Rd and Bass Rd.

Continue earthworks and pavement construction between Eastbourne Rd and Days Bridge, and opposite Albany Senior School.

Continue pavement works between Days Bridge and the Albany Presbyterian Church.

Commence removal of overhead services from Appleby Rd to Bush Rd.


17 April


This week we:

Continued works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, and installed the first of the new traffic signal poles.

Continued drainage works from Oakway Drive to Appleby Road on the west side of Albany Highway.

Continued service relocation works from Appleby to Rothwell Avenue.

Continued retaining wall construction outside Hasbro.

Continued stormwater works on Wharf Rd.

Continued scour protection works in Oteha Stream at Days Bridge.

Continued stage 1 bridge works at Days Bridge.

Continued clearing and common service trenching work between Summerfield and Bass Rd.

Next week we will:

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement construction.

Continue drainage works from Oakway Drive to Appleby Road on the west side of Albany Highway.

Continue retaining wall construction outside 265 Albany Highway.

Continue Stage 1 bridge works at Days bridge.

Continue stormwater works between Wharf Rd and Bass Rd.

Continue clearing and common service trenching work between Summerfield and Bass Rd.

Begin trenching for gas pipe protection opposite Albany Senior School.

Continue earthworks for pavement construction between Eastbourne Rd and Days Bridge.

Night works:

Please note that night works are scheduled to continue up to Thursday April 23 as follows:

Service relocations and paving works at Wharf Rd/Eastbourne Rd and Bass Rd/Oaklands Rd intersections.

Asphalting of the Wharf and Bass Rd Roundabouts.

Remarking of lanes between Wharf Rd and Princeton Parade and the roundabouts at Wharf Rd/Eastbourne Rd and Bass Rd/Oaklands Rd intersections.

Asphalt works at Rosedale Intersection on Sunday 19th April.

Watermain works at the Rosedale intersection are scheduled for the week after Anzac weekend.

Ongoing works:

Work in the North Shore Golf Club grounds.

Thrusting for services on the eastern side of Albany Highway from the Appleby Rd / Albany Highway intersection to 265 Albany Highway.

Constructing retaining walls between 225 and 265 Albany Highway.

Looking ahead: 

We are continuing to develop the Rosedale/Albany Highway roundabout in preparation for installing a fully signalised intersection. A temporary roundabout and pedestrian refuges will be in place after the school holidays and these will remain until other works in the area are complete and full signalisation is possible.


10 April


This week we:

Completed drilling power ducts outside Buyers Demolition along the west side of Albany Highway towards Schnapper Rock.

Continued works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, and completed the first section of new road pavement.

Continued drainage works from Oakway Drive to Appleby Road on the west side of Albany Highway.

Removed large trees between Oak Manor Dr and Appleby Rd.

Undertook tree removal along Albany Highway from Rosedale Road to Oak Manor Drive. 

Continued stormwater works on Wharf Rd.

Continued scour protection works in Oteha Stream at Days Bridge.

Continued stage 1 bridge works at Days Bridge.

Continued clearing and common service trenching work between Summerfield and Bass Rd.

Began trenching for gas pipe protection opposite Albany Senior School.


Next week we will:

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement construction.

Continue drainage works from Oakway Drive to Appleby Road on the west side of Albany Highway.

Continue retaining wall construction outside Hasbro and 265 Albany Highway.

Continue Stage 1 bridge works at Days bridge.

Continue scour protection works in Oteha Stream at Days Bridge (weather dependant).

Continue stormwater works on Wharf Rd.

Continue clearing and common service trenching work between Summerfield and Bass Rd.

Continue trenching for gas pipe protection opposite Albany Senior School.


Night works

Please note that night works are scheduled to continue up to Thursday April 16 as follows;

Service relocations and paving works at Wharf Rd/Eastbourne Rd and Bass Rd/Oaklands Rd intersections.

Watermain works at Rosedale Intersection are scheduled for the night of Wednesday April 15.

Ongoing works

Work in the North Shore Golf Club grounds.

Thrusting for services on the eastern side of Albany Highway from the Appleby Rd / Albany Highway intersection to 265 Albany Highway.

Constructing retaining walls between 225 and 265 Albany Highway.

Looking ahead

Over the school holiday break we are working at the Rosedale/Albany Highway roundabout in preparation for installing a fully signalised intersection. A temporary roundabout and pedestrian refuges will be in place after the school holidays and these will remain until other works in the area are complete and full signalisation is possible.


2 April


This week we:

Completed ducting installation from Appleby Road to Bush Road to allow the service provider to commence pulling electrical cables to underground the power.

Commenced drilling power ducts outside Buyers Demolition along the west side of Albany Highway towards Schnapper Rock.

Continued works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, and the installation of the first sections of footpath and new kerb.

Continued drainage works from Oakway Drive to Appleby Road on the west side of Albany Highway.

Continued stormwater works on Wharf Rd.

Continued scour protection works in Oteha Stream at Days Bridge.

Continued stage 1 bridge works at Days Bridge.

Continued clearing and common service trenching work between Summerfield and Bass Rd.

Removed the roundabouts and ancillary islands at Bass and Wharf Rd intersections.

Next week we will:

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting, footpath and pavement construction.

Continue drainage works from Oakway Drive to Appleby Road on the west side of Albany Highway.

Continue retaining wall construction outside Hasbro and 265 Albany Highway.

Continue tree removal along Albany Highway from Rosedale Road to Oak Manor Drive. This will entail some short duration closures of Albany Highway during the day.

Continue Stage 1 bridge works at Days bridge.

Continue scour protection works in Oteha Stream at Days Bridge (weather dependant).

Continue stormwater works on Wharf Rd.

Continue clearing and common service trenching work between Summerfield and Bass Rd.

Begin trenching for gas pipe protection opposite Albany Senior School.

Night works

Please note that night works will continue throughout the site up to Thursday April 16 as follows:

Drainage and ducting works across Albany Highway from Rothwell Avenue to Appleby Road. 

Service relocations and paving works at Wharf Rd/Eastbourne Rd and Bass Rd/Oaklands Rd intersections.

Generally works each week are Sunday to Thursday; however, we are not working through Easter or the night of Thursday 2 April.

Ongoing work

Work in the North Shore Golf Club grounds.

Thrusting for services on the eastern side of Albany Highway from the Appleby Rd / Albany Highway intersection to 265 Albany Highway.

Constructing retaining walls between 225 and 265 Albany Highway.

Looking ahead

Over the Easter school holiday break we plan to be working at the Rosedale/Albany Highway roundabout in preparation for installing a fully signalised intersection. A temporary roundabout and pedestrian refuges will be in place after the school holidays and these will remain until other works in the area are complete and full signalisation is possible.

We plan to be removing trees on Albany Highway opposite Oak Manor Drive during April.


27 March


This week we:

Continued service relocation works near Parkhead Reserve.

Continued works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting and poured the first sections of footpath installation.

Continued drainage works from Oakway Drive to Appleby Road on the west side of Albany Highway.

Continued stormwater works on Wharf Rd and from Wharf Rd to Bass Rd.

Continued stormwater works North of Eastbourne Rd.

Continued undergrounding house connections for power and telephone between Wharf Rd and Bass Rd.

Cleared trees and vegetation between Wharf Rd and Bass Rd.

Began scour protection works in Oteha Stream at Days Bridge.

Continued Stage 1 bridge works at Days Bridge.

Reopened the footbridge in the reserve at the bottom of Wharf Rd.

Next week we will:

Continue service relocation works near Parkhead Reserve.

Continue works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting and poured the first sections of footpath installation.

Continue drainage works from Oakway Drive to Appleby Road on the west side of Albany Highway.

Continue Stage 1 bridge works at Days Bridge.

Continue clearing works between Summerfield and Bass Rd.

Continue scour protection works in Oteha Stream at Days Bridge (weather dependant).

Continue stormwater works on Wharf Rd.

Night works

Please note there will be night works throughout the site Sunday 29 March to Thursday April 16 as follows:

Drainage and Ducting works across Albany Highway from Rothwell Avenue to Appleby Road will take place Sunday 29 March to Thursday 9 April

Roundabout removals and service relocations will take place at Wharf Rd/Eastbourne Rd and Bass Rd/Oaklands Rd Sunday 29 March to Thursday 9 April.

Generally works each week are Sunday to Thursday; however, we are not working through Easter or the Thursday night prior to Good Friday.

Ongoing works

Work in the North Shore Golf Club grounds

Thrusting for services on the eastern side of Albany Highway from the Appleby Rd / Albany Highway intersection to 265 Albany Highway

Constructing retaining walls between 225 and 265 Albany Highway

Looking ahead

Over the Easter school holiday break we plan to be working at the Rosedale/Albany Highway roundabout in preparation for installing a fully signalised intersection. A temporary roundabout and pedestrian refuges will be in place after the school holidays and these will remain until other works in the area are complete and full signalisation is possible.

We plan to be removing trees on Albany Highway opposite Oak Manor Drive during April.


20 March


This week we:

Continued service relocation works near Parkhead Reserve.

Continued retaining walls between 221 and 265 Albany Highway.

Continued trenching for services on the eastern side of Albany Highway from Rosedale Road to Appleby Road.

Continued works at the Rosedale Rd intersection including drainage, water main, gas and communication relocations, lighting and poured the first sections of footpath installation.

Commenced drainage works from Oakway Drive to Appleby Road on the west side of  Albany Highway.

Prepared berm works opposite Albany Senior High School.

Continued stormwater works on Wharf Rd and from Wharf Rd to Bass Rd.

Continued undergrounding house connections for power and telephone between Wharf Rd and Bass Rd.

Continued Stage 1 bridge works at Days Bridge.

Next week we will:

Continue service relocation works near Parkhead Reserve.

Continue retaining walls between 221 and 265 Albany Highway.

Continue trenching for services on the eastern side of Albany Highway from Rosedale Road to Appleby Road.

Continue works at Rosedale Intersection including drainage, water main, gas and communication relocations, lighting and footpath installation.

Continue drainage works from Oakway Drive to Appleby Road on the west side of  Albany Highway.

Continue Stage 1 bridge works at Days Bridge.

Continue clearing vegetation between Wharf Rd and Bass Rd.

Begin scour protection works in Oteha Stream at Days Bridge (weather dependant).

Continue stormwater works on Wharf Rd and from Wharf Rd to Bass Rd. The footbridge in the reserve Rd has been replaced and the new bridge will open next week.

Night works

Due to schedule revisions, we now plan to remove both the roundabouts at Wharf Rd/Eastbourne Rd and Bass Rd/Oaklands Rd, at night, between Sunday 29 March and Thursday April 16. Generally, works each week are Sunday to Thursday, however, we are not working through Easter, the Thursday night prior to Good Friday, or the nights of Easter Sunday and Monday.

Ongoing works

Work in the North Shore Golf Club grounds

Thrusting for services on the eastern side of Albany Highway from the Appleby Rd / Albany Highway intersection to 265 Albany Highway

Constructing retaining walls between 225 and 265 Albany Highway

Service relocations north of Days Bridge and Eastbourne Rd

Looking ahead

Over the Easter school holiday break, we plan to be working at the Rosedale/Albany Highway roundabout in preparation for installing a fully signalised intersection. A temporary roundabout and pedestrian refuges will be in place after the school holidays and these will remain until other works in the area are complete and full signalisation is possible.


27 February


This week we:

Continued construction of the retaining wall outside 265 Albany Highway.

Continued drainage works opposite Oakway Drive including night works.

Continued earthworks, service works and drainage at the Rosedale/Albany Highway intersection.

Continued relocating services at Rothwell Avenue and between Knights Road and Appleby Road.

Continued works at NSGC pond.

Commenced drilling telecommunications ducts from opposite Appleby Road up to the Rosedale Intersection.

Continued excavating pavement to subgrade level opposite Albany Senior School.

Continued common services trenching north of Summerfield Lane.

Continued installing Massey University services relocations.

Began construction of the new footbridge at bottom of Wharf Road.

Removed kerb and channel and redundant light bases opposite the Albany Senior High School.

Constructed a new exit road to our Site compound.

Began piling at Days Bridge.

Next week we will:

Continue construction of the retaining wall outside 265 Albany Highway.

Commence construction of a retaining wall outside Hasbro.

Carry out night works for drainage and services outside 281 Albany Highway and at the Rosedale Intersection.

Continue earthworks, services and drainage at the Rosedale/Albany Highway intersection.

Continue relocating services at Rothwell Avenue and between 265 Albany Highway and Knights Road.

Install concrete protection to the gas main near Days Bridge.

Begin installing subsoil drainage opposite the Albany Senior High School.

Continue stormwater works at the bottom of Wharf Road.

Continue clearing works between Wharf Road and Bass Road.

Install time lapse cameras at three locations to record work progress.

Ongoing works

The footbridge in the reserve at Wharf Rd is now closed and there will be no through-access for pedestrians until mid to late March.

Services investigation work throughout the site.

Ducting works on the eastern side between Rothwell Ave and the northern end of Schnapper Rock Rd.

Work in the North Shore Golf Club grounds.

Trenching for services on the eastern side of Albany Highway from the Appleby Rd / Albany Highway intersection to 265 Albany Highway.

Constructing retaining walls between 225 and 265 Albany Highway.

Relocation of Massey University Services.

Service relocations north of Days Bridge and Eastbourne Rd.

Looking ahead

Over the Easter school holiday break we plan to work at the Rosedale/Albany Highway roundabout in preparation for installing a fully signalised intersection. A temporary roundabout and pedestrian refuges will be in place after the school holidays and these will remain until other works in the area are complete and full signalisation is possible.


20 February


This week we:

Continued construction of the retaining wall outside 265 Albany Highway.

Continued drainage works opposite Oakway Drive.

Continued earthworks, service works and drainage at the Rosedale/Albany Highway intersection.

Continued relocating services at Rothwell Avenue and between Knights Road and Appleby Road.

Continued works at the North Shore Golf Club pond.

Began drainage works at the bottom of Wharf Rd.

Carried out Pile Test Cores at Days Bridge.

Installed a stormwater filter device near the sewer pump station at Days Bridge.

Installed a stormwater catch pit and began excavating the pavement opposite Albany Senior High School.

Began common services trenching north of Summerfield Lane.

Completed common service trenching north of days bridge to the Albany Presbyterian Church.

Next week we will:

Commence drilling a telecommunications duct from opposite Appleby Road up to the Rosedale Intersection.

Commence construction of a retaining wall outside Hasbro.

Carry out night works for drainage and services at Oakway Drive, outside TimberWorld and at the Rosedale Road Intersection.

Continue earthworks, services and drainage at the Rosedale/Albany Highway intersection. 

Continue relocating services at Rothwell Avenue and between 265 Albany Highway and Knights Road.

Begin installing subsoil drainage opposite the Albany Senior High School.

Continue stormwater works south of Days Bridge.

Continue stormwater works at the bottom of Wharf Road.

Continue clearing works between Wharf Road and Bass Road.

Continue installing Massey University services relocations.

Begin undergrounding works for power and telecom for properties between Wharf and Bass Roads.

Commence establishment of equipment for undertaking piling works at Days Bridge.

Ongoing works

The footbridge in the reserve at Wharf Rd is now closed and there will be no through-access for pedestrians until mid to late March.

Services investigation work throughout the site.

Ducting works on the eastern side between Rothwell Ave and the northern end of Schnapper Rock Rd.

Work in the North Shore Golf Club grounds.

Trenching for services on the eastern side of Albany Highway from the Appleby Rd / Albany Highway intersection to 265 Albany Highway.

Constructing retaining walls between 225 and 265 Albany Highway.

Relocation of Massey University Services.

Service relocations north of Days Bridge and Eastbourne Rd.

Looking ahead

Over the Easter school holiday break we plan to be working at the Rosedale/Albany Highway roundabout in preparation for installing a fully signalised intersection. A temporary roundabout and pedestrian refuges will be in place after the school holidays and these will remain until other works in the area are complete and full signalisation is possible.


13 February


This week we:

Finished removing the redundant gas pipe at Days Bridge.

Continued stormwater installation between Eastbourne Rd and Days Bridge.

Began common services between Wharf Rd & Summerfield Lane.

Began construction of the retaining wall outside 265 Albany Highway.

Continued drainage works in Oakway Drive.

Continued earthworks, service works and drainage at the Rosedale/Albany Highway intersection.

Continued relocating services at Rothwell Avenue and between Knights Road and Appleby Road.

Began clearing for a retaining wall outside the Stihl shop at 265 Albany Highway.

Completed excavation for retaining wall footing outside Hasbro.

Began drainage works at the bottom of Wharf Rd.

Next week we will:

Close the footbridge in the reserve at Wharf Rd and there will be no through-access for pedestrians until mid to late March.

Begin Earthworks for pavement widening opposite the Albany Senior High School.

Install a stormwater catch pit opposite Albany Senior High School.

Begin clearing works between Wharf Rd and Bass Rd.

Continue stormwater works near the bottom of Wharf Rd.

Continue earthworks, services and drainage at the Rosedale/Albany Highway intersection. 

Continue drainage works in Oakway Drive. 

Continue relocating services at Rothwell Avenue and between 265 Albany Highway and Knights Road.

Ongoing works:

Services investigation work throughout the site

Ducting works on the eastern side between Rothwell Ave and the northern end of Schnapper Rock Rd

Work in the North Shore Golf Club grounds

Trenching for services on the eastern side of Albany Highway from the Appleby Rd / Albany Highway intersection to 265 Albany Highway

Constructing retaining walls between 225 and 265 Albany Highway

Relocation of Massey University Services

Service relocations north of Days Bridge and Eastbourne Rd

Looking ahead:

Over the Easter school holiday break we plan to be working at the Rosedale/Albany Highway intersection in preparation for installing traffic signals at a later date.


5 February


This week we:

Installed a sewer diversion outside the site compound near Days Bridge.

Continued preparing for piling at Days Bridge.

Hydro investigated the existing services between Wharf Rd and Bass Rd.

Completed the stormwater outlet near the sewer pump station at Days Bridge.

Continued drainage works in Oakway Drive.

Continued earthworks, service works and drainage at the Rosedale/Albany Highway intersection.

Continued relocation of transformers at the Rosedale Intersection.

Commence clearing for a retaining wall outside Hasbro.

Next week we will:

Finish removing the redundant gas pipe at Days Bridge.

Continue new stormwater installation between Eastbourne Rd and Days Bridge.

Continue earthworks, services and drainage at the Rosedale/Albany Highway intersection. 

Continue drainage works in Oakway Drive. 

Continue relocating services at Rothwell Avenue and between Knights Road and Appleby Road.

Commence construction of the retaining wall outside 265 Albany Highway.

Commence clearing for a retaining wall outside the Stihl shop at 265 Albany Highway.

Ongoing works:

Services investigation work throughout the site.

Ducting works on the eastern side between Rothwell Ave and the northern end of Schnapper Rock Rd.

Work in the North Shore Golf Club grounds.

Trenching for services on the eastern side of Albany Highway from the Appleby Rd / Albany Highway intersection to 265 Albany Highway.

Constructing retaining walls between 225 and 265 Albany Highway.

Earthworks between Days Bridge and Eastbourne Rd.

Relocation of Massey University Services.

Service relocations north of Days Bridge and Eastbourne Rd.

Looking ahead:

From February 16 we plan to replace the footbridge in the reserve at Wharf Rd and there will be no through-access for pedestrians for approximately one month until this work is complete.

Over the Easter break we plan to be working at the Rosedale/Albany Highway intersection in preparation for installing traffic signals at a later date.


30 January


This week we:

Completed drainage works within Kristin School grounds.

Commenced drainage works in Oakway Drive.

Removed trees at Rosedale Roundabout.

Commenced drainage works at Rosedale roundabout.

Continued excavating for the retaining wall outside 265 Albany Highway.

Continued relocating services at Rothwell Avenue and between Knights Road and Appleby Road.

Commenced relocation of transformers at the Rosedale Intersection.

Commenced service relocations north of Days Bridge and Eastbourne Rd.

Next week we will:

Continue earthworks at the Rosedale/Albany Highway intersection.

Continue drainage works on Albany Highway at the Rosedale Rd intersection.


2014


18 December


This week we

Moved traffic onto the western side of Albany Highway between Wharf Road and Days Bridge.

Carried out service investigation works at night at the Rosedale/Albany Highway roundabout.

Demolished the wing walls on Days Bridge.

Next week we will

Continue stormwater works at Kristin School/North Shore Golf Club. Please note that this work will continue throughout the Christmas period to late January.

Gate 1 at Kristin School is closed to enable these works within the school grounds.  Please use Gate 2 for the Middle and Senior Schools and Gate 4 on Bass Rd for the Junior School and Administration.

The Albany Family Medical Centre can be accessed directly from Albany Highway.

Ongoing works

Services investigation work throughout the site.

Drainage works at 221 Albany Highway.

Ducting works on the eastern side between Rothwell Ave and the northern end of Schnapper Rock Rd.

Establishing the works compound area opposite the Albany Senior College. 

Constructing retaining walls between 225 and 265 Albany Highway.

Gas pipe diversion works by Days Bridge.

Looking ahead

In the New Year we will be digging a trench for services on the eastern side of the highway from the Appleby/Albany Highway intersection to 265 Albany Highway.

In mid-January we will be trenching at night across Rothwell Ave.

During January we plan to remove the Rosedale/Albany Highway roundabout and replace it with a smaller temporary roundabout. 

In early February we plan to carry out drainage works in Oakway Drive.

Over the Easter break we plan to be working at the Rosedale/Albany Highway intersection in preparation for installing traffic signals at a later date.


12 December


This week we

Set up to move traffic onto the western side of Albany Highway between Wharf Road and Days Bridge.

Started stormwater works at Kristin School/North Shore Golf Club.

Started ducting works on the eastern side between Rothwell Ave and the northern end of Schnapper Rock Rd.

Lifted the gas pipe into place at Days Bridge.

Re-opened the pedestrian path to Lucas Creek from Days Bridge.

Next week we will

Carry out service investigation works at night at the Rosedale/Albany Highway roundabout.

Work at night installing concrete barriers beside our works area between Days Bridge and Wharf Rd. 

Close Gate 1 at Kristin School to enable works within the school grounds; please use Gate 2 for the Middle and Senior Schools and Gate 4 on Bass Rd for the Junior School and Administration.

Ongoing works

Services investigation work throughout the site.

Drainage works at 221 Albany Highway.

Establishing the works compound area opposite the Albany Senior College. 

Constructing retaining walls between 225 and 265 Albany Highway.

Gas pipe diversion works by Days Bridge.

Looking ahead

In the New Year we will be digging a trench for services on the eastern side of the highway from the Appleby/Albany Highway intersection to 265 Albany Highway.

At the end of January 2015 we plan to remove the Rosedale/Albany Highway roundabout and replace it with a smaller temporary roundabout.

Over the Easter break in 2015 we plan to be working at the Rosedale/Albany Highway intersection in preparation for installing traffic signals at a later date.


5 December


This week we

Removed trees near Rothwell Ave as part of stormwater works at the North Shore Golf Club.

Continued to set up for the gas main diversion across the Oteha Stream.

Continued widening the northbound lane on the western side of Albany Highway between Wharf Road and Days Bridge, so traffic can be moved over next week.

Continued services investigation work throughout the site.

Continued drainage works at 221 Albany Highway.

Continued establishing the works compound area opposite the Albany Senior College. Portable offices are now on site.

Continued constructing retaining walls between 225 and 265 Albany Highway.

Next week we will

Continue constructing retaining walls between 225 and 265 Albany Highway.

Continue drainage works at 221 Albany Highway. 

Continue setting up the works compound area opposite the Senior High School on Albany Highway.

Start stormwater works at Kristin School/North Shore Golf Club.

Start ducting works on the eastern side between Rothwell Ave and the northern end of Schnapper Rock Rd.

Asphalt the northbound lane on the western side of Albany Highway between Wharf Road and Days Bridge, so traffic can be moved over. 

Lift the gas pipe into place at Days Bridge.

Temporarily close the Days Bridge end of the Lucas Creek path. Walkers please follow the signs and detour via Widdison Place.

Looking ahead

In the New Year we will be digging a trench for services from the eastern side of the Appleby/Albany Highway intersection to 265 Albany Highway.

At the end of January 2015 we plan to remove the Rosedale/Albany Highway roundabout and replace it with a smaller temporary roundabout.

Over the Easter break in 2015 we plan to be working at the Rosedale/Albany Highway intersection in preparation for installing traffic signals at a later date.


28 November


This week we

Worked at night pavement sampling at the Rosedale intersection. 

Continued services investigation work throughout the site.

Installed new line marking near the Rothwell and Albany Highway intersection.

Installed an access road for Christmas storm water works at the North Shore Golf Club.

Continued drainage works at 221 Albany Highway.

Installed a haul road and stripped topsoil in preparation for constructing retaining walls between 225 and 265 Albany Highway.

Continued establishing the works compound area opposite the Albany Senior College.

Next week we will

Continue constructing retaining walls between 225 and 265 Albany Highway.

Continue drainage works at 221 Albany Highway.

Remove trees near Rothwell Ave and as part of stormwater works at the North Shore Golf Club.

Continue setting up the works compound area opposite the Senior High School on Albany Highway.

Continue works widening the northbound lane on the western side of Albany Highway between Wharf Road and Days Bridge, so traffic can be moved over.

Set up for the gas main diversion across the Oteha Stream.

Looking ahead

Before and after Christmas we will be working inside the grounds of Kristin School thrusting a new Storm Water line under the North Shore Golf Club greens.

Over the Easter break in 2015 we plan to be working at the Rosedale/Albany Highway intersection in preparation for installing traffic signals at a later date.


21 November


This week we:

Continued services investigation work throughout the site.

Cleared trees on the eastern side from Bush Rd to 225 Albany Highway.

Continued drainage works at 221 Albany Highway.

Installed a haul road and stripped topsoil in preparation for constructing retaining walls between 225 and 265 Albany Highway.

Removed fencing, vegetation and topsoil near Days Bridge.

Installed temporary pedestrian fencing on the eastern side of Days Bridge.

Installed erosion and sediment protection near Days Bridge.

Continued establishing the works compound area opposite the Albany Senior College.

Next week we will:

Work at night pavement sampling at the Rosedale intersection. The intersection will remain open but traffic controls will be in place.

Continue services investigation works and pavement sampling throughout the site.

Install new line marking near the Rothwell and Albany Highway intersection.

Install an access road for  Christmas storm water works at the North Shore Golf Club.

Start constructing retaining walls between 225 and 265 Albany Highway.

Continue drainage works at 221 Albany Highway.

Continue setting up the works compound area opposite the Senior High School on Albany Highway.

Widen the northbound lane on the western side of Albany Highway between Wharf Road and Days Bridge, so traffic can be moved over.

Looking ahead

Before and after Christmas we will be working inside the grounds of Kristin School thrusting a new Storm Water line under the North Shore Golf Club greens.

Over the Easter break in 2015 we plan to be working at the Rosedale/Albany Highway intersection in preparation for installing traffic signals at a later date.


14 November


This week we:

Started setting up our compound area opposite the Senior High School on Albany Highway.

Continued services investigation work and pavement sampling throughout the site.

Closed the Days Bridge underpass in preparation for service relocations.

Cleared trees near Days Bridge.

Cleared trees on the eastern side from Bush Rd to 225 Albany Highway.

Started drainage works at 221 Albany Highway.

Next week we will:

Continue services investigation works and pavement sampling throughout the site.

Strip topsoil and begin constructing retaining walls between 225 and 265 Albany Highway.

Continue drainage works at 221 Albany Highway. 

Remove fencing, vegetation and topsoil near Days Bridge. Install temporary pedestrian fencing on the eastern side of Days Bridge.

Continue setting up our compound area opposite the Senior High School on Albany Highway.

Looking ahead

Before and after Christmas we will be working inside the grounds of Kristin School thrusting a new Storm Water line under the North Shore Golf Club greens.

Over the Easter break in 2015 we plan to be working at the Rosedale/Albany Highway intersection in preparation for installing traffic signals at a later date.


24 October


AT has reviewed and amended plans for the lane configuration on the Albany Highway North project. This is due to further study of future bus movements and efficient use of the transit lanes. 


1 October


Open days on the Albany North upgrade project will be held at Kristin School at 360 Albany Highway at the end of this month.


28 August


The main construction work on the Albany North upgrade project is scheduled to commence in November 2014. Read the media release here.

Sign up for our newsletter

Sign up for the Albany Highway north upgrade newsletter

Albany Highway south

The Albany Highway south project has been put on hold at this stage.


For more information

Contact Auckland Transport