Selwyn Street and Trafalgar Street intersection improvement
We are proposing safety improvements at the Selwyn Street and Trafalgar Street intersection.
On this page
Project details
Start date
2026End date
2027Location
Selwyn Street and Trafalgar Street, OnehungaTransport involved
Walking, driving and cyclingOverview
We are proposing safety improvements at the Selwyn Street and Trafalgar Street intersection.
We will:
install traffic lights and new pedestrian crossings with directional and warning tactile pavers on all legs of the intersection
install cycle stop boxes on all approaches
install yellow hatching road marking (‘keep clear’) outside 145 Trafalgar Street
rebuild the footpath with a new berm to align with the kerb line
rebuild the vehicle crossing outside 145 Trafalgar Street and 143 Trafalgar Street to align with the new kerb line.
We will also install broken yellow lines (no stopping at all times). As a result, overall, 15 parking spaces will be removed. This includes:
5 roadside parking spaces outside 145 to 151 Trafalgar Street
4 roadside parking spaces outside 146 and 148 Trafalgar Street
6 roadside parking spaces outside 134 to 140 Trafalgar Street.
You can view the proposed layout in the project design.
Project designs
Give feedback
Project benefits
Safer turning movements
Safer crossings
Better visibility
Better connections
Project background
We’re planning safety improvements at the intersection of Selwyn Street and Trafalgar Street in Onehunga. This will make it safer and easier to use for everyone, whether you’re walking, cycling or driving.
We’ve identified the intersection as a high-risk location from its crash history. Between 2021 and 2025, 14 crashes were recorded at the intersection. That includes:
one serious-injury crash
6 minor-injury crashes
7 non-injury crashes.
All crashes recorded between 2021 and 2025 involved drivers failing to give way.