2017

11 May - C3 Stations and Tunnels Expressions of Interest (EOI) invited

On 11 May 2017 the EOI for the C3 Stations and Tunnels was issued to invited Respondents.

11 May - C6 RFT released

The C6 Mt Eden Stormwater Main Relocation RFT has been released. The notice was advertised on Tenderlink (Ref: AKTSPT-765220) and GETS (ref: 18601130) on 28 April.

Interested organisations proving to be viable tenderers who registered with CRLL were granted access to AWARD, the tender portal software on 11 May.

The C6 RFT closes on 22 June 2017.

8 May - C3 Pre Qualification outcome

The C3 Stations and Tunnels Pre Qualification phase is complete and 8 respondents will be invited to proceed to the RFT phase. The 8 respondents are:

  • Acciona Infrastructure New Zealand Limited.
  • Bam International Australia Pty Limited.
  • China Machinery Engineering Corporation (CMEC) JV.
  • CPB Contractors Pty Limited.
  • Ferrovial Agroman (New Zealand) Limited.
  • Salini Impregilo S.p.A.
  • The Fletcher Construction Company Limited.
  • Vinci Construction Grands Projects S.A.S (VCGP) JV.

24 April - C7 EOI tender evaluation complete

The C7 Systems, Integration, Testing and Commissioning Expression of Interest (EOI) tender evaluation is complete and 3 respondents have been shortlist to proceed to the RFT phase. 

The shortlisted respondents are:

  • John Holland (NZ) Ltd.
  • Laing O'Rourke Australia Construction Pty Ltd.
  • RCR (Infrastructure) NZ Ltd.

11 April - C3 Pre-Qualification Evaluation outcome

On 1 March 2017 the C3 Pre-Qualification tender closed. 10 submissions were received. The evaluation is complete and 8 respondents have qualified to proceed to the next tender phase - the Expression of Interest (EOI) phase. The C3 EOI will be released soon.

20 February 

On 20 February 2017 the C7 Systems, Integration, Testing and Commissioning Expression of Interest (EOI) tender closed. 8 submissions were received.

3 February - Pre Qual invited for C3 Stations and Tunnels 

On 1 February 2017 the invitation to submit a Pre Qual for the C3 Stations and Tunnels was issued. 

Interested parties should refer to Tenderlink / GETS for documentation. The Tenderlink reference is AKTSPT-754861.

CRL Ltd is using the AWARD software for managing the tender process for this Pre Qual. The AWARD system will be the portal used for tender notifications. Respondents must register by emailing crlprocurement@at.govt.nz for access and to be set up for the AWARD software.

The registration email must include:

  • Company/consortium name.
  • User's full name.
  • User's position or role within the company/consortium.
  • User's email address.

Submissions are to be made via AWARD software. Details of this are included in the C3 Pre Qual documentation.

To be considered for the C3 Pre Qual suppliers must prequalify through this process. CRL Ltd tenders will not be using Auckland Transport’s Prequalification Register. All CRL Work Packages will be tendered as separate contracts and contractors will need to prequalify through the CRL Ltd process.

20 January - C7 Expression of interest (EOI) released

On 18 January 2017 the invitation to submit an EOI for the C7 Systems, Integration, Testing and Commissioning was issued.

Interested parties should refer to Tenderlink / GETS for the documentation. The Tenderlink reference is AKTSPT-753390.

CRL Ltd is using the AWARD software for managing the tender process for this EOI. The AWARD system will be the portal used for tender notifications. Respondents must register by emailing crlprocurement@at.govt.nz for access and to be set up for the AWARD software.

The registration email must include:

  • Company/consortium name.
  • User's full name.
  • User's position or role within the company/consortium.
  • User's email address.

Submissions are to be made via AWARD software. Details of this are included in the EOI documentation. 

19 January - CRL milestone achieved

The CRL has reached a major milestone with the first city to Mt Eden contract documents being sent to the industry. 