Skip to Main Content
Auckland Transport

Waterview Shared Path project updates

Get the latest updates on the new cycling and walking path that will connect Waterview and Mt Albert.


2016


21 December

The installation of two piers for the Alford Street Bridge was completed in the first week of December. 

Alford Street bridge - bridge pier installation

Alford Street bridge - bridge pier installation

Phyllis to Harbutt Boardwalk

All material suspected to contain asbestos has been removed and rock breaking was undertaken.

Piling work for the central pier and northern abutment will startin late January 2017.

Soljak Bridge

The southern abutment has been poured for the Soljak Place Bridge that will cross over the western railway line. One bridge pier has also been installed.

A crosshead will be placed on top of the piers to take the weight of the beams for the bridge early in 2017, following the completion of the northern abutment and the installation of the other two piers.

Soljak Place Bridge - southern abutment and pier with falsework around it.


5 December

Alford Street Bridge

A capping beam has been established on the eastern side of Te Auaunga (Oakley Creek). This is part of a palisade wall that will retain the eastern abutment of the bridge. Deep ground anchors will add further strength.

A 450-tonne crane and 10 pre-cast pier sections have been delivered to Waterview Esplanade. These sections were progressively installed at night during the last week of November.

alford st bridge beams

Image: Capping beam and temporary bridge on the western side of Te Auaunga (Oakley Creek). 

alford st bridge casing

Image: Vibration hammering of casing into the ground on the eastern side of Te Auaunga.

Video: Time-lapse of progress on the bridge.

Phyllis to Harbutt Boardwalk

Building and domestic waste materials (suspected to include asbestos) that was dumped several years ago in the area between Harbutt Reserve and Phyllis Reserve has been professionally removed. We are awaiting confirmation from specialists that the site is free of hazardous materials before work resumes.

We will send a letter to residents and other stakeholders when the bush area is re-opened.

Soljak Place Bridge

Piling work has resumed on the northern side of the western railway line opposite the Mt Albert Pak ’n Save. Increased background noise is expected but we will continue to monitor vibration and noise levels to ensure they are within council regulations.

We expect to release the final design for the path connecting Soljak Place Bridge to Trent Street soon.


12 July

A temporary platform was built to lift the precast sections of Alford Bridge into place. 

The finished Alford Street Bridge is set to open in early 2017.

Check out the video for a time-lapse view of the construction. 


13 June

Construction of the Alford Street Bridge is underway.

Image: Piles are driven into the ground to build a temporary structure from which the bridge can be built.

Alford Street Bridge Construction 


5 February

Start of construction

A ceremony has been held to launch the Waterview Shared Path.

The first sod was turned by cabinet minister Paula Bennett accompanied by representatives of the organisations that have joined to create the new connection, which will contribute to the Auckland urban cycleway programme.  

Read the media release: Construction beginning on Waterview cycling and walking connection.


2015


24 September

Waterview Shared Path Joe Wilson Leading A Karakia

On 16 September, a dawn karakia celebrated the upcoming start of construction for Waterview Shared Path.

Held near the site from where Alford bridge will connect Unitec Institute of Technology with Great North Rd, the ceremony (lead by Joe Wilson of Te Ākitai Waiohua) was an acknowledgement of the area's significance for mana whenua, including Ngāti Whātua Ōrākei, Te Ākitai Waiohua, Ngāi Tai ki Tamaki and Te Kawerau a Maki.

Construction of the path is expected to start in early 2016, once consents are granted and site investigations are completed over the coming months.


2014


18 December

The period for public submissions on the Notice of Requirement (NOR) has been extended from 23 January to 5 February 2015.


14 November

AT is applying for consents on Waterview Shared Path. AT has developed preliminary designs for the route and will lodge a Notice of Requirement (NOR) with Auckland Council.

Public submissions will be from 5 December 2014 to 23 January 2015.