North Urban Auckland flood recovery progress North Urban Auckland flood recovery progress

Damage has been caused to roads by the recent extreme weather events in Tāmaki Makaurau / Auckland.

Read the North Urban Flood Recovery Update - December 2023 and keep updated on the progress of the repair work in your area. 

We ask for patience while trying to repair sites all over Auckland.

To report new issues, please contact us.

Dairy Flat Highway, Dairy Flat

Road status: Open.

December 2023

Works started this month on two large slips close to each other along Dairy Flat Highway.  Two timber retaining walls will be constructed in this area.  We are currently working on the piles and anchors.

Photo Credit: Auckland Transport and Fulton Hogan

Gills Road, Albany

Road Status: Closed

Slip remediation works are underway on the lower portion of Gills Road where the downhill side of the road is continuing to subside. 

December 2023 

Vector has carried out works to secure the leaning power pole and install a switch to divert power from the overhead lines. This piece of work was necessary to ensure the site is safe to undertake the slip repair works. 

January 2024 

Our contractor Fulton Hogan has begun repair works on the lower section of Gills Road to mitigate further damage and ensure the road is fit for purpose in the future. 

This site repair is significant and requires large piles and anchors to be installed to retain the embankment (see similar works in the image below). We have closed this section of Gills Road to allow large machines to work safely within the limited work space available on this narrow section of road. 

Works began on Monday 29 January and we expect them to continue until early April.

Works similar to this will take place on Gills Road
Works similar to this will take place on Gills Road
Gills Road Works Site
Site where works will take place

 

Time to complete: 10 weeks, weather dependent.  

Access restrictions: No vehicles are allowed through the section where works are being undertaken. These restrictions will be in place 24 hours a day. Pedestrians will continue to have access through the site. 

  • There will be changes to your usual route driving down into Albany Village which will add to your journey time. To keep you and our team safe, please follow the instructions of the onsite traffic control team and plan ahead. 
  • All heavy plant machinery and equipment will stay onsite during the works. As the road is very narrow in the section where the works are taking place, the machinery will occupy both lanes, necessitating the road closure. 
  • This work involves machinery which can create noise, vibration and dust. All efforts will be made to minimise these disturbances as much as practically possible. Works will only be carried out during daylight hours, Monday to Friday, and some Saturdays if required. 
  • To ensure the safety of you and your whānau, please keep young children and animals well supervised and away from the work area.

East Coast Road / Haigh Access

December 2023

A concrete retaining wall has been constructed to support the road and prevent further slips.

September 2023

As part of the road maintenance, a significant repair needs to be undertaken on East Coast road, close to Haigh Access.

This work will include a retaining wall, kerb and channel and pavement rehabilitation. To allow this works to be undertaken safely, a steel barrier will be installed, prior to works starting.

Works begin: Monday 18 September

Time to complete: 13 Weeks

Time: 7am to 7pm, Monday to Saturday

  • We will install signage, barriers and road cones the day before the retaining wall works begin.
  • Please park away from the work area during the working hours above. We may need to tow vehicles parked in the work area to a safe position a short distance from the work site. We will make every effort to locate the owner before towing.
  • There may be changes to road layout and access. To keep you and our team safe, please follow the instructions of the onsite traffic control team and plan for some delays.
  • We will park our equipment on within the worksite, behind the barriers, during the works. Please contact us if that causes you any problems.
  • This work involves heavy machinery which can create noise, vibration, and dust. All efforts will be made to minimise these disturbances as much as practically possible.
  • To ensure the safety of you and your whanau, please keep young children and animals well supervised and away from the work area.

Hinemoa Terrace, Birkenhead

Road status: Closed, Access only for residents.

Hinemoa Terrace was damaged by a slip as a result of the storm events in early 2023.  A new timber retaining wall is to be constructed, with works carried out mainly from the top of the slip on Hinemoa Terrace.

15 February 2024

Construction is progressing well with piling underway to support a retaining wall.

2 February 2024

  • Contractors are moving equipment to the site prior to starting construction work next week.
  • Due to the narrowness of Hinemoa Terrace, and large machinery required for the repairs, access to properties will be restricted at times.
  • All vehicles will need to park outside of the works area on Hinemoa Street.

January 2024

  • Utility works in progress.
  • Wall construction works to start early February.

December 2023

Final designs completed.

20 July 2023

Awaiting Vector and Chorus service relocations and new streetlight layout

3 May 2023

  • Geotechnical testing is complete, and our contractor Fulton Hogan is now working on the final designs and specifications.
  • We’re currently working with Vector to find the best solution for the location of power lines.
  • Road status – closed in both directions.

26 April 2023

  • Finalising design with community board support.
  • Road status – closed, open to residents only.

Marine Parade Reserve, Bayswater

Road status: Open.

Sir Peter Blake Parade, adjacent to Marine Parade, was damaged by a slip as a result of the storm events in early 2023. A new 30 metre timber retaining wall will be constructed next to the carpark access road.

22 February 2024

Work is scheduled to begin next week to repair the slip, which is expected to take around five weeks.

  • Work will take place between 7am and 7pm, Monday to Saturday, from 26 February 2024.
  • Marine Parade Reserve carpark will remain closed to pedestrians and vehicles for the duration of the works.
  • Access through Sir Peter Blake Parade will be narrowed during the works. AT contractors will use a mix of temporary
    traffic management including a lower speed limit and shoulder closure, with stop/go at times.
  • Traffic controllers will help to manage pedestrian access. Please follow all signs and traffic directions.
  • On street parking will be limited while the works are undertaken.

Paremoremo Road, Lucas Heights

Road status: Open - Single Lane.

December 2023

Work started in November on site #2 on Paremoremo Road.  A massive slip reduced the road to one lane in this location.  The scale of the slip can be seen in the image immediately below.  Fulton Hogan on behalf of Auckland Transport are installing a new 70m timber retaining wall.  This wall consists of 46 timber poles along with 40 12-metre long anchors.  The retaining wall is now finished and the team are working on the pavement and new footpath through December.

Photo Credit: Fulton Hogan and Auckland Transport

Ridge Road, Lucas Heights

Road status: Open to Residents Only.

December 2023

Work started in October on Ridge Road to repair two major slips along the road. Great progress has been made installing two timber piled retaining walls. The team are now focused on stabilising the road area itself.  Two failed stormwater pipes will also be replaced before the final pavement is repaired prior to reopening.

In a very unique situation, the only way for a young neighbour Tyler Parker to get to his school bus each day is to walk through the construction site.  Every morning and every afternoon, our traffic controller on this site stops the works and escorts Tyler to and from home.  

Check out this feel-good video on LinkedIn here.

4 October 2023

Works will begin on 9 October 2023 and we expect works will take six months to complete, weather dependant.

There will be restrictions to the traffic with lane closures and detours in place.  Hours of work are 7am – 7pm Monday to Saturday.

6 September 2023

Plans at the slip sites on Ridge Road are still being finalised, working on resolutions to the gas line and power sources. 

20 July 2023

Designs have been completed for 2 adjacent sites on Ridge Road. Construction planning is in progress

25 May 2023

  • We are currently undertaking geotechnical testing and initial designs to build several retaining walls to support the road where slips have occurred
  • We will begin works in early 2024 and expect to be finished by Mid 2024
  • Road status: One lane open

Tauhinu Road and The Close, Greenhithe

Road status: Open - Single Lane.

December 2023

Works are in progress at the intersection of Tauhinu Road and The Close in Greenhithe. Repairs will consist of placing concrete blocks in a terraced arrangement within the deep gully. The site will be fully planted once stabilised.  This is a large and steep site for the team and will take several months to complete.  It is currently programmed for completion April 2024.

Photo Credit: Auckland Transport and Fulton Hogan

4 October 2023

Works began on 2 October 2023 and we expect works will take up to March 2024 to complete, weather dependant. The works consist of constructing a stepped arrangement of block walls to protect the road from future stream damage.

There will be restrictions to the traffic with lane closures and detours in place.  Hours of work are 7am – 7pm Monday to Saturday.

Residents have been informed via a letter drop sent 29 September 2023.

Twin Wharf Road, Herald Island

Road status: Open - Single Lane.

January 2024

Final design is being reviewed.

20 July 2023

Preliminary design is being reviewed.

3 May 2023

  • We are currently undertaking geotechnical testing and initial designs to build a new retaining wall to replace the previous wall that has collapsed.
  • We plan to begin construction in early 2024 and, weather permitting expect to be finished by mid 2024.
  • Road status – one lane open.

Wade River Road, Stanmore Bay

Road status: Open - Single Lane.

January 2024

Design in being finalised.

20 July 2023

Design in progress.

25 May 2023

  • We are currently undertaking geotechnical testing and initial designs to build a new retaining wall to replace the damaged one
  • We plan to begin construction in early 2024 and, weather permitting, expect to be finished by mid 2024
  • Road status: One lane open

Upcoming construction

December 2023

New construction works are currently planned to start on the following roads from January 2024:  

  • Scott Road, Stillwater

  • Twin Wharf Road, Herald Island

  • Riverhaven Drive, Wade Heights

  • Swale and culvert clearing across the North Urban area

  • Hydro-seeding of minor slip sites

Please note all works are subject to changes due to a number of factors such as weather, resourcing and delivery of supplies.  Information contained here is for general purposes only to provide a guide as to works this month.