Skip to Main Content
Auckland Transport

Pukekohe Station project updates Pukekohe Station project updates

2018

20 May

Construction across the entire project is progressing well and is on target for the opening of the new bus and train facilities from midday (12pm) on Wednesday 6 June. This will include the new park’n ride area, station platform, bus lane and bus shelter and the Station Road carpark.

The overbridge is mostly complete and will be opened to the public in late July after the existing overbridge has been removed in the scheduled block of lines on the weekend of 14 and 15 July.

Please note: For customers requiring step free/mobility access, please continue to use the Station Road access until the new overbridge is opened in late July 2018.

Park’n ride area

All elements including the carpark, new toilets, bus lane, landscaping and rain gardens are complete. Only the bus shelter fitout remains and is due for completion before the end of May.

New bus shelters and landscaping

Bus Station Line marking complete

Park'n ride Carpark view from new overbridge

Platform works

The platform upgrade is mostly complete and fully operational but will require some minor works when the old overbridge is removed on the weekend of 14 July.

Northern end platform

Platform

Station Road

The carpark upgrade is mostly done. There are still some small pedestrian detours in place while some minor details are tidied up. The final step in the Station Road upgrade will be the road resurfacing which is expected to be completed before the 6 June opening.

Station Rd speedtable

Ramp to bridge from Station Road

New Pedestrian Overbridge

The overbridge is mostly complete but is awaiting canopy installation on piers 2 and 4. It will be opened to the public in late July once the existing overbridge has been removed in the scheduled block of lines on the weekend of 14 and 15 July.

Bus and bridge


20 April

The Park & Ride area is rapidly progressing and will open to the public in late May. The bus shelter fit out is nearing completion while the public toilet block is being finished.The toilet block will open to the public when the entire facility including the car park, bus shelter and bus lane opens. The bus station asphalting is expected to be complete by Friday 27 April, leaving only minor landscaping to be done and the remaining bus shelter fit out requirements to be installed. 

Car park and new bus shelter view from bridge
View of carp park and new bus shelter from the new overbridge.

Landscaping car park and bus shelter
Landscaping work taking shape in the new Park & Ride car park and bus shelter.

Construction on the new pedestrian overbridge is continuing at steady pace, targeting completion early June 2018. On the bridge itself, only finishing works like the installation of handrails and steel grating remains.

Work on the piers however, is more complex, and there are a number of elements requiring completion:

New steel grating on overbridge progressing well
Steel grating installation on the new pedestrian overbridge.

Pier 1

The precast stair hand rails have been installed and the concrete ramp is complete. Permanent hand rails will replace the temporary ones currently in place next week

Temp rails on P1 ramp
Temporary hand rail in place on the pier 1 concrete ramp.

Pier 2

The lift is in final stages of commissioning. The stair canopy installation is underway.

Pier 4

The precast stairs have been installed with temporary handrails. The pier 4 lift has started the commissioning process.

Station Road carpark

The carpark upgrade is well advanced with the new kerb expected to be poured week commencing Monday 23 April and the traffic island due to be poured week commencing 30 April. While the works are taking place there are some minor pedestrian detours in place.

Station Platform

Works are nearly done with only part of the downmain section remaining. CCTV has been installed and final back filling and asphalting will be completed once the old pedestrian ramp is removed.


18 March

Though construction across the entire project continues to progress well, the complex nature of the pedestrian overbridge has pushed out works completion date to mid-2018. The remaining elements of the upgrade, including the new park’n ride area, station platform, bus lane and bus shelter, remain on target for completion in April 2018.

Park’n Ride area/Bus shelter & bus lane

The bus lane is rapidly approaching completion with the concrete lane and kerbing complete, and the footpath almost done. The Manukau Road bus lane tie in construction is ongoing with asphalting due to be undertaken after Easter 2018.

The steel frame of the shelter itself is now in place and the fit out well advanced. The new toilet block has been installed and the plumbing is underway. The toilets will be operational when construction for the entire project finishes in June 2018.

Bus shelter in progress

Car Park

The new 87 space carpark is complete and landscaping around the facility being finalised. Up on Station road the carpark upgrade has passed the midway point.

Park'n ride car park and station view

Station Platform

The finishing touches to the platform works will be made this week with backfilling and final asphalting expected to be completed by Easter 2018.

New Pedestrian Over Bridge

Due to its many complex components, the new pedestrian overbridge is taking longer than anticipated to complete. The construction on the overbridge is now expected to be completed and open for use in mid-2018.

Pier 1: Stairs are now complete and concrete has been poured for the access ramp

Pier 1 precast stairs installed

Pier 2: Stairs are fully installed and the lift is at commissioning stage.

Pier 4: The precast stairs have been installed while construction continues on the pier 4 lift, the canopy is due to be installed after Easter.

Pier 4 stair installation


14 February

Excellent work in early 2018 has seen Stage 2 of the Pukekohe Station upgrade progress solidly and is currently target for completion in Mid-2018.

New pedestrian overbridge

The roof and ceiling construction for the new overbridge well advanced and piers 3 & 4 are complete. Work on the pier 1 ramp resumed this week and the stair installation is due to resume late February.

Pukekohe Station constructions
Roofing and ceiling construction continues 

Pukekohe Station bridge view
Pukekohe Station bridge view

Pier 2’s stairs are now in place while the glazing on the lift shaft is almost finished. Installation of the lift will begin this week. Across at pier 4 the glazing is also nearing completion and the installation also due to commence this week.

Pukekohe Station new stairs
New stairs at Pier 2 installed 

Station platform

The Station Platform is looking good with the tactile paving and the platform backfilling complete. The stop wall at the Southern end is under construction.

Pukekohe Station view
Tactile installation complete. 

Pukekohe Station platform
Platform backfilled and stop wall under construction 

Park’n Ride area

Car park

The park and ride car park asphalting is complete, allowing line markings and works on the raingarden installation to recommence.

Pukekohe Station car asphalting
Car park asphalting now complete

Bus shelter and bus lane

The bus shelter and bus lanes are coming along nicely with the 3/4‘s of the concrete laying complete for the bus lane itself, while the steel framework for the bus shelter is fully installed. The kerbing is also complete and preparation on the footpath construction has begun.

Pukekohe station kerbs complete
Kassel kerbs complete and framework installation continues 


15 January

Pukekohe Station New Year updates

Continuation of works over the holiday period has seen the Pukekohe Station upgrade make dramatic progress across all the key construction sites and we are able to see an indication of how the station will look at the end of the project, expected to be completed in early 2018.

New pedestrian overbridge

The new overbridge trusses were successfully installed on the four piers over the 3rd and 4th of January 2018.

Overbridge trusses installed on the piers early in Jan
Overbridge trusses installed on the piers early January 2018

On the week finishing 19 January, the contractor was completing the welding on the bridges trusses and work on the timber roof continues and is expected to be complete by the end of the week ending 28 January.

Overbridge trusses installed and being welded in place
Overbridge trusses installed and being welded in place

Work on installing the timber floor starts the week between 22 and 26 January and construction is also continuing on the pier 1 ramp and stair construction. Glazing is also ongoing for the lift shafts at pier one and two.

Installation of the new lifts is expected to take place at the end of January/early February.

Station Platform

At the central and southern end of the station platform, the old timber platform has been removed and new drainage is being installed. The precast concrete platform has been put in place and the concreting of the new platform is complete.

Boxed and ready for precast concrete platform install
Boxed and ready for precast concrete platform install

Precast concrete platform installed and ready for concrete pour
Precast concrete platform installed and ready for concrete pour

If works continue at the current rate, the platform is on target for proposed re-opening in mid-February.

Park’n Ride Area

Bus shelter & bus lane

The concrete layer for the bus lane is nearing completion while the installation of concrete beams for the bus shelter foundation continues. The steel framework installation for the bus shelter has also begun.

Bus shelter steel frame work installation has begun
Bus shelter steel frame work installation has begun

Carpark

The pavement construction is nearing completion and will soon be asphalted. The concrete pour for the new kerb line is also ongoing.

Pavement construction in the car park continues
Pavement construction in the car park continues


2017

Temporary car park loss - Station Road carpark and drop-off

Works begin in the Station Road car park on Monday 16 October. The works are expected to take around four weeks to complete and will involve the temporary loss of six car parks.

Two mobility carparks will be retained and available at all times. Access to the station from Station Road will be retained at all times.

Please see the map below to see where the lost parks are located.

Pukekohe Station Temp Car Park Loss


9 October 2017

The first two weeks of night works at Pukekohe Station have progressed smoothly, allowing work to continue on construction of the new concrete platform as well as the new pedestrian over bridge. Night works continue on the platform this week, installing drainage and building the foundations for later installation of the platform kerb units.

Across the remainder of the site the new pedestrian overbridge is clearly starting to take shape. Concreting is complete on the Pier 4 lift shaft and well underway on the pier 2 lift shaft. The construction and installation of Pier 3 is also complete.

The new pedestrian overbridge taking shape  Pier 3 foreground Pier 4 l...

Caption: The new pedestrian overbridge taking shape: Pier 3 (foreground) Pier 4 lift shaft (background)

On the Manukau Road side of the station piling work continues on the bus shelter and drainage works for the new Park n Ride is well advanced complete.The Transdev offices have been relocated from is old site where the Custom Street park and ride site is being built to on the KiwiRail land on the other side of Custom Street.


26 September 2017

Night works begin Tuesday 26 September

Night works are scheduled to commence Tuesday, 26 September 2017 between the hours of 11.30pm and 4.30am. This will take place from Sunday to Thursday nights intermittently until mid-December 2017. The number of nights required each week will vary, but we expect a minimum of one night work each week will be required.

As part of the Pukekohe Station Upgrade works, Downer is rebuilding and raising the Station platform level and constructing one of the eastern piers and new lift shaft for the new over-bridge. To minimise disruption and ensure commuter safety, we are completing these works at night, outside train service operating hours. While we are taking all necessary steps to minimise disruption, please be aware there may be some construction noise coming from the site. We apologise if this causes any disturbance to everyone in the area.


25 September 2017

Station Road carpark and drop-off

Works will begin in the Station Road car park in Monday 16 October. Works are expected to take around four weeks to complete, and will involve the temporary loss of six car parks. Two mobility carparks will be retained and available at all times. Access to the station from Station Road will be retained at all times.


19 September

  • The new Transdev office deck is complete while the installation of utility services and compound fences is nearly finished and on target for office relocation on the weekend of 23-24 September.
  • The retaining wall for the new park and ride site is finished with the bus shelter piling to be undertaken once geo-tech testing has been concluded.
  • The new pedestrian overbridge is taking shape with precast concrete structures (vertical columns, horizontal beams, table top pier head) installed within the supporting falseworks on piers 3 & 4.

Platform work

Works to rebuild and raise the station platform level are scheduled to begin the weekend of 23-24 September, with night works from 25 September as required.

Station Road carpark and drop-off

Works are expected to begin on the Station Road car park in early October. This may involve the temporary loss of approximately six car parks. Two mobility carparks will be retained and available at all times.


30 August

Construction is progressing well and on target for completion early 2018. For the first two months, works have been located on the Manukau Road / Custom Street side of the track. The focus has been on three main areas:

  • Drainage and earth works for the new Transdev office site south of the overbridge. The existing offices will be moved as they currently lie where the new station park and ride carpark is being constructed.
  • Stormwater drainage for the new park and ride, in preparation for the pavement to be laid.
  • Construction of the new pedestrian overbridge between the new park and ride car park and Pukekohe Station.

Design image of the new pedestrian overbridge

Image: Design image of the new pedestrian overbridge.

In September, work will continue on these sites as well as commencing on the platform and Station Road side of the tracks. Works will also include replacing the old timber platform with a new concrete platform and starting construction on the lift to the station platform.

Station Road car parks temporary closure

Construction works are expected to commence in September on the Station Road car park to relocate the existing median. These works are expected to have minimal impact on parking.

Following the median relocation, work will commence on the Station Rd pier (where the new bridge meets Station Rd).
This will unfortunately require the temporary loss of around five carparks on Station Road. Please note that two mobility parks will always be available and access to the Station from the pier will remain open.


25 July

Works are progressing on stage two of the Pukekohe Station upgrade. The initial works have mostly been preparatory and getting the necessary infrastructure in place.

Transdev Depot

The rest of July and early August will focus on preparing for relocation of the Transdev depot including earthworks, drainage and kerbing activity. Transdev is scheduled to be relocated mid-August.

Park and Ride

Earthworks including drainage and pavement works for the new Park and Ride will continue for the remainder of July and August.

Pier 4

The contractor is currently working on the construction of the new lift pit base which will be part of the new rail overbridge.

Platform

Protective hoardings are scheduled to be installed on the platform in August. The purpose of the hoardings are to protect the public and to ensure station access is maintained at all times during construction.


17 July

Preparatory works have commenced on the Custom Street park and ride site. We anticipate beginning works on the Station Road and Pukekohe platform sites mid to late August.

We will provide more details about the specific timing and site information once these have been confirmed.


3 July 

Works on stage 2 of the station upgrade commence Monday, 10 July

The $15.4-million project will cover the build of the new park and ride area, improved bus station facilities, and a pedestrian overbridge at the new integrated bus and train station.

We expect to complete construction in early 2018.

Parking changes

  • As part of the upgrade, the KiwiRail land near the V8 bridge, unofficially used for car parking, will be closed indefinitely from Monday, 10 July.
  • If you use this parking facility, please make alternative plans. Given there is limited on-street parking nearby, you may want to consider taking the bus to and from the station. With new Simpler Fares, you can pay one fare for using up to 5 buses and trains across 4 hours, with no more than a 30-minute transfer using your AT HOP card. Excludes SkyBus. Terms of use for AT HOP cards are available at AT.govt.nz/athopterms.
  • The V8 bridge will remain open to the public. Pedestrian access to will be via the footpath running along the fence line on the right-hand side of the KiwiRail land as you enter from Custom Street.

Image: Map of the closed KiwiRail land.

Pukekohe station map


20 February

Over the past 2 months, good progress has been made on the new station:

  • Piling works have now been fully completed at the site for the new pedestrian overbridge, which will connect Station Road to Custom Street.
  • Piling works for overbridge have been tendered and awarded, with building consents obtained.
  • Rail corridor piles were successfully installed during the Christmas break.
  • Electronic passenger information screen, passenger info board, and tag on/off machine have been relocated on the platform in preparation for future construction works.

Get full details in the February project newsletter (PDF 1.2MB)

Pukekohe Station works Jan17

Image: A temporary road placed over the rail tracks that allowed the contractor’s crane and piling rig to cross onto the platform.


13 January

Parking lot closed, 15 to 30 January.

To allow for the completion of essential piling works, we are closing the parking lot on Station Road from the evening of Sunday 15 January to Monday 30 January.

If you use this parking facility, you will need to make alternative plans during this time. We apologise for any disruption this may cause and thank you in advance for your cooperation.

Please note:

  • Two disabled car parking spaces will be unavailable during this time. As no alternative disabled parking spaces are located nearby, we recommend affected passengers use Papakura Station until the spaces are restored.
  • Pedestrian access to the station will also be affected. An alternative access route will be clearly signposted. Access to the rail bridge will be kept open and monitored accordingly.

2016


12 December

Over the next few weeks and into the new year, these works are planned:

  • Laying the foundation (piling) for the new pedestrian overbridge that will connect Station Road to Custom Street.
  • Painting of the new cycle lane leading to the intersection of Manukau Road and minor repairs.
  • Between 27 and 31 December, piling works will be undertaken at the station. This will involve drilling 30m long piles. Subsequent piles will be installed in January. Work will be undertaken between 6am and 6pm (work will start at 4.00am on 27 December).
  • Other isolated works on the rail platform and layout changes.

Changes to the station’s layout from 13 December

  • On 13 December, the existing Passenger Information Display will be relocated to the underside of the station building.
  • Between 13 and 23 December, the base of the station ramp will be temporarily reconfigured to avoid the construction area for the new overbridge. This will see a temporary ramp section installed to ensure continued access is provided.
  • On 13 December (during off peak hours), the AT HOP card reader at the base of the station ramp will be temporarily relocated to the end of the new temporary ramp. An alternative HOP card reader can be found under the station building.
  • Between 13 and 23 December (from 10pm to 5am), the 2 plant boxes located adjacent to the station building will be removed.
  • Between 13 and 23 December, the station information board will be removed, with a temporary information board positioned under the station building.
  • Between 15 and 23 December (during off peak hours), a section of the timber platform is planned to be cut out and replaced with a temporary section. This is to allow easier machine access onto the platform and reduce disruption to passengers.

Disruption to train services at Pukekohe Station - 27 December to 3 January 2017

Buses will replace all trains between Pukekohe and Otahuhu stations from Tuesday, 27 December 2016 until Tuesday, 3 January 2017 (inclusive). 

The closure is to allow for important improvements and maintenance work on the rail network. There are a number of worksites between the stations where upgrades will be happening.

See a map of the rail replacement bus stop in Pukekohe (PDF 374KB)

December newsletter

Download the second Pukekohe Station project newsletter (PDF 1.17MB)


23 November

pukekohe-station-sod-turning

Main construction work on upgrading Pukekohe Station to a fully-integrated bus and train interchange started today.

Transport Minister Simon Bridges and Mayor Phil Goff marked the start of main construction work with the turning of the first sods.


18 November

Access between Custom St and Pukekohe station.

There is a temporary pedestrian overbridge at the southern end of the station for access to and from Custom St. Please be aware this overbridge has stairs.

Access for those who can not use stairs is over Massey Avenue and along the walkway beside the rail line down to the station.


2 November

AT has released images of what the upgraded Pukekohe Station will most likely look like once construction is complete in late 2017.


31 October

The New Network for South Auckland (including Pukekohe and Waiuku) has been launched.

Find out more about the new buses and bus routes.


30 September

Read the first Pukekohe Station project update newsletter (PDF 1.77MB)


8 September

From 12 September, these changes will be made to the layout of the Harris Street/Manukau Road intersection:

  • Left turn only into Harris St from Manukau Rd.
  • Left turn only out of Harris St into Manukau Rd.
  • No right turns from Harris St into Manukau Rd or from Manukau Rd into Harris St.

See a map of changes around Harris Street (PDF 166KB)

The restrictions will allow the construction of new kerbs and footpaths and will become permanent once works have been completed.


5 September

Custom St entrance to Auckland Council service centre closed.

As part of the work on the Manukau Road-Custom Street intersection, the public carpark entrance to the Auckland Council Pukekohe Service Centre on Custom St will be closed until September 2017.

  • The carpark entrance off Manukau Road will remain open at all times.
  • There will be some minor disruption with noise.
  • Traffic management staff will be on site to provide assistance if required.

See a map of the changes around Custom Street (PDF 240KB)


19 July

A dawn blessing ceremony has marked the start of the first phase of construction of Pukekohe's new bus and train station.

Read the media release: Construction to start on new Pukekohe bus and train station.


2015


16 December

AT held a public meeting on 8 December at the Franklin Arts Centre to discuss proposed changes to the Manukau Road/Custom Street intersection as part of Pukekohe Station upgrade project.

Get details of changes proposed for the Manukau Road/Custom Street intersection.


14 October

An information session was held at Pukekohe Station on 14 October. The session was attended by about 150 people who were able to see the project information boards and get their questions answered by the project team.


5 October

Work is about to begin work on the detailed design of the new bus-train facility at Pukekohe Station.

AT has engaged mana whenua, the Franklin Historical Society and the Franklin Local Board to identify possible opportunities to incorporate cultural and historical connections into the design.

If you are experiencing family violence, don't worry, the information within this pop-up won't appear in your browser's history.

enter
Privacy policy

We’ve made asking for help safer than ever.

Join us in standing up against domestic violence and making more places of refuge across the internet.

If you, your business or your agency want to have The Shielded Site tab on your site we’ve made adding it very easy.

Click here to find out more. (WARNING: this will take you away from our shielded portal.)

NEED MORE ANSWERS

If you are living in fear in your relationship or in your family, there are so many ways we can help you right now. You won’t be turned away even if you don’t have children, a NZ visa, or money. If you still have more questions have a read below and contact us when you’re ready.

I’m ready to talk now.

You can call our 24-hour support and crisis line on 0800 REFUGE (733843). Or, if you prefer, you can click here and contact us discretely through our contact form and we will email you back as soon as possible.

What will I do for money?

There are a number of benefits and allowances you may be eligible for if you are a victim of domestic violence in New Zealand. We can help you better understand your options once you make contact.

I haven’t been beaten up, can Women’s Refuge still help me?

We support women who have experienced any form of domestic violence: verbal, psychological/emotional, sexual, and financial as well as physical. In fact, psychological/emotional abuse is the most common form of domestic violence.

How much does it cost to stay?

Women's Refuge support and advocacy services are free. In the safe house, rent is usually charged once your financial situation is sorted out. Safety is our main concern. You won't be turned away if you don't have any money.

How long can I stay in a safe house?

Some women only stay a night or two, while others stay for weeks. You can talk with the advocates at your local refuge about how long you think you need to stay to ensure your safety.

I don’t live with my partner, but he is abusing me. Can you still help me?

Yes, you don’t have to be living with your partner to experience domestic violence and you can still call us.

What happens if I haven't got any clothes or food?

Women's Refuge has clothing that you can have. We’ve also got toys and books, formula and nappies. You are welcome to use our emergency food until you get your financial situation sorted out.

Will other people be there?

Safe houses usually have other women, including women with their children, staying there. Refuge advocates are around during the day.

How will I get my kids to school?

The advocates at your local refuge will help you work out transport for your children, or help with changing schools.

Can Women's Refuge help me if I stay in my own house?

Yes, we can provide all the same support and advocacy for you no matter where you choose to live. You may be eligible to access support through the Whanau Protect service.

I'm living in a rural area. Can you still help me?

Yes. Find your local refuge and they will be able to arrange support, advocacy and transport for you.

Can Women's Refuge help around issues with children?

Yes. We can provide support and advocacy around matters to do with custody, access and care.

BEING SAFE ONLINE

The safest way to browse the internet if you suspect your browsing history is being monitored, is to use your browser’s private or incognito mode.

If you suspect your device has been compromised by spyware, then you should use consider using another device as some spyware may still be able to monitor icognito sessions.

To activate a private browsing session, follow the instructions below.

Safari

Open Safari > go to the File menu > select New Private Window

When finished, don’t forget to close your browser window to ensure your safety and privacy.

Chrome

Open Chrome > go to the triple-dot menu (top right of your browser's window) > select New Incognito Window

Internet Explorer

Open IE > click the Tools button > select Safety > and then click InPrivate Browsing

Mozilla Firefox

Open Firefox > click the menu button ☰ > and then click New Private Window

You should see a message in the new window saying that you are now browsing privately.

When finished, don’t forget to close your browser window to ensure your safety and privacy.

Getting out

The most important thing is for you and your children to get out safely. It is important to know that leaving a violent relationship can be one of the most dangerous times for women and children so it is important to make a safety plan around leaving and keep your plans confidential. Below are some tips to help you make a plan.

  • If you can, pack a bag with bare necessities and important documents that you can leave with someone you trust. Include important documents such as passport, birth certificate, bank account details, driver’s licence, and bank cards and other things like medicines.

  • Know abuser's schedule and safe times to leave.

  • Contact us for guidance or a safe place to stay for you and your children.

Getting help

We warmly welcome all women and their children to access our support, advocacy and crisis accommodation. If you need help or have questions, use our live chat to get in touch.

making a plan

The safety of you and your children (if you have them) will be your primary concern. If you’re not ready or cannot safely leave, here are some things you can do to stay safe now.

  • Make a safety plan with the guidance of a refuge advocate.

  • Get yourself a pre-paid phone; keep it charged and safe.

  • Keep photocopies of important documents (passport, birth certificate, bank account details, medical notes, driver's licence, etc) and store these at the home of a supportive friend or family member.

  • Keep a journal of all violent incidents, noting dates and events.

  • If you can, open your own bank account and try to save some money.

  • If you have pets you are worried about, consider them in your safety plan.

Privacy Policy – The Shielded Site Application.

General

In this privacy policy, the terms ‘NCIWR’, ‘we’, ‘us’, and ‘our’ refer to National Collective of Independent Women’s Refuges Inc. NCIWR operates this web application at https://d3f5l8ze0o4j2m.cloudfront.net (‘this web application’).

This privacy policy explains how we may collect, store, use, and disclose personal information that we collect and that you provide to us. By using this web application you acknowledge that we may collect, store, use, and disclose your personal information in the manner set out in this privacy policy.

Collection of personal information

We may collect personal information from you when you use this web application, for example when you make a request for contact on this web application.

You may decide not to provide your personal information to us. However, if you do not provide it, we may not be able to provide you with access to certain information or services. For example, we may be unable to make contact with you if you do not provide us with your contact information.

Automated collection of non-personal information

When you visit this web application, we will not add traceable elements (such as cookies, sessions, and usage monitoring software) to your browser or device.

Use and disclosure

We will not use or disclose your personal information except in accordance with this privacy policy or the Privacy Act 1993. We may use your personal information to:

  • assist in providing information and services requested by you;

  • communicate with you

Your personal information will only be made available internally for the above purposes. We will not disclose your personal information to third parties. We will only use or disclose personal information that you have provided to us, or which we have obtained about you:

  • for the above-mentioned purposes;

  • if you have otherwise authorised us to do so;

  • if we have given you notification of the intended use or disclosure and you have not objected to that use or disclosure;

  • if we believe that the use or disclosure is reasonably necessary to assist a law enforcement agency or an agency responsible for national security in the performance of their functions;

  • if we believe that the use or disclosure is reasonably necessary to enforce any legal rights we may have, or is reasonably necessary to protect the rights, property and safety of us, our customers and users, or others;

  • if we are required or permitted by law to disclose the information; or

  • to another entity that carries on the business of operating this web application.

Storage and security

All personal information collected on this web application is collected and held by NCIWR. We will endeavour to protect your personal information that is held by us from unauthorised access, use, disclosure, alteration, or destruction.

Third party service providers

This website may be hosted by one or more third party service providers (‘service providers’) who enable us to provide this web application. You acknowledge and agree that any personal information that may be collected on this web application may also be held and used by our service providers on our behalf. Any information collected will be securely sent and securely stored on a server.

Third party websites

This web application may be hosted by websites operated by third parties. We are not responsible for the content of such websites, or the manner in which those websites collect, store, use, or distribute any personal information you provide. When you visit third party websites from hyperlinks displayed on this web application, we encourage you to review the privacy statements of those websites so that you can understand how the personal information you provide may be collected, stored, used, and distributed.

Right to access and correct

You may request access to, or correction of, any personal information we hold about you by contacting us as follows:

Email:info@refuge.org.nz
Post:Privacy Officer
NCIWR
PO Box 27-078
Marion Square
Wellington 6141

To ensure that the contact information we hold about you is accurate and current, please notify us of any changes to such information as soon as possible.

Contacting NCIWR

Any emergency relating to domestic violence should be directed to 111 for New Zealand Police assistance.

If you request assistance through this website, we will endeavour to respond as soon as we can. If you require advocacy services phone 0800 REFUGE or 0800 733 843 to talk to a refuge in your area within New Zealand. All member refuges of NCIWR are listed on our main website (www.womensrefuge.org.nz). If you do visit the Women’s Refuge Website, please note that it is a traceable site so we recommend you use the online safety tips found on this web application to visit www.womensrefuge.org.nz safely.

Advocacy services are available at member refuges. Your call and information will be treated in confidence and privacy.

Changes to our privacy policy

We reserve the right, at our discretion, to alter this privacy policy at any time. Changes to this privacy policy will take effect immediately once they are published on this web application. Please check this privacy policy regularly for modifications and updates. If you continue to use this web application or if you provide any personal information after we post changes to this privacy policy, this will indicate your acceptance of any such changes.

This privacy policy was last updated on 6 October 2015.

If You’re In
Immediate danger
CALL 111 IMMEDIATELY

If you fear for your safety:

  1. Run outside and head for where there are other people.
  2. Ask someone to call 111
  3. If you have children take them with you if you can
  4. Don't stop to get anything else
Close