Tir Conaill Avenue and Greenan Drive intersection safety improvements
We are proposing safety improvements at the Tir Conaill Avenue and Greenan Drive intersection.
On this page
Project details
Start date
2026End date
2027Location
Tir Conaill Avenue and Greenan Drive, Flat BushTransport involved
Walking, driving, bus and ferryOverview
We are proposing safety improvements at the Tir Conaill Avenue and Greenan Drive intersection.
To help people cross the road safely, we will:
upgrade pedestrian crossing facilities
install pedestrian refuge islands
improve the existing kerb ramps and tactile pavers.
Other improvements include:
installing a new mountable roundabout
installing new road markings and signage to support the new road layout
upgrading and shift the rain garden to accommodate a new pram crossing.
We will also install broken yellow lines (no stopping at all times) to keep parked vehicles clear of the crossings and improve visibility for pedestrians and drivers. As a result, we will remove about 22 parking spaces overall.
Parking changes
Greenan Drive
We will remove:
4 roadside parking spaces outside 24 Tir Conaill Avenue
3 roadside parking spaces outside 26 Tir Conaill Avenue
3 roadside parking spaces outside 31 Tir Conaill Avenue
4 roadside parking spaces outside 15 to 17 Greenan Drive.
Tir Conaill Avenue
We will remove:
2 roadside parking spaces outside 31 Tir Conaill Avenue
4 roadside parking spaces outside 26 to 30 Tir Conaill Avenue
2 roadside parking spaces outside 17 Greenan Drive.
You can view the proposed layout in the project design.
Project designs
Give feedback
Project benefits
Lower vehicle speeds
Safer turning movements
Safer crossings
Project background
This intersection has been identified as a community safety concern, particularly for people turning into and out of Tir Conaill Avenue. Seven crashes were recorded at the intersection from 2020 to 2025, with 3 resulting in injuries.
Crash history and observations indicate that these are likely due to drivers accepting unsafe gaps. On-street parking has at times made it even harder to see.
We expect the proposed roundabout to:
improve visibility
slow vehicle speeds
lower the risk of crashes.
This will help to create a safer and better-connected neighbourhood for everyone who lives, works, or visits the area.