East & South Auckland flood recovery progress East & South Auckland flood recovery progress
Extreme weather events in Tāmaki Makaurau / Auckland caused damage to roads in 2023.
Over the last 18 months or so, we have made significant progress on repairing storm-damaged roads in the East and South Auckland area.
Reported sites and slip repairs in East and South Auckland as of 31 August 2024.
- Total number of sites: 34 (24 major).
- Currently under construction: 2 (all major).
- Completed sites: 20 (59%, 12 major).
South summary, September 2024
- 24 major slip sites
- 10 minor slip sites
- 8 of the 10 minor slip sites are complete
- 12 of the 24 major slip sites are complete
Major slip sites currently under construction are:
- Awhitu Road, Pollock
- Grahams Beach Road, Manukau Heads.
Upcoming sites include:
- Hunua Gorge Road, Hunua
- Union Road, Makau.
The reported number of sites requiring minor to major repairs will change slightly over time as the design and investigation of each slip site develops.
We ask for your patience as we repair sites all over Auckland.
To report new issues, please contact us.
Completed slip repair sites
The following is a list of recently completed major slip sites in the eastern and southern areas of Auckland. Our thanks go to everyone in these communities for your patience and understanding as we made necessary repairs and restored safe connections.
- Awhitu Road, Pollok (1 of 2 sites)
- East Street, Pukekohe
- Kingseat Road, Patamahoe
- Laing Road, Karaka
- Linwood Road, Karaka (2 sites)
- Marine Parade, Mellons Bay
- Monument Road, Clevedon (2 sites)
- Otau Mountain Road, Clevedon
- Skyhigh Road, Hunu
Awhitu Road, Pollok
Road status: open, single lane
9 September 2024
Work is progressing well to repair the slip near #1966 Awhitu Road (original slip shown below left). The team have now finished all the soil nail and shotcrete work. Drainage installation and pavement repairs will take place this month.
9 July 2024
Two slips have occurred on Awhitu Road, near property numbers 1966 and 2049.
A new retaining wall is now in place at the slip near 2049 Awhitu Road. All traffic management has been lifted and the road is fully open at this site.
Work on the slip near 1966 Awhitu Road started on 24 June 2024. This is a large slip and will take approximately 6 weeks to repair. Reinstating the slip area will involve installing soil nails, a concrete retaining wall, and guardrail and pavement works.
Stop/go traffic management will be in place when the contractor is working on the site. After hours and weekends, a traffic signal will manage traffic flow.
Before the works started, the site was blessed by local iwi and a powhiri held at Awhitu School. AT and Liveable Streets, the contractor for these works, have held 2 sessions with Awhitu School, including a site visit to see the dramatic slip on Awhitu Road.
Grahams Beach Road, Manukau Heads
Road status: open under restriction
9 September 2024
The team came back to the site in late August to begin soil nail installation. Work is expected to take about one month.
Manukau Heads Road, Awhitu Peninsula
Road status: closed, resident access only
9 July 2024
Design and project planning continues.
14 February 2024
The project team has completed geotechnical testing and a hydrology assessment. Their recommendation is to reestablish the road link by building a short road bypass at the slip site. Preparation of the detailed design and resource consent is under way. The project will include stormwater work to prevent storms from causing the same damage in the future.
20 July 2023
- A safety fence to restrict access at the slip location has been installed.
- ‘No access to lighthouse’ signage has been installed.
- The local access gate has been upgraded, for use by residents only.
17 May 2023
On Manukau Heads Road, Awhitu Peninsula, a major slip occurred just a few hundred metres from the Manukau Lighthouse. The slip severed the road connection, and public access to the lighthouse and nearby properties is unavailable. The following aerial photo shows the extent of the slip, which extends approximately 80 metres downwards from the road.
An estimated 90,000 cubic metres of soil moved during the slip.
Initial assessment
The initial assessment indicates that stabilising the slip and restoring the road connection will not be a short process. A robust evaluation of repair options and site investigations are needed to ensure that the correct information informs decision-making before funds are committed to the design and construction of a permanent solution.
With restoration of the road connection being 12 to 18 months away, discussion around whether temporary public access should be restored in the interim is needed. This will also be a lengthy process because it involves land that AT does not own.
The most recent traffic data indicates that during the summer of 2020 (before the slip), about 240 vehicles travelled to the lighthouse per day.
Manukau Lighthouse
Road access to the lighthouse remains closed to the public.
Monument Road, Clevedon
Road status: open
9 September 2024
On 24 June 2024 we started to repair the two slips on Monument Road. Work is now complete and the road reopened. AT and our contractor would like to thank the local community for their patience during these repairs.
9 July 2024
Enabling works started on 24 June 2024 and are now well under way.
Repairs include the construction of a timber retaining wall, drainage improvements, and guardrail and pavement works. The work should take 6 weeks to complete, weather dependent.
The road is fully closed during construction due to the space needed for construction equipment. A detour provides general access to the Hunua/Clevedon area. Resident access is available at all times.
McNicol Road, Clevedon
Road status: closed, resident access only
9 September 2024
Work started this month on two small retaining walls and rock armour protection to repair the slip on this road. We expect to complete repairs within the month.
9 July 2024
Design is in progress, and AT is looking for options to restore access to all motorists. This road provides access to one resident only.
Hunua Gorge Road, Hunua
Road status: open
9 July 2024
Design is complete, and we are looking to resource construction in September. Traffic management has been changed to allow for 2-way traffic flow.
Union Road, Mauku
Road status: open, single lane
9 July 2024
Design is complete, and we expect to start work at the site in September or October.