East & South Auckland flood recovery progress East & South Auckland flood recovery progress

Extreme weather events in Tāmaki Makaurau / Auckland caused damage to roads in 2023.

Over the last 18 months or so, we have made significant progress on repairing storm-damaged roads in the East and South Auckland area.

Reported sites and slip repairs in East and South Auckland as of 31 December 2024

  • Total number of sites: 30 (21 major, 9 minor)
  • Currently under construction: 0 (sites closed for holidays)
  • Completed sites: 20 (67%).

We have completed:

  • 16 out of 21 major slip repairs (62%)
  • 4 out of 9 minor slip repairs (44%).

There are no major sites under construction.

Summary of south and east Auckland flood repair sites

The reported number of sites requiring minor to major repairs will change slightly over time as the design and investigation of each slip site develops.

We ask for your patience as we repair sites all over Auckland.

To report new issues, please contact us.

Completed slip repair sites

The following is a list of recently completed major slip sites in the eastern and southern areas of Auckland. Our thanks go to everyone in these communities for your patience and understanding as we made necessary repairs and restored safe connections.

  • Awhitu Road, Pollok (2 of 2 sites)
  • East Street, Pukekohe
  • Grahams Beach Road, Manukau Heads
  • Hunua Gorge Road, Hunua
  • Kingseat Road, Patamahoe
  • Laing Road, Karaka
  • Linwood Road, Karaka (2 sites)
  • Marine Parade, Mellons Bay
  • McNicol Road, Clevedon
  • Monument Road, Clevedon (2 sites)
  • Otau Mountain Road, Clevedon
  • Skyhigh Road, Hunua
  • Te Tero Road, Pollock
  • Union Road, Makau.

East Coast Road, Whakatiwai

Road status: open, single lane

We're designing repairs needed on East Coast Road. Construction is planned for 2025.

Kemp Road, Awhitu

Road status: open

We're designing repairs needed on East Coast Road. Construction is planned for 2025.

Kohekohe Kariotahi Road, Waiuku

Road status: open

18 December 2024

We're designing repairs needed on Kohekohe Kariotahi Road. Construction is planned for 2025.

Manukau Heads Road, Awhitu Peninsula

Road status: closed, resident access only

10 December 2024

We've finished the design and a physical works tender has been released. We're now looking at tenders. We expect a successful contractor will be picked in January 2025. 

20 November 2024

We have advertised a physical works tender to realign the road around the section that was destroyed. This work will also include drainage pipes to redirect water and remove the risk of flooding damaging the new road.

We plan to begin construction in January. This will take 4 months to complete.

9 July 2024

Design and project planning continues.

14 February 2024

The project team has completed geotechnical testing and a hydrology assessment. Their recommendation is to reestablish the road link by building a short road bypass at the slip site. Preparation of the detailed design and resource consent is under way. The project will include stormwater work to prevent storms from causing the same damage in the future.

20 July 2023

  • A safety fence to restrict access at the slip location has been installed. 
  • ‘No access to lighthouse’ signage has been installed.
  • The local access gate has been upgraded, for use by residents only.

17 May 2023

On Manukau Heads Road, Awhitu Peninsula, a major slip occurred just a few hundred metres from the Manukau Lighthouse. The slip severed the road connection, and public access to the lighthouse and nearby properties is unavailable. The following aerial photo shows the extent of the slip, which extends approximately 80 metres downwards from the road.

An estimated 90,000 cubic metres of soil moved during the slip.   

Image showing an aerial view of the major slip on Manukau Heads Road, Awhitu Peninsula

Initial assessment

The initial assessment indicates that stabilising the slip and restoring the road connection will not be a short process. A robust evaluation of repair options and site investigations are needed to ensure that the correct information informs decision-making before funds are committed to the design and construction of a permanent solution. 

With restoration of the road connection being 12 to 18 months away, discussion around whether temporary public access should be restored in the interim is needed. This will also be a lengthy process because it involves land that AT does not own.

The most recent traffic data indicates that during the summer of 2020 (before the slip), about 240 vehicles travelled to the lighthouse per day. 

Manukau Lighthouse

Road access to the lighthouse remains closed to the public.

Urquhart Road, Karaka

Road status: open

18 December 2024

We're designing repairs needed on Urqhart Road. Construction is planned for 2025.