Skip to Main Content
Auckland Transport

Tamaki Dr Ngapipi Rd project updates Tamaki Dr Ngapipi Rd project updates

2018


5 July

Tamaki Drive - Ngapipi Road intersection work is almost complete

New road layout will be operational soon.

Traffic signals will be switched on during July school holidays.

Monitoring of intersection in early weeks of signals switched on to ensure traffic flow and light phasing is optimised.

Please take care travelling through the intersection and look out for pedestrians and cyclists.

Thank you for your patience and understanding while we worked to get the job done.

Fulton and Hogan staff thumbs up on Tamaki Dr web 


23 April

Project Update Tamaki Dr Ngapipi Rd Intersection

In this update:

  • Progress so far
  • Tamaki Drive works
  • Ngapipi Road works
  • New footpath layout
  • Upcoming night works
  • Ngapipi Bridge maintenance

Progress so far

Tamaki Dr, Ngapipi aerial view

The safety improvement works at one of Auckland’s highest risk intersection is progressing well. Stage 2 that involves the realignment of the seawall along the coastal edge is almost complete and the upgrade of footpath and pavement is now about to get underway.

Our progress over the last 6 weeks:

  • Completed 95% of the new seawall.
  • Installed all underground utility services and will begin relocation of the street light columns.
  • Formed the foundation of the bus stop near the boat sheds.
  • Completed all the underground ducting for the traffic signals.
  • Completed all drainage works for both Tamaki Drive and Ngapipi Road.

Tamaki Drive works

Coastal work complete

It has been six months in the making and now the seawall along Tamaki Drive is complete. It involved building the embankment with rocks and layering a concrete blinding over it. Stonemasons then installed the basalt stone facing and did the detailed ‘pointing’ or filling in between the stones with concrete grout to match the adjacent seawall.

At the edge of the new seawall, precast wave reflection walls, each weighing 5 tonnes, were carefully manoeuvred into place. These walls will reduce waves topping over onto the road.

The inside of the sea wall forms the new shared path.

Prepping for the shared path

We are now building up the embankment to the finished level of the shared path. Concrete for the first section of the path closest to the seawall will be poured in a couple of weeks.

Once concrete is poured and set, this section of the shared path will open to the public

Caption: Once concrete is poured and set, this section of the shared path will open to the public

Street lighting

A number of streetlights will be relocated to suit the new road layout. The foundations for the streetlight columns are being built in their new positions.

We are aware that some of the streetlights along Tamaki Drive are not working. The issue is related to a localised power outage, which Vector is working to resolve the fault. During this time, two mobile lighting units are onsite to provide temporary light for the intersection, until power is restored. Please drive to the conditions and approach the work site carefully.

Ngapipi Road works

The rock facing of the sea wall is complete, with the wave reflection wall being formed.

The original bus shelter has come out of storage and is going back to the same bus stop location near the boat sheds. 

Ngapipi Road seawall

Caption: Ngapipi Road seawall

Ngapipi Road seawall and future shared path

Caption: Ngapipi Road seawall and future shared path

New path layout for Tamaki Drive

Once the concrete for the shared path closest to the seawall is poured and set, we will open this section up to the public. It will be the first opportunity for pedestrians and people on bikes to be close to the seawall edge since construction commenced.

Work to widen the road and to build the remaining half of the shared path will start soon. For this next phase of construction, we are closing the existing footpath and switching to a new path alignment on 23 April.

New crossing points

There are new crossing points to get across Tamaki Drive and Ngapipi Road. Currently there is a gap between the road barriers allowing people to cross from the seaside of Tamaki Drive to the other.
This gap is closing because with the new kerbside work starting, people would otherwise walk straight into the construction zone.

For safety, people will be directed to walk further along (up to two minutes’ walk) to the new crossing points.

Map- crossing

Please cross with care and watch out for traffic and people on bikes.

Ngapipi Bridge maintenance

We will soon begin some maintenance work on the underside of Ngapipi Bridge. Majority of the work will be done by using a barge for the maintenance crew and equipment.

At some stages of the work, boats entering and exiting the marina will be required to change the navigation lanes. These changes will be advised in advance.

There is no impact on Tamaki Drive users. Maintenance is being done during the winter months when boat traffic is lighter and is expected to take 3 months to complete.


26 January

January works update

Working to schedule, the construction team completed essential work near Ngapipi Bridge, poured concrete for the new shared path, and reopened the road as planned. 

Tamaki bridge concrete pour

Image: Pouring concrete to form the shared path for cyclists and pedestrians.

Ngapipi Road works

In early January, the foothpath, kerb and channel, and a small part of the sea wall was removed for the future shared path.

Near the water’s edge, we are building an 800mm extension to the existing sea wall. This will form the edge of the shared path. We are also installing a ground beam that will tie back the existing wall.

We acknowledge that there were delays to traffic during the morning peak, especially for Ngapipi Road drivers.

We did consider using STOP/GO or temporary signals to facilitate traffic movements, however, it was unlikely temporary signals would make any improvement except to increase the demand from Ngapipi Road (which was mostly being re-routed to Shore Road). Alternatively, drivers that would use Ngapipi Road instead joined Tamaki Drive from other access streets ahead of the intersection.

Tamaki bridge side January 2018 2

Image: Looking towards Ngapipi bridge, footpath and kerb dug up.

Tamaki bridge side January 2018

Image: From Ngapipi bridge, footpath and kerb dug up.

Bridge from Ngapipi January 2018

Image: Near abutment of bridge, preparations to put an extra 800mm above the existing sea wall.

Tamaki Drive works

The partially-constructed seawall on Tamaki Drive held up during the recent stormy weather. There are still more stones to be laid before the embankment and seawall are complete.

On the road-side edge of the embankment, a wave wall to reduce waves topping over is still to come. The old kerb from this section was removed and stored away. When the embankment is complete, the old kerb will go back in.

Progress after 5 months
  • Footpath work (Stage 1) completed ahead of schedule.
  • Formed the foundation of the new seawall along Ngapipi Road.
  • Installed new underground drainage pipes across Tamaki Drive to Ngapipi Road.
  • Installed underground electric services for lighting and traffic signals.
  • Environmental monitoring and compliance of the site by specialist arborists and ecologists.

8 January

When work recommences after the Christmas break on 8 January, the plan is to focus on completing the work adjacent to Ngapipi Bridge, particularly at the south-west corner. To enable this, a new road layout will be implemented from 8 January 2017 (weather permitting) until 31 January 2018.

How this will affect you and what to watch for

  • We will maintain all existing traffic movements at the intersection. However, the left turn traffic from Ngapipi Road will need to give traffic on Tamaki Drive for this period. 
  • In late November/early December, we have made some minor re-alignment to our layout on Ngapipi Road to accommodate drainage works on the eastern side.
  • After Christmas when the traffic is at its lightest, we are planning to temporarily change the left free turn from Ngapipi Road to Tamaki Drive to a give way. This is required to accommodate the work adjacent to the bridge abutment. Ngapipi Road traffic will need to give way to traffic on Tamaki Drive during this period. 
  • During summer, there are more pedestrians and cyclists along Tamaki Drive. Please approach the work site safely and watch out for all users at this intersection.

Tamaki Dr Ngapipi Rd intersection works stage 2 map

Map of changes to Tamaki Drive and Ngapipi Road intersection.


2017


5 December

From 5 to 7 December 2017, we will be undertaking night drainage works.

This will include a partial road closure with stop/go signage in operation. Work hours are between 7pm and 5am. If work is delayed, it will roll to the next fine night.

There will be some light and heavy machinery noise and truck movements associated with this work and we apologise for any disruption this may cause.

Cyclists are urged to take extreme caution as temporary steel plates on the road may be slippery. These plates will be removed by the end of the week.


22 November

We are planning to do night drainage work between Sunday 26 and Tuesday 28 November (weather permitting).

This will include a partial road closure with go/stop signage in operation. Work hours are between 7pm and 5am.

If work is delayed, it will roll to the next fine night. 


15 November

The seawall construction on Tamaki Drive is progressing well with over half of the embankment formed since we started the marine works in October. Our stonemasons will be on site later this week to start building the new seawall facing along Tamaki Drive using basalt stones.

We will also continue with our work along the coastal edge of Ngapipi Road including the formation of the embankment for the new shared path.

Seawall construction on Tamaki Dr Ngapipi Rd intersection

Looking ahead

Based on our current progress, we will have the majority of the seawall completed up to the intersection before Christmas and our site office will be closed for 2 weeks between 23 December and 7 January for Christmas/New Year break.

Specific feedback 

  • Road layout over the Christmas break. Based on our current progress, we will have the majority of the seawall completed up to the intersection before Christmas. Our site office will be closed for two weeks between 23 December and 7 January for Christmas/New Year break. We will maintain the current road layout over the break. While the site office will be closed for Christmas, our site traffic management supervisor will undertake regular monitoring of the site. A new road layout will be implemented from 8 January 2018 (weather permitting) until 31 January 2018.
  • Questions about why the change to the road layout is done in January and if this work would be better done under the current temporary traffic layout. We have explored a number of options to undertake the work adjacent to the bridge abutment. However, there is inadequate space to accommodate two lanes of traffic towards the city and footpath; while maintaining a safe working area adjacent to the bridge. As a result, the city bound approach to the bridge will reduce to a single lane. For this to work, traffic turning out of Ngapipi Road will need to operate under a give way control. This will only be for the month of January when traffic is lightest.
  • Enquiry about what the road layout will be in February 2018. We will resume the current road layout on 1 February 2018 with two citybound traffic lanes and a free left turn from Ngapipi Road.

22 September

Stage 2 works

Tamaki Drive – Ngapipi Road intersection works are running ahead of schedule. We are starting stage 2 four weeks early.

The road layout will change during stage 2 works.

Road layout changes from 26 September

Weather permitting, a new road layout will be in place from Tuesday, 26 September. It will have the same number of lanes, but these will narrow on the approach to Ngapipi Road.

The speed limit will be reduced to 30km/h and traffic delays can be expected. Please approach the intersection with care and watch out for pedestrians and cyclists.

Pedestrian and cycling facilities will also be retained, but the shared path on Tamaki Drive and footpath on Ngapipi Road will also narrow.

Tamaki Dr Ngapipi Rd intersection works stage 2 map


12 September

Ngapipi bridge widening

We want your feedback on a proposal to widen Ngapipi bridge to provide new footpaths and convert the existing footpaths into cycleways.

Feedback is open until 8 October.

Find out more and have your say.


Night works next week

On Sunday 17, Monday 18, and provisionally Tuesday 19 September, we will be working at night to install a new drainage pipe across Tamaki Drive.

This work is scheduled to take place at night (from 7pm to 5am) as the traffic volumes are too high during the day to do it safely.

This work is weather dependent and will be rolled to the next fine night if impacted by weather.

There will be some noise and truck movement associated with this work and we apologise for any disruption this may cause.


8 September

Work for Stage 1 is now well underway.

Tamaki Dr cyclist using cycle lane

What we did last week

Removed existing footpath and kerb & channel along the south side of Tamaki Drive and east of Ngapipi Road.

Happening this week

  • Continue footpath and kerb & channel renewal along the south side of Tamaki Drive and east of Ngapipi Road.
  • Commence service installation including drainage upgrades.

Watch out for

For safety reasons, the stairs linking Paritai Drive to Tamaki Drive will be closed later this week for up to a month as we install new kerb & channel and footpath at the corner.  Pedestrian detours are sign posted via Paritai Drive/Ngapipi Road and/or Paritia Drive/Okahu Street.

As a live construction site, the speed limit has been reduced to 30km/h and traffic delays can be expected. Please approach the intersection with care.


21 August

Stage 1 construction begins on Monday and Tuesday nights (21 and 22 August), with the removal of the traffic island at the intersection to create room for lane realignment.

The hours of work are 7pm to 5am, weather permitting. Traffic will be managed by stop-go signals.

There will be some associated noise and truck movement and we apologise for any disruption.

Get more construction details.


1 August

Work will start later this month on the footpath along Tamaki Drive and Ngapipi Road. Work will then begin on extending the seawall.

The upgrade should take 12 months to complete.


7 June

AT is currently in the process of engaging a suitable contractor for the intersection upgrade work.

We expect to begin construction in mid 2017.


2016


24 September

Submissions on the resource consent application have closed.

A decision is expected in early 2017.


18 August

AT has applied to Auckland Council for the resource consent for the intersection upgrade. The consent application has been notified, which means you can make a submission.

Submissions are open until 23 September.

If you are experiencing family violence, don't worry, the information within this pop-up won't appear in your browser's history.

enter
Privacy policy

We’ve made asking for help safer than ever.

Join us in standing up against domestic violence and making more places of refuge across the internet.

If you, your business or your agency want to have The Shielded Site tab on your site we’ve made adding it very easy.

Click here to find out more. (WARNING: this will take you away from our shielded portal.)

NEED MORE ANSWERS

If you are living in fear in your relationship or in your family, there are so many ways we can help you right now. You won’t be turned away even if you don’t have children, a NZ visa, or money. If you still have more questions have a read below and contact us when you’re ready.

I’m ready to talk now.

You can call our 24-hour support and crisis line on 0800 REFUGE (733843). Or, if you prefer, you can click here and contact us discretely through our contact form and we will email you back as soon as possible.

What will I do for money?

There are a number of benefits and allowances you may be eligible for if you are a victim of domestic violence in New Zealand. We can help you better understand your options once you make contact.

I haven’t been beaten up, can Women’s Refuge still help me?

We support women who have experienced any form of domestic violence: verbal, psychological/emotional, sexual, and financial as well as physical. In fact, psychological/emotional abuse is the most common form of domestic violence.

How much does it cost to stay?

Women's Refuge support and advocacy services are free. In the safe house, rent is usually charged once your financial situation is sorted out. Safety is our main concern. You won't be turned away if you don't have any money.

How long can I stay in a safe house?

Some women only stay a night or two, while others stay for weeks. You can talk with the advocates at your local refuge about how long you think you need to stay to ensure your safety.

I don’t live with my partner, but he is abusing me. Can you still help me?

Yes, you don’t have to be living with your partner to experience domestic violence and you can still call us.

What happens if I haven't got any clothes or food?

Women's Refuge has clothing that you can have. We’ve also got toys and books, formula and nappies. You are welcome to use our emergency food until you get your financial situation sorted out.

Will other people be there?

Safe houses usually have other women, including women with their children, staying there. Refuge advocates are around during the day.

How will I get my kids to school?

The advocates at your local refuge will help you work out transport for your children, or help with changing schools.

Can Women's Refuge help me if I stay in my own house?

Yes, we can provide all the same support and advocacy for you no matter where you choose to live. You may be eligible to access support through the Whanau Protect service.

I'm living in a rural area. Can you still help me?

Yes. Find your local refuge and they will be able to arrange support, advocacy and transport for you.

Can Women's Refuge help around issues with children?

Yes. We can provide support and advocacy around matters to do with custody, access and care.

BEING SAFE ONLINE

The safest way to browse the internet if you suspect your browsing history is being monitored, is to use your browser’s private or incognito mode.

If you suspect your device has been compromised by spyware, then you should use consider using another device as some spyware may still be able to monitor icognito sessions.

To activate a private browsing session, follow the instructions below.

Safari

Open Safari > go to the File menu > select New Private Window

When finished, don’t forget to close your browser window to ensure your safety and privacy.

Chrome

Open Chrome > go to the triple-dot menu (top right of your browser's window) > select New Incognito Window

Internet Explorer

Open IE > click the Tools button > select Safety > and then click InPrivate Browsing

Mozilla Firefox

Open Firefox > click the menu button ☰ > and then click New Private Window

You should see a message in the new window saying that you are now browsing privately.

When finished, don’t forget to close your browser window to ensure your safety and privacy.

Getting out

The most important thing is for you and your children to get out safely. It is important to know that leaving a violent relationship can be one of the most dangerous times for women and children so it is important to make a safety plan around leaving and keep your plans confidential. Below are some tips to help you make a plan.

  • If you can, pack a bag with bare necessities and important documents that you can leave with someone you trust. Include important documents such as passport, birth certificate, bank account details, driver’s licence, and bank cards and other things like medicines.

  • Know abuser's schedule and safe times to leave.

  • Contact us for guidance or a safe place to stay for you and your children.

Getting help

We warmly welcome all women and their children to access our support, advocacy and crisis accommodation. If you need help or have questions, use our live chat to get in touch.

making a plan

The safety of you and your children (if you have them) will be your primary concern. If you’re not ready or cannot safely leave, here are some things you can do to stay safe now.

  • Make a safety plan with the guidance of a refuge advocate.

  • Get yourself a pre-paid phone; keep it charged and safe.

  • Keep photocopies of important documents (passport, birth certificate, bank account details, medical notes, driver's licence, etc) and store these at the home of a supportive friend or family member.

  • Keep a journal of all violent incidents, noting dates and events.

  • If you can, open your own bank account and try to save some money.

  • If you have pets you are worried about, consider them in your safety plan.

Privacy Policy – The Shielded Site Application.

General

In this privacy policy, the terms ‘NCIWR’, ‘we’, ‘us’, and ‘our’ refer to National Collective of Independent Women’s Refuges Inc. NCIWR operates this web application at https://d3f5l8ze0o4j2m.cloudfront.net (‘this web application’).

This privacy policy explains how we may collect, store, use, and disclose personal information that we collect and that you provide to us. By using this web application you acknowledge that we may collect, store, use, and disclose your personal information in the manner set out in this privacy policy.

Collection of personal information

We may collect personal information from you when you use this web application, for example when you make a request for contact on this web application.

You may decide not to provide your personal information to us. However, if you do not provide it, we may not be able to provide you with access to certain information or services. For example, we may be unable to make contact with you if you do not provide us with your contact information.

Automated collection of non-personal information

When you visit this web application, we will not add traceable elements (such as cookies, sessions, and usage monitoring software) to your browser or device.

Use and disclosure

We will not use or disclose your personal information except in accordance with this privacy policy or the Privacy Act 1993. We may use your personal information to:

  • assist in providing information and services requested by you;

  • communicate with you

Your personal information will only be made available internally for the above purposes. We will not disclose your personal information to third parties. We will only use or disclose personal information that you have provided to us, or which we have obtained about you:

  • for the above-mentioned purposes;

  • if you have otherwise authorised us to do so;

  • if we have given you notification of the intended use or disclosure and you have not objected to that use or disclosure;

  • if we believe that the use or disclosure is reasonably necessary to assist a law enforcement agency or an agency responsible for national security in the performance of their functions;

  • if we believe that the use or disclosure is reasonably necessary to enforce any legal rights we may have, or is reasonably necessary to protect the rights, property and safety of us, our customers and users, or others;

  • if we are required or permitted by law to disclose the information; or

  • to another entity that carries on the business of operating this web application.

Storage and security

All personal information collected on this web application is collected and held by NCIWR. We will endeavour to protect your personal information that is held by us from unauthorised access, use, disclosure, alteration, or destruction.

Third party service providers

This website may be hosted by one or more third party service providers (‘service providers’) who enable us to provide this web application. You acknowledge and agree that any personal information that may be collected on this web application may also be held and used by our service providers on our behalf. Any information collected will be securely sent and securely stored on a server.

Third party websites

This web application may be hosted by websites operated by third parties. We are not responsible for the content of such websites, or the manner in which those websites collect, store, use, or distribute any personal information you provide. When you visit third party websites from hyperlinks displayed on this web application, we encourage you to review the privacy statements of those websites so that you can understand how the personal information you provide may be collected, stored, used, and distributed.

Right to access and correct

You may request access to, or correction of, any personal information we hold about you by contacting us as follows:

Email:info@refuge.org.nz
Post:Privacy Officer
NCIWR
PO Box 27-078
Marion Square
Wellington 6141

To ensure that the contact information we hold about you is accurate and current, please notify us of any changes to such information as soon as possible.

Contacting NCIWR

Any emergency relating to domestic violence should be directed to 111 for New Zealand Police assistance.

If you request assistance through this website, we will endeavour to respond as soon as we can. If you require advocacy services phone 0800 REFUGE or 0800 733 843 to talk to a refuge in your area within New Zealand. All member refuges of NCIWR are listed on our main website (www.womensrefuge.org.nz). If you do visit the Women’s Refuge Website, please note that it is a traceable site so we recommend you use the online safety tips found on this web application to visit www.womensrefuge.org.nz safely.

Advocacy services are available at member refuges. Your call and information will be treated in confidence and privacy.

Changes to our privacy policy

We reserve the right, at our discretion, to alter this privacy policy at any time. Changes to this privacy policy will take effect immediately once they are published on this web application. Please check this privacy policy regularly for modifications and updates. If you continue to use this web application or if you provide any personal information after we post changes to this privacy policy, this will indicate your acceptance of any such changes.

This privacy policy was last updated on 6 October 2015.

If You’re In
Immediate danger
CALL 111 IMMEDIATELY

If you fear for your safety:

  1. Run outside and head for where there are other people.
  2. Ask someone to call 111
  3. If you have children take them with you if you can
  4. Don't stop to get anything else
Close