Improving traffic flow on Morningside Drive
We’re planning improvements around the New North Road and Morningside Drive intersection.
On this page
Project details
Start date
November 2026End date
February or March 2027Location
Between 615 New North Road and 3 Morningside DriveTransport involved
Walking, driving, bus and trainOverview
We are planning targeted improvements around the New North Road and Morningside Drive intersection.
Stage 1 will include:
a new signalised pedestrian crossing
parking and clearway changes
more space for vehicles to queue
measures to reduce the risk of vehicles queuing over the rail crossing.
These changes aim to improve:
safety
access to Morningside Station
traffic flow during busy periods.
We expect Stage 1 construction to start in February or March of 2027. This project is separate from but supports the longer-term Western Line Rail Crossings Programme.
The remaining road layout changes form Stage 2. We cannot progress them while construction at 10 Morningside Drive occupies part of the road. We will investigate Stage 2 later in 2027 once that work allows the remaining design to be considered. Delivery timing for Stage 2 is still to be confirmed.
Timeline
Informing businesses and getting feedback
We are informing businesses directly affected by the Stage 1 changes.
Before construction, we will consider feedback about:
parking
deliveries
property access.
Businesses will get a further update once we confirm the construction programme.
Construction
We expect to build the Stage 1 improvements in February to March 2027. We will give more information about timing and temporary impacts before work begins.
Stage 2 investigation
Stage 2 will be investigated later in 2027, once construction at 10 Morningside Drive allows the remaining road-layout changes to be considered. The scope and delivery timing are still to be confirmed.
Project designs
Give feedback
Project benefits
Safer access to the station
Better traffic flow
Space to move around the rail crossing
Project background
The New North Road and Morningside Drive intersection is close to the rail crossing. When the barriers are down, queues can build between the crossing and the intersection. Earlier community feedback from Western Line Rail Crossings engagement also identified concerns about:
congestion
vehicles queuing near the tracks
access to local properties
safer connections to Morningside Station.
The project is being delivered in stages because construction at 10 Morningside Drive currently occupies part of the road. Stage 1 covers improvements that can be delivered while that development is under construction. Stage 2 will be investigated later in 2027, once the remaining road-layout changes can be considered. Its delivery timing is still to be confirmed.