Skip to main content
Last updated
Project status Construction

Project details

Start date

23 March 2026

End date

December 2026

Location

Onehunga

Transport involved

Walking, driving and bus

Overview

Vector works

Vector is installing a new 33kV underground power connection at the intersection.

We are taking a dig approach and are delivering Vector’s trench work at the same time, approximately 72m.

Progress for this stage is heavily dependent on what sort of ground conditions we encounter. This would include existing services and if we need to lower them or not to fit in the power connection.

It will depend on what we find once we open the road.

Latest updates

  • Footpath and pram crossing.
  • Kerb and channel.
  • Street lighting.

Traffic management

  • Selwyn Street open to traffic both ways.
  • Road closure on Arthur Street west.
  • Detours via Hill Street, Grey Street and Church Street.
  • Bus access open 24/7 on Selwyn Street south and Arthur Street east towards town centre side.   

  • Footpath and pram crossing.
  • Kerb and channel.
  • Street lighting.

Traffic management

  • Selwyn Street open to traffic both ways.
  • Road closure on Arthur Street East, town side.
  • Detours via Grey Street, Onehunga Mall and Church Street. 
  • Bus access open 24/7 on Selwyn Street south and Arthur Street east town centre side.   

Vector is installing a new 33kV underground power connection at the   
intersection.

We are taking a dig once approach and are delivering Vector’s trench works at the same time, approximately 72m.   

Vector’s work is on Selwyn Street and Arthur Street east. It involves digging down 1.5m under the road.  

Traffic management remains the same from Stage 2. 

Project benefits

Slower traffic speeds

The roundabout will slow traffic speeds, making it safer for bus and other heavy vehicle movements, as well as for turning and crossing.

Safer pedestrian crossing

Safer pedestrian crossing facilities will make it easier and more enjoyable for you, our tamariki, and the community to navigate your neighbourhood with confidence.

Parking changes

Reprioritising 2 parking spaces, one on Arthur Street for the new pedestrian crossing and another on Selwyn Street to formalise the broken yellow lines opposite the Harbour View Terrace intersection.

Project background

This project is part of Auckland Transport's High-Risk Intersection programme, a safety improvement programme that prioritises safety interventions at high-risk intersections in Auckland.   

Between 2018 and 2025, 34 crashes occurred at the intersection, resulting in 1 serious injury and 12 minor injuries, primarily due to turning or failure to give way. Contributing factors include poor visibility, high approach speeds, and inadequate pedestrian facilities that are misaligned with the desire lines to nearby shops and schools.   

Public engagement for the project was held in August 2025.

After reviewing feedback the project would proceed with removing the speed cushion on Arthur Street approaches to minimise the risk of excess noise and vibration on the minor road corridors.  

The work we're doing:

  • Installing a mountable urban roundabout, including any associated signage and road markings.
  • Installing speed cushions on all approaches and traffic islands to   slow approaching traffic and improve vehicle deflection when entering the roundabout.
  • Providing pedestrian crossings on all four legs of the intersection, including the removal of the existing pedestrian refuge islands on Selwyn Street near numbers 74 and 110.
  • Installing 2 driver feedback signs on Selwyn Street, one outside number 68 and another outside number 83.