Skip to main content

Project updates

We are currently completing minor:

  • remedial work
  • line marking.

This work will be less intrusive, but there may be times when we need traffic management. This could include lane closures, stop/go or traffic light controls.

For more information about the Point Chevalier to Westmere improvements project, watch the video on our YouTube channel (opens in a new tab).

About the project

We’re working to make Point Chevalier Road, Meola Road, and Garnet Road safer and more accessible. The project is under construction and will be completed in mid-2025.

The project will:

  • add more pedestrian crossings
  • improve cycling safety
  • improve existing bus stops and add new shelters
  • add more trees and landscaping
  • redesign streets to encourage slower vehicle speeds
  • add seating and rubbish bins
  • provide a great environment for outdoor dining
  • improve storm water and drainage
  • rebuild Meola Road's foundations
  • move Meola Road powerlines underground.

Project information and benefits

For detailed information about each location, including artist’s renders of what the completed improvements will look like, download these resources.

 

Project staging overview

Gantt chart showing project stages in 3 locations. Stage 1 of Meola Road and Point Chevalier Road is complete. Both started in October 2023 and finished in April 2024. On Meola Road, Stage 2 paving, landscaping and road repairs from Huia Road to Walford Road start May 2024 and finish December 2024. Stage 3 roundabout construction starts August 2024 and finishes November 2024. Stage 4 finishing works start November 2024 and finish February 2025. On Point Chevalier Road, Stage 2 stormwater and roadworks from Smale Street to Wakatipu Street start March 2024 and finish August 2024. Stage 3 stormwater and surface works start May 2024 and finish September 2024. Stage 4 stormwater works on the southern part of Point Chevalier Road start August 2024 and finish November 2024. Stage 5 Meola Road roundabout and surface works start September 2024 and finish January 2025. Stage 6 upgrades at the Great North Road intersection start December 2024 and finish March 2025. Stage 7 finishing works on the southern part of Point Chevalier Road start February 2025 and finish May 2025. On Garnet Road, Stage 1 drainage works start May 2024 and finish August 2024. Stage 2 town centre and intersection upgrades start July 2024 and finish February 2025. Stage 3 work on Garnet Road to Meola Road roundabout starts December 2024 and finishes February 2025. Stage 4 finishing works start February 2025 and finish April 2025.
Project stages and dates for Meola Road, Point Chevalier Road and Garnet Road

Stage 1 of Meola Road and Point Chevalier Road (October 2023 to April 2024) is complete. 

Meola Road

  • May 2024 to December 2024: Stage 2 paving, landscaping and road repairs from Huia Road to Walford Road 
  • August 2024 to November 2024: Stage 3 roundabout construction 
  • November 2024 to February 2025: Stage 4 finishing works.

Point Chevalier Road

  • March 2024 to August 2024: Stage 2 stormwater and roadworks from Smale Street to Wakatipu Street 
  • May 2024 to September 2024: Stage 3 stormwater and surface works 
  • August 2024 to November 2024: Stage 4 stormwater works on the southern part of Point Chevalier Road 
  • September 2024 to January 2025: Stage 5 Meola Road roundabout and surface works
  • December 2024 to March 2025: Stage 6 upgrades at the Great North Road intersection
  • February 2025 to May 2025: Stage 7 finishing works on the southern part of Point Chevalier Road. 

Garnet Road

  • May 2024 to August 2024: Stage 1 drainage works
  • July 2024 to February 2025: Stage 2 town centre and intersection upgrades
  • December 2024 to February 2025: Stage 3 Garnet Road to Meola Road roundabout  
  • February 2025 to April 2025: Stage 4 finishing works.
View larger image

Stay up to date

To sign up for a monthly update, email: projects@at.govt.nz. Please include "PTC2W sign up" in the subject line of your email.

Stormwater network

We're delivering the stormwater network installation on Point Chevalier Road for Healthy Waters, saving money and time by sharing contractors, equipment and utilising the same traffic management plan and only digging up the road once.

The new stormwater network planned for Point Chevalier is part of a larger project in Auckland to separate combined networks, where stormwater discharges into the wastewater network. Separating the stormwater from the combined network reduces overflows in wet weather.

The stormwater infrastructure for Point Chevalier Road will include the installation of around 900 metres of pipe and associated stormwater manholes.

Timeline

  • 2016 – community consultation on cycle routes between Point Chevalier and the city fringe
  • 2017 – community consultation on a concept design for a cycleway between Point Chevalier and Westmere
  • 2017 to 2018 – reviewed design based on community feedback
  • 2019 – community consultation on a revised design
  • 2020 to 2021 – project delay due to 2020 Covid-19 emergency budget
  • early 2022 – re-engaged with the community
  • late 2022 – political re-engagement
  • late 2023 – construction begins
  • mid-2025 – construction complete.

New projects in the area

Maintenance work is currently being carried out on Tui Street, Huia Road and Kiwi Road. We expect to complete this by the end of February 2025.

Last updated Back to top

Related Content