Project status Construction

Project details

Start date

September 2025

End date

Mid-2026

Location

Glen Innes Station

Transport involved

Train and walking

Overview

From 2026, more people will use Glen Innes station. That’s because the City Rail Link will unlock more frequent trains and new connections, making it easier to get around Auckland.

However, with more trains more often there is a higher safety risk for pedestrians. Safety gates would also need to be closed more often, impacting travel times. 

To provide safer, easier access to Glen Innes station we're removing the level crossings and replacing them with a new pedestrian bridge. The pedestrian bridge will have lifts and stairs, making it more accessible. 

Latest updates

We heard it makes sense to remove the level crossing and replace it with a pedestrian bridge. We also heard that the new bridge should be fully accessible, safe and connected.

We did receive some feedback about retaining the level crossings or only having the pedestrian underpass as access. Removing the level crossings at Glen Innes Station and replacing them with a pedestrian bridge will provide the community with a safer way to access the station and help improve journey times by train.

Maintaining only the pedestrian underpass would not cater to the number of people traveling at peak times.

There are no current plans to provide additional car parks as part of this project. Instead, this project ties in closely with the new shared path and cycleway, as well as the Apirana Avenue bus exchange to encourage a variety of travel options.

During the consultation, we:

  • delivered 19,075 flyers
  • had face to face conversations with the occupants of 25 surrounding properties
  • held 4 customer engagement sessions at Glen Innes Station
  • held 2 engagement events and spoke with about 50 people in person
  • held stakeholder presentations
  • engaged with Maungakiekie Tāmaki Local Board and Ward Councillor
  • engaged with mana whenua
  • engaged with the Capital Projects Accessibility Group (CPAG)
  • engaged with 4 schools
  • received and analysed 640 insights (138 responses to our Have Your Say website).

Most feedback we received was consistent with the project delivery goals.

Lifts will be installed with a regular maintenance schedule and operational procedure in place for any breakdowns. An alternative accessible exit will be available during emergency situations.

Lifts will have capacity for 26 people. Prams, e-bikes, courier bikes, wheelchairs and mobility scooters can comfortably use these.

The bridge will be constructed from concrete and provide stair and lift access, non-slip surfaces and design standard tactiles for low vision customers.

Width of the stairs and bridge is confirmed to be 2.5m, allowing space for people to pass and travel in both directions.

Well-designed bike access ramps on stairs will be 180mm in width (wide enough for all bike tires) and designed with space away from handrails.

Lighting and security (including CCTV), emergency alarm help points, and lighting on and around the pedestrian bridge are all included in the design and will be confirmed before construction.

Existing bike racks will be moved from the current location to the base of the bridge, where there will be weather protection, CCTV and lighting.

We will include wayfinding to help people with the transition between the bus interchange, shared path and cycleway and train station.

Changes we’re making because of the feedback

We listened to your feedback and we will:

  • add anti-climb/throw/ jump screens as a core safety feature in the final design
  • include weather protection/canopies in the final design
  • work with mana whenua to include cultural design elements.

How we are addressing other important customer, community and stakeholder feedback

The following investigations and designs are underway through the First and Final Leg (FFL) and Public Transport Safety and Amenity (PTSA) programmes:

  • vegetation removal (close to the car park near Merton Street) is underway
  • upgrading the pedestrian underpass prior to the closure of the level crossings
  • reviewing drop-off / pick up areas
  • reviewing more secure bike storage at the station (and more broadly across Auckland) 
  • reviewing whether more AT HOP card readers are needed.
  • delivering the final stage of the Links to GI project along Merton Road. This is due to start from September 2025.

Project designs

An artist's render of the Glen Innes Station pedestrian overbridge.

Community feedback

Project benefits

Safer journeys for everyone

Level crossings increase safety risk and make travel times longer as there's more trains. If we don’t remove or replace them people may take more risks as barrier arms are down more often.

Supports more frequent trains

Removing level crossings helps futureproof the rail network and is part of a broader commitment to better public transport and connected communities.

Reduced travel delays

Removing level crossings helps reduce congestion and helps economic productivity.

Better station accessibility

By adding a lift as well as stairs to the pedestrian overbridge, the station becomes more accessible to everyone.

Project background

In May 2025 we shared our preferred design with customers, the community and stakeholders. We asked for feedback to ensure this new infrastructure will tie in with the existing community and village.

Specifically, we asked for feedback on:

  • access and connection
  • safety
  • bike facilities
  • any other local insights.
An artists impression of the new pedestrian overbridge at Glen Innes Station.
This render was used for engagement with the community in May 2025.
Map showing the location of the new pedestrian overbridge at Glen Innes Station we well as other key proposals including shared path and level crossing removal.
Map of the proposed design for the Glen Innes Station pedestrian bridge, shared with the community in May 2025.
View larger image JPG, 814KB
Download image

To see the page we used to engage with the community, go to Safer access to Glen Innes Station is coming (opens in a new tab).

Subscribe to our newsletter

Subscribe to receive emails for project updates. You can unsubscribe at any time.

Subscribe to our newsletter

Subscribe to receive emails for project updates. You can unsubscribe at any time.