Upgrade and Extension to Bawden Road
Notice of Requirement (NoR) 12
On this page
Project overview
This project will be a key connection to/from the proposed future metropolitan/town centre in Dairy Flat and the rapid transit corridor and will be an important link in the public transport network.
The nature of the proposed works includes:
- The upgrade of Bawden Road to an urban arterial corridor with walking and cycling facilities between Dairy Flat Highway and just east of Top Road, and the construction of a new extension of Bawden Road from just east of Top Road to State Highway 1.
- Tie-ins with existing roads and localised widening around the existing intersections to accommodate new intersection forms.
- New or upgraded stormwater management systems, bridges and culverts (where applicable).
- Batter slopes, and associated cut and fill earthworks.
- Vegetation removal.
- Other construction related activities required outside the permanent corridor including the regrade of driveways, construction traffic manoeuvring and construction laydown are areas.
Notice of Requirement (NoR)
Full information about the Notice of Requirement (NoR) is available to view on Auckland Council’s website.
NoR Map
Project status and anticipated construction timeframes
This project is currently in the appeal period. Submitters had 15 working days in which they could appeal to the Environment Court, against the whole or any part of the decision from AT. Appeals are under Section 174 of the Resource Management Act 1991.
During this process AT works together with submitters to come to a resolution. The Environment Court appoints a mediator to facilitate these conversations and if a resolution cannot be reached then an Environment Court hearing will take place and the Environment Court will issue a decision on the outcome.
There is currently no funding for detailed design or construction of this project. We anticipate the project will be delivered sometime within the next 30 years in line with Auckland Council’s land release strategy.