West Auckland flood recovery progress West Auckland flood recovery progress
Extreme weather events in 2023 caused damage to roads throughout Tāmaki Makaurau / Auckland. On this page, you can stay up to date on the progress of repair works in your area.
West Auckland road updates
Not all sites are listed on this page, as some have already been repaired. Design work on others is still ongoing, and other roads will be added as we work through the programme. Works may be completed on some roads without being added to this page, depending on the scale of the work and the number of residents affected.
We ask for patience as we work to repair more than 2,000 sites across Auckland.
To report new issues, please contact us.
Huia Road – various sites
4 November 2024
There are multiple slip sites along Huia Road. We are looking for ways to keep one lane open on all sites while work in progress. We will update the community before works start on any of these sites.
81 Huia Road – Works are planned to start in January after Scenic Drive, Titirangi is open to traffic.
370 Huia Road – We plan to start work on this site in December 2024 and finish by the end of January 2025.
634 Huia Road – Work will begin in February 2025 and is expected to be completed by the end of March 2025.
100m past Cornwallis Road – We plan to begin work in October 2024, and we expect the work to finish by December 2024.
100m past Kaitarakihi Road – Work will begin in March 2025. We expect to finish by the end of June 2025.
We are investigating one more site. Once the plan is confirmed, we will update the community about estimated work dates.
Karekare Road
4 November 2024
Karekare Road was closed on 19 August 2024 for slip repair.
Slip repair works have progressed well on Karekare Road and Lone Kauri Road. Works on the 2 remaining sites on Karekare Road (K4 and K5) were planned to be completed by December 2024.
The first site is completed and we are working on site K5, and progress is going well.
We have been monitoring the banks near these sites and will be also completing more rock scaling (removing loose material and rocks) and soil nailing to make this area more secure.
Kay Road, Waitākere
Closed - Residents and emergency services access only from Waitākere Road end.
Work is under way on the repair design.
While are unable to give a specific timeframe on repair works. We aim to restore this connection for the community in the first half of 2025.
Kellys Road, Oratia
4 November 2024
We started work on the slip repair on Kellys Road on 2 October 2024. Vector isolated the overhead powerlines during works.
We have completed the excavation and preparation works and have built a temporary structure to support the machinery while we build the permanent retaining wall. The UC piles for the retaining wall are being installed. The road remains closed during works.
We expect works to be completed in mid-December depending on weather.
Konini Road, Titirangi
4 November 2024
Repairs for Konini Road are in the design phase.
We do not plan to start works on Konini Road while Scenic Drive is closed. Konini Road repairs will start in 2025, after Scenic Drive. From Woodlands Park to Titirangi is open to traffic.
Lone Kauri Road, Karekare
14 August 2024
Karekare Road is closed for the rest of 2024 for slip repair.
Following Karekare Road’s completion, Lone Kauri Road will be closed in January 2025 to complete one more site (L4).
Mountain Road
16 October 2024
We are still on track to complete the 10 sites on Mountain Road by the end of 2024.
Each site has been named for its distance from Scenic Drive. For example, site 0.655 is 0.655km from Scenic Drive.
We have finished sites 0.655 and 0.712.
GSI completed the structural work on sites 1.833 and 1.664. Pavement repairs will start on these sites on 15 October 2024.
Repairs on site:
- 1.833 will last for 10 working days, ending on 29 October 2024
- 1.664 will last for 40 working days, ending on 12 November 2024.
GSI are currently working on sites 2.775, 1.468 and 1.387.
Repairs will take:
- 40 working days on site 2.775, ending 8 November 2024
- 30 working days on 1.468, ending 1 November 2024
- 45 working days on 1.387, ending 6 December 2024.
We will be starting work on site 1.318 at the end of October. Repairs will take 35 working days, ending 6 December 2024.
We will start repairs on site 0.899 on 5 November 2024. Works will last 30 working days, ending 16 December 2024.
Our schedules for each site may change depending on final designs and weather.
We will keep you updated with any changes and provide updates on each site as we progress.
We must consider that:
- we can only work on 2 sites at any given time, due to the narrowness of the road and access through sites
- in some places, road layouts might make it too unsafe to work on 2 sites at once
- site designs must be approved before works can start, and work on some of these designs is still ongoing
- although we have built some flexibility into the timeline, weather and other factors may cause delays.
Ngaio Road, Waima
4 November 2024
We are doing geotech monitoring on Ngaio Road and working on the repair design for this slip. A section of the road is coned off, though a newly created pedestrian path will keep people safe and keep vehicles off the damaged section.
Because we need to provide safe passage for pedestrians, we have had to extend the pedestrian walkway onto the road. This has narrowed the carriageway to around 4 metres, which is not enough space for 2 lanes and offers no visibility for giving way. Please use the detour route.
Part of the cyclone recovery, this work is scheduled for the first quarter of 2025.
Paturoa Road, Titirangi
20 November 2024
We have a final design confirmed for the major slip on Paturoa Road. Although the design is ready, we have found that the timber pole retaining wall nearby is also failing. We are in the design process for the repair of this wall. We will need to complete this work first so that we have secure access to the main site. We will update the community when the work starts. In the meantime, a crew will occasionally be onsite. They will be drilling a bore hole for investigation at this location.
While the slips on Paturoa Road are significant to fix, the repair work is important. Paturoa Road provides an alternative option for Titirangi Beach Road, Aydon Road and Mahoe Road.
Piha Road
4 November 2024
Works on the slip site at 73 Piha Road were completed in December 2023.
After further monitoring of this location – we are working on the design of an extended area to be supported by an additional retaining wall.
We are working through finalising the plans for this new section of retaining wall, and plan to start work on the construction in the Summer of 2024/25.
Rayner Road, Piha
31 July 2024
47 to 49 Rayner Road, Piha
Flexi-posts have been installed to keep vehicles away from the slip side of the road. The weight restriction is lifted. Our contractor is continuing to monitor this section of the road.
Scenic Drive, near Arataki
4 November 2024
The slip repair near 412 Scenic Drive, Waiatarua, is completed and the road is open through this section for residents only. There is no through access to Arataki Visitors Centre or Titirangi, as there are two other major slips under repair.
There are two slips in the section of road before Arataki Visitors centre.
Slips in both locations affect half the width of the road. The machinery used in the repairs will sit on the remaining section of the road. The road is fully closed in this location, and there is no pedestrian or cycle access through.
At this stage, we expect these sites to be completed by the end of February 2025.
Slip sites on Scenic Drive between Arataki Visitors Centre and West Coast Road
Scenic Drive, Titirangi
4 November 2024
We are working on the third section of retaining wall. This wall will be 76m long and will join the first 2 sections together. We have installed 30 out of the 50 piles for this retaining wall.
We are also working on a repair to the embankment above the road. Over winter this section deteriorated more. We are working with the property owners to stabilise this section and build a buttress wall to prevent further slips above the road. We expect to open this section of the road by Christmas 2024, weather dependent.
We put together a behind-the-scenes video with our contractor, Fulton Hogan. To view the video, visit our Facebook page.
Update on timeframe for Scenic Drive, Titirangi – 8 August 2024
The timeframe for slip repairs to Scenic Drive, Titirangi has changed. Originally, we were working on 2 major slip repairs. During works we decided to fix a third damaged section 76m long that has not collapsed yet, but will slip if the road is open to traffic.
The first 2 sections are almost 90% complete. However, we have experienced delays in the design for the third section. There has been some complexity in getting the structural components of the wall design correct. This element is essential as the road must withstand the load of heavy vehicles. This design delay has deferred the start of construction of the retaining wall.
Our contractors have begun rock scaling the embankment above this section of the road. Rock scaling involves working on abseiling equipment to assess the stability of the embankment, and to remove any unstable sections or rocks from the rockface.
We undertook a geotechnical assessment of the embankment above the road corridor. We discovered a section of the embankment which is at risk of failure. There are large fissures, or cracks, in the rocks and there is potential risk that this will collapse onto the road. We are planning to build a buttress wall to protect the road from this embankment. Although this damage is not on AT property, we will need to address this risk before the road can be opened.
This section of road between Woodlands Park Road and the roundabout will now be closed until late December 2024. We know this will be an additional disruption to the community.
This section will remain closed to pedestrians and cyclists. Kohu Road will remain closed at the Scenic Drive end, except to pedestrians and cyclists.
Impact on bus routes: School buses will continue to take the detour, and the shuttle bus will continue to serve Woodlands Park Road until the road is open.
The following bus routes are affected by the closure:
Bus Route Number | Changes |
Glen Eden Intermediate 073 and 074 Green Bay High School 075 and 076 |
From Monday 4 March, school bus routes and times will start 10 minutes earlier in the mornings to accommodate the detour. You should also expect the bus to arrive back a little later due to the detour. |
Public Bus Route 171 |
From midday 27 February, the 171 bus will service Laingholm only, following the usual route, but will miss Woodlands Park Road and take Huia Road to and from Titirangi. A shuttle bus service will meet the 171 bus in Titirangi to transfer passengers to and from Woodlands Park Road bus stops during the closure of Scenic Drive. A shuttle bus timetable is available. Please note: This timetable is based on approximate travel times. We recommend arriving at your bus stop on the earlier side. |
Detour route
During the works, this section of Scenic Drive will be closed. The detour route will be along Woodlands Park Road and Huia Road, as shown in the map. We understand the inconvenience this may cause and ask drivers to plan ahead and allow extra time.
We’ve received questions from the community about the detour route and have put together some FAQs about Scenic Drive, Titirangi (PDF 148KB).
Scenic Drive, Waiatarua (elevation site)
30 May 2024
Interim road repair works at this site are complete, and the road is open both ways. We are pleased to have this important connection open for the community. We will do a final road reseal when other drainage works in this area are finished.
What happens next?
Final design plans are progressing for this site. A series of fan drains will be installed to reduce pore pressure from within the slip. We are working with property owners in this section of the road to finalise plans for these works. After we complete the drainage then the final repair will be made to the road pavement.
The road pavement and road surface drainage repairs will be from approximately driveway of 469 Scenic Drive to driveway of 461 Scenic Drive.
Simpson Road
20 November 2024
There is a slip outside 163 Simpson Road. It extends approximately 107m, with 77m of significantly affected carriageway. The failing retaining wall is along the edge of the road, on the downslope side.
In our final preparations for the physical works we have discovered a utility pipe that is in a different location from the plans. We have paused starting work on this site while we investigate further.
Full Road Closure during works
The road will be closed at this section once works start. The extensive damage to the road requires a full closure to repair. Once we have finalised the plans we will let the community know the start date.
Residents will have access to their homes from either side of the road closure.
Takahe Road, Titirangi
4 November 2024
The slip repair on Takahe Road is completed, with the block retaining wall, new drainage, planting and repair to the road surface.
The road is fully open to traffic.
The contractor does have some minor finishing touches to complete, but these will not require any road closure.
A power pole near the top of the wall will be relocated to its original position at the foot of the wall by Vector. It was put in its current position temporarily to maintain power for the community while the slip was repaired.
Taunton Terrace, Blockhouse Bay
20 November 2024
Work will begin on the slip outside 4 Taunton Terrace on Wednesday 27 November. We expect the work to take 7 weeks, weather dependent.
The repairs will include vegetation clearing, soil nailing and shotcreting (sprayed concrete).
Walkway closed during works
The section of walkway below this site (The Manukau Coastal Walkway, Taunton Terrace) will be closed during working hours to make sure the public are kept safe from any debris that may come loose during construction.
Road closed during works
The work requires a full road closure to complete the repairs. Residents will have limited vehicle access during the workday. We will operate the following timetable:
8:45am to 12:15pm - road closed for works
12:15pm to 1pm - road open for resident access only
1pm to 3:15pm - road closed for works
3:15pm to 4pm - road open for resident access only
4pm to 5:30pm - road closed for works
From 5:30pm to 8:45am the next day and on weekends - road open with one lane access under priority give way.
Emergency vehicle access will be managed by the crew on site.
Te Henga Road
20 November 2024
Work on Te Henga Road began on Monday 19 August. The slip is located near the intersection of Te Henga Road and Falls Road.
The road is closed from 60 to 66 Te Henga Road.
A wall made of compacted layers of gravel has been constructed at this site. This week we are working on the pavement repair and will lay the asphalt. We expect this site to have 1 lane open by end of day Saturday 23 November.
Next week the team will be working on final touches, including installing a safety rail.
We plan to have this road re-opened by the end of November 2024.
Wairere Road
On 14 October 2024, Fulton Hogan started repairs near 349 Wairere Road. We needed to fully close the road while these works are in progress, as machinery will block narrowest section of the road.
We have now completed the first section of the repairs, we hope to open one lane to traffic, most of the day, except at times when we need to move equipment or to spray concrete onto the slip face.
On days when we need to close the road for concreting we will open the road for 5-minute windows at set times throughout the day. For information about the closure, including the timetable for openings, download the Wairere Road closure FAQs (PDF, 765KB).
Emergency access: Our contractor will work with emergency services to allow access in case of emergency.
Contact us with your email address or to sign up to join the WhatsApp group
We understand that this will be a challenging time for residents. We have created an email list so we can communicate with everyone affected by this work. Our contractor is also running a WhatsApp notification group, when the traffic controller can notify the community any changes to the road open times in real time. Please email us at atengagement@at.govt.nz.
We expect this slip repair to be completed in December 2024.
Waitākere Road Bridge – underpass closed
The underpass is closed at the bridge at the intersection of Waitākere Road and Bethells Road.
We have installed extra crossing signs and hit sticks on the approach to Bethells Road Waitākere Road (township end) to improve visibility and safety.
On 1 April 2023, the speed limit was lowered to 60km/hr near the intersection (between 190 metres north of Bethells Road and 220 metres south of Township Road).
6 September 2024
We are currently designing the repair to the underpass. It is not safe for pedestrians to use.
We will update you when repair works begin.
The bridge is also scheduled for scour protection works. We will check if there have been changes to the stream bed below the bridge and make any necessary repairs.
West Coast Road, Oratia
Works to repair the slip on the edge of the road on West Coast Road, between Parker Road and Carter Road is planned to begin in late November 2024.
There is a slip that is under the road at this location just above the stream. A new retaining wall will be built and drainage on both sides of the road will be upgraded.
While we are working in this area, we will try to maintain two lanes of traffic at most times, however at times one lane may be closed to complete some portions of the work. Please plan ahead, and follow traffic management.
Woodlands Park Road, Waima
4 November 2024
Work on the repair design is progressing. As this road is part of the detour route for Scenic Drive, we will schedule the repair work after the Scenic Drive link to Titirangi reopens.
Due to the nature of this slip, we plan to begin work in the drier months and will start in early 2025.