Aotea flood recovery progress Aotea flood recovery progress
Aotea, Great Barrier Island
Extreme weather events in Tāmaki Makaurau / Auckland caused damage to roads in 2023.
For monthly progress statistics covering all Central, Aotea and Gulf Islands flood repair works, see the Central Auckland tab.
We ask for your patience as we repair sites all over Auckland.
To report new issues, please contact us.
Completed slip repair sites
The following is a list of recently completed slip sites on Aotea, Great Barrier Island. Our thanks go to everyone in these communities for your patience and understanding as we made necessary repairs and restored safe connections.
- Blind Bay Road, Okupu (2 sites)
- Cape Barrier Road, Tryphena (2 sites)
- Medland Road, Medlands Beach
- Motairehe Road, Motairehe
- Puriri Bay Road, Tryphena (9 of 9 sites)
- Whangaparapara Road, Whangaparapara (3 sites)
Aotea Road, Awana
Road status: open
1 August 2024
Three slip sites on Aotea Road are awaiting exemption work from the Department of Conservation.
Subsoil drains through the slump by the Pinnacles seat (site RP8274) have been installed.
June 2024
Three slip sites on Aotea Road are awaiting final design.
Shoal Bay Road, Tryphena
Road status: open, single lane
18 December 2024
One slip site is left to be repaired. We expect to complete repairs in 2025.
1 August 2024
There are 2 slip sites here. We are currently designing slip repairs.