Auckland Transport

Glen Innes shared path project updates

2017


12 September

Feedback on the preferred route for section 4 is open until 8 October 2017.

Find out about the preferred route and have your say.


4 August

AT and NZTA have released the preferred route for section 4, the last leg of the path (between Orakei Basin and Tamaki Drive).

We will seek public feedback on this section next month.

Read the media release: Preferred route announced for Glen Innes to Tamaki Drive section 4.


24 May

AT and NZTA have made a short-list of 3 route options for section 4, the last leg of the shared path (between Orakei Basin and Tamaki Drive). The options are now being taken forward for further investigation that will include geotechnical study and value engineering.

Find out more about section 4.


5 April

Feedback on section 1 of the shared path (the section between Merton and St Johns Roads) was open from 27 March until 4 April 2017. Thanks to everyone who provided feedback.


2016


9 December

This morning, Mayor Phil Goff and Transport Minister Simon Bridges opened section 1 of Te Ara Ki Uta Ki Tai (the path of land and sea). Children from Stonefields School were among the first to ride and scooter on the path.

Glen Innes shared path stage 1 opening (2)


6 December

Get ready to ride! Section one is open to the public from midday Friday 9 December. Coast downhill from St Johns Road to Merton Road, then wind your way back for a coffee and a view of east Auckland.

Eastern path connection coming up to St Johns Rd

Approaching the connection with St Johns Road.

Eastern path looking towards Glen Innes

Looking toward Glen Innes.

Greening the Eastern path

Greening the path.


28 July

The project team recently hosted members of the Orakei Local Board and Bike Auckland on a site tour of section one. The path is taking shape and is on track for a late October opening.

Earth ramp towards St Johns Road

This earth ramp will reduce the gradient as the path climbs towards St Johns Road. This will be grassed and planted once the path is built. 

Rippling of path

The rippling in the path is where it levels out at regular intervals. This makes access for wheelchair users easier and will help reduce downhill speed. 

Paths from St Johns Road and Merton Road

The path is being built from the St Johns Road and Merton Road ends and will meet in the middle. 


9 June

Work is underway to connect the walkway between Felton Mathew Ave and Apirana Ave with the Glen Innes to Tamaki Drive Shared Path.

We have had to divert an old unmarked stormwater pipe. This additional work has increased the time the walkway will be closed. We now expect it to be reopened in late June.

During the closure, Glen Innes station can be accessed from Merton Road and Apirana Ave.


18 May

The notification period for the consent applications for sections 2 and 3 has ended. A decision is expected in late July.


10 May

Walkway closed mid-May to mid-June

Work is underway to connect the walkway between Felton Mathew Ave and Apirana Ave with Glen Innes to Tamaki Drive Shared Path.

A raised concrete table will be built at the path junction, to keep speeds low and pedestrians safe.

During this time, Glen Innes Station can be accessed from Merton Road and Apirana Ave.

Map showing the closed walkway

Map showing the closed walkway


15 April

Before continuing the path through Meadowbank and Orakei in late 2016, we have shared our path designs for the next phase with the community at 2 open days.

Thank you to everyone who came along to the open days.

The consent applications for sections 2 and 3 have been notified and can be viewed on the Auckland Council website

Photos from the Glen Innes to Tamaki Drive Shared Path open days

Glen Innes to Tamaki Drive Shared Path open day

Glen Innes to Tamaki Drive Shared Path open day


13 April

We held a busy first open day, with lots of people visiting St Chads Church to view the new path designs.

The second open day will be held on 14 April 2016.

This week, we applied to Auckland Council for the consents needed to build sections 2 and 3. 


1 April

Read the latest project newsletter (PDF 484KB)


11 March

 Section one is taking shape. The photos below show the route up and down the hill between Merton Road and St Johns Road.

 Gi TrackGi Track 2


2015


23 November

A helicopter has delivered equipment to test ground conditions at locations within the Meadowbank section of the Glenn Innes to Tamaki Drive Shared Path route. This section (2) will begin construction in late 2016.

Image: Some areas of the route are difficult to access, so the helicopter has been used to transport testing equipment.

Helicopter Delivering Equipment November 15

Image: A contractor attaches a longline and cargo hook to the helicopter.

Contractor Attaching Longline To Helicopter November 15

Image: Looking along the path route from Kohimarama towards Meadowbank.

Helicopter Along Path Route From Kohimarama To Meadowbank


21 October

The start of construction of the Glen Innes to Tamaki Shared Path has been marked by a dawn blessing and sod-turning ceremony attended by the Minister of Transport and Mayor of Auckland.

Read the media release and see photos of the ceremony.


13 October

Construction of section 1 begins on Thursday 22 October 2015. Section 1 should be completed in mid 2016 and the whole project is scheduled to be completed in late 2018.


9 September

Since feedback closed in December 2014, we have further developed the path route and design for section one (Merton Road to St Johns Road).

AT received 127 submissions, with a majority giving positive feedback on the project.

Comments focussed on the way in which the path improves connectivity to the city and links with public transport along the way. 


2014


22 December

Feedback on the path closed on 19 December. AT is reviewing submissions and will report back in the new year.