North Rural Auckland flood recovery progress North Rural Auckland flood recovery progress
The North Rural area of the Auckland region was the most severely impacted by the storm events of 2023. We’ve made significant progress on repairing storm-damaged roads over the last 18 months, as shown by the following statistics.
Reported sites and slip repairs as of 30 November 2024
- Total number of sites: 323 (67 major)
- Completed sites: 313 (97%).
We have completed:
- 57 of 67 major slip sites (85%)
- all 256 minor slip sites (100%).
There are 7 slips now under construction:
- Ahuroa Road, Puhoi
- Leigh Road, Leigh
- Pinchgut Road, Kaukapakapa
- Pine Valley Road, Dairy Flat
- Smyth Road, Warkworth
- Takatu Road, Tawharanui (two sites).
The reported number of sites requiring minor to major repairs will change slightly over time as the design and investigation of each slip site develops. We ask for your patience as we repair sites all over Auckland.
To report new issues, please contact us.
Completed slip repair sites
The following is a list of recently completed major sites in the North Rural area. Our thanks go to everyone in each of these communities for your patience and understanding as we made necessary repairs and restored safe connections.
- Ahuroa Road, Puhoi – 5 of 8 slips
- Ashton Road, Leigh
- Coatesville Riverhead Highway, Coatesville
- Goat Island Road, Leigh
- Haruru Road, Wainui
- Kahikatea Flats Road, Warkworth
- Krippner Road, Puhoi – 22 slips
- Mahurangi Road East, Snells Beach
- Makarau Road, Makarau
- Matakana Valley Road, Matakana – 9 of 10 slips
- Moir Hill Road, Warkworth – 11 slips
- Pakiri Road, Leigh and Pakiri – 8 slips
- Pinchgut Road, Kaukapakapa – 1 of 4 slips
- Pine Valley Road, Dairy Flat
- Ridge Road, Riverhead – 2 slips
- South Head Road, Helensville
- Tahekeroa Road, Tahekeroa
- Takatu Road, Tawharanui Peninsula - 6 of 8 slips
- Tauhoa Road, Tauhoa
- Wainui Road, Wainui
- Waitoki Road, Waitoki
- Waiwhiu Road, Dome Valley
- Weranui Road, Wainui – 6 of 6 slips
- West Road, Kaukapakapa
- West Coast Road, Kaipara Flats – 9 slips
- Wishart Road, Helensville – (now monitoring)
Ahuroa Road, Puhoi
Road status: open, single lane with stop/go traffic management
4 December 2024
The Downer team will resume work on Monday 9 December. They will be working on:
- the capping beam of the retaining wall
- soil nails
- drainage.
The team will take a break over the holiday period and return to the site on Monday 6 January 2025. The stop/go system will be operating during this time. The site will also be regularly checked for safety and functionality.
We are now into the last stretch of flood recovery work on Ahuroa Road. We expect it to be complete within the first quarter of 2025.
The road sealing team have also finished work (Stage 2B) along Ahuroa Road. They plan to start the Stage 2C seal extension works in March 2025.
8 November 2024
The site team remains disestablished while AT do back-end work around site anchors. We need to install these anchors into the hillside. This work is ongoing and making good progress. You will hopefully see the site team back on-site soon.
4 September 2024
At site RP7784, east of J Tolhopf Road, all piles have been built. The site team is temporarily away while details for the anchors are being addressed. A lane closure with stop/go traffic signals remains in place.
A Mason Contractors maintenance crew is also working on Ahuroa Road, doing extensive road rehabilitation and some minor slip repairs. The current stage, 2B, should be complete by the end of October 2024. The next stage is scheduled to start construction in January 2025 and will complete the remaining section to J Tolhopf Road.
21 August 2024
All piling work is now complete on the site east of J Tolhopf Road (site RP7784). Work on the timber lagging and drainage behind the new wall is now under way.
26 July 2024
Work east of J Tolhopf (site RP7784) is progressing, despite the weather and difficult ground conditions. To date, 38 of 46 piles have been drilled and concreted.
26 June 2024
Two slip sites, near 849 Ahuroa Road and the ‘hairpin’ bend, are set for final guardrail and line-marking work during the first week of July (weather permitting). This will only require a stop/go lane closure.
Work east of J Tolhopf (site RP7784) started on 27 May. Benching is complete and 4 piles have been installed. The team are encountering some hard rock similar to the other repairs along the road. Approximately 2 months’ work remains at this site. Stop/go and occasional stop/stop traffic management is occurring, but no delays have been noted as a result of these Downer works.
22 May 2024
Work on the main slip site near 900 Ahuroa Road has been completed, and the road is now open to residents on a stop/go basis while further slips are being worked on.
Construction works near 859 Ahuroa Road (on the northern side) began in early May, and one lane is closed. All timber piles have been installed and backfilling is under way.
Work beginning near J Tolhopf Road from 27 May is expected to take around 3 months.
Of 8 slips identified along Ahuroa Road, 3 are largely complete, with 5 remaining.
Another 2 slip sites are being repaired alongside road maintenance work further down the road towards Puhoi.
24 April 2024
Downer is planning to begin construction work opposite 859 Ahuroa Road (on the northern side) from Monday 29 April. Access will be maintained with a stop/go in place. This work is expected to take around 4 weeks.
Work continues near 900 Ahuroa Road with a full road closure. Work in this area is expected to take until 7 May.
The design and methodology for repairs to Ahuroa Road at RP 7.784, approximately 50 metres east of J Tolhopf Road, is progressing. Access will be maintained, but at times there may be a delay of 10 minutes when travelling through this section of road. During peak times, Downer will ensure access is uninterrupted. We will provide an update once a construction start date is confirmed.
22 April 2024
All piling has now been completed with a total of 149 piles installed. Our priority now shifts to drainage works and the capping beam. The focus has now shifted to the concrete work on the capping beam of the retaining wall. The heavy machinery within the road corridor restricts both vehicle and pedestrian traffic in the area.
8 April 2024
The construction team is installing the last of the 300m of piling and continuing to install the capping beam, poured to support the retaining wall and road.
18 March 2024
All 900mm 17m piles are in and Downer is now installing 900mm 12m piles using steel casing.
February 2024
Downer is making good progress, with 73 of 150 piles (some up to 17 metres deep) and 80 soil nails in place.
January 2024
Downer has now reestablished all construction equipment on site in preparation for the months ahead. The team is drilling and filling piles on the upper section of the site and the road will continue to remain closed for the duration of these works.
December 2023
Downer, on behalf of Auckland Transport (AT), continues to make progress on the remediation of the roadway on Ahuroa Hill. Since construction activities
began, a total of 16 piles have been drilled across the two sections. This is a considerable effort given the ground conditions which includes hard rock at a much lower depth than expected.
The construction team will be taking a break over the holiday period, from Thursday 22nd December 2023 returning on Monday 8th January 2024. During
this period the road will remain closed with all current temporary traffic management remaining in place.
26 October 2023
Ahuroa Road is proving difficult to repair. The original design was completed and works began in July 2023 on the permanent reinstatement. Unfortunately, the underlying rock layer is substantially deeper than thought, which has required a review of design options and a temporary hold on works.
AT is assessing six new design options and will select the most appropriate. Once we have the preferred option, Downer and AT will be able to provide programme information to the community around timing and options.
AT remains committed to the successful completion of these works and expects that we will be able restart construction within four weeks and have the road open by April 2024.
10 October 2023
On Ahuroa Road, several major slips have completely closed the road through to Puhoi. There has been considerable progress on the slip at Ahuroa Hill RP8200-8600. Soil nails acting like anchors are in place, which means the slope is now stabilised against further erosion. Shotcrete (sprayed-on concrete) was completed in September, as shown in the image on the right. This specialised process involves the high-pressure spraying of concrete onto the retaining wall's surface, reinforcing its structural integrity. Some remaining components for this slip are currently in design.
21 September 2023
Completion of works is expected by February 2024.
7 September 2023
Ahuroa Road is being worked on in sections. Some sections have already been completed, some are in construction. One section near J Tolhopf Road, where there was a major slip, is in the design phase. Designs are being prepared to repair this section in conjunction with the other repairs.
There are several retaining walls to be completed and will be worked on in sections. Each section will be completed separately. Road sealing will be completed afterwards.
30 May 2023
- Final design has been approved. Works to start shortly.
- Road status - open from both ends with one section of road closed at J Tolhopf Road.
3 May 2023
- 8 underslips have been identified.
- Geotechnical investigation has been completed, and an inclinometer has been put in place.
- Preliminarily assessment and design for the road rebuild were completed and presented on 20 April 2023. We are now moving forward to the final design phase using the existing road alignment.
- Road status – open from both ends with one section of the road closed at J Tolhopf Road.
Dairy Flat Highway, Dairy Flat
Road status: open
8 November 2024
Construction work is now planned for early 2025.
25 September 2024
The final design process is underway for repairs needed on Dairy Flat Highway. We expect to begin construction work later this year.
Leigh Road, Leigh
Road status: open, single lane with stop/go traffic management
4 December 2024
All 51 piles were installed by the end of November and backfilling is being done. Drainage will be done during December. The road is now a single lane. This site is expected to be largely complete by the holiday break, with the road reopened to two lanes. More work may need to be done in the New Year.
8 November 2024
Work is progressing well. The team have installed the steel beams. They are now installing lagging and backfilling as they go.
15 October 2024
We started work on Leigh Road on 7 October 2024. The team created a bench below the road from which to work on the new retaining wall. Traffic is running on a single lane.
25 September 2024
AT and Downer are expecting to start work on Leigh Road, near Schollum Road, from 7 October 2024. The work will involve the construction of a retaining wall and shoulder repair work. A lane closure will be in place with stop/go operating.
We expect to complete work before Christmas.
Vector will also be operating either side of these works to move powerlines and poles. They will notify residents separately.
26 July 2024
Currently in design. Power cables near the slip site will impact design and construction methodology. We are working with Vector to address this.
Matakana Valley Road, Matakana
Road status: open, single lane with stop/go traffic management
There are 10 slips along Matakana Valley Road. Repairs at the first site started on 29 February 2024. To date, 9 of the 10 sites are complete. We expect to begin work on the 10th site, near the waterfall, in early 2025.
21 August 2024
Site 9 (of 10 sites) has now been largely completed. This month, pavement and asphalting, line marking and guard rail installation have been completed. Minor remedial work will be undertaken as the weather allows. Site 10 remains in design and work is planned to begin later in the year.
26 July 2024
This month, we installed 16 piles at site 9. All piling and retaining wall work is now complete, and pavement work will progress this coming month. Site 10 is still in design. Work should begin later in the year.
26 June 2024
The team here are making great progress and are well ahead of programme. Eight sites have now been completed, with another one under way and one in design.
22 April 2024
Three slip sites have been repaired and another 5 are under way.
At RP773 (below left) 17 steel UC beams have been installed, ready for the lagging to be installed. Further along the road 39 timber poles have been installed with another 8 to come (see below right).
At RP7037 timber poles and lagging is complete (below left), while at RP7730 all steel beams are in place and timber lagging and backfilling is under way (below right).
At RP7330 (below left) and RP7257 (below right) 17 beams have been installed, and curb and channel work are under way.
8 April 2024
Chip sealing has been completed on 3 sites (RP7330, RP7257 and RP5900) and 25 retailing poles are being installed and backfilled at RP7037. Ten steel beams have been installed at RP7730.
18 March 2024
The retaining wall at RO5900 is completed and kerb and channel will be installed next. Contractors are working on another three sites.
21 February 2024
Downer, on behalf of AT, will be undertaking permanent repair works on the 10 slip sites across Matakana Valley Road between numbers 732-952 from late February/early March. The construction work includes building retaining wall structures to reinforce and prevent further slips from occurring.
Works will begin near number 952 Matakana Valley Road, with the plan to progressively move through the area as each slip is remediated. Construction is expected to take 10 months, and we will provide regular updates on timelines.
- Hours of work 7am to 7pm, Monday to Friday
- Traffic management includes temporary traffic signals, stop/go and speed restrictions.
22 September 2023
Work commenced on Monday 18 September. After initial works, we found that a design change was required. Works are on hold while we refine the design. Traffic management will remain in place.
20 September 2023
Work commenced on Monday 18 September. Our initial works will involve excavation and site setup before preparing for construction of the timber pole retaining wall. This work is expected to take 6 weeks. Once this is completed, Downer will make their way to the next slip further up on Matakana Valley Road. Resilience work in this area is still in the design phase.
8 September 2023
Work is set to begin on Monday 11 September for a 6-week period. A lane closure will be required with a stop/go in place.
17 August 2023
- Final designs under way
20 July 2023
- Additional damage caused by storm of 9 May 2023
- More slips were identified during investigation.
3 May 2023
- 6 underslips and overslips have been identified
- Preliminary site investigations completed
- Road status - open.
26 April 2023
- 6 underslips and overslips have been identified
- Preliminary site investigations completed
- Road status - open
Mill Flat Road Bridge, Coatesville
2 December 2024
During November, work has continued in preparation for the upcoming construction work.
Vector requirements for the movement of lines and poles need to be resolved before further construction progress can be made. The team are working hard to achieve this.
Unfortunately, the Vector relocation works are having an impact on our ability to award the contract. As soon as this is resolved, the contract will be awarded and work will begin.
Construction is now expected to start in early 2025.
AT sent a memo to update the Coatesville Transport Forum on 28 November. You can download the memo (PDF, 105KB).
8 November 2024
During October, ecologists monitored the site we will work in.
They were looking for:
- bats
- native skinks and lizards
- native bird nests.
Before removal of any trees, they were checked for nests. No bats, skinks, lizards or native bird nests were found. Monitoring for skinks and lizards will be ongoing throughout construction.
We are still working with Vector to determine a start date for their work. We are also yet to confirm a preferred contractor for the work.
26 September 2024
The Auckland Transport (AT) design team has completed their part. Our construction team will now take over. We expect to appoint a contractor in October.
Sub-contractors and team members will be doing surveys and preparation works until mid to late October. Pending the survey's findings, Treescape will be on site to do vegetation work.
Before construction starts, Vector needs to move the power lines and poles out of the work area near the bridge. Chorus will be on site with Vector to reconnect power to the new source. That may affect telecommunications and internet access as the changeover happens. Vector and Chorus will liaise with residents about this work.
21 August 2024
An update has been shared with Mill Flat Road residents and the surrounding community this week, following the completion of the design phase of work.
The letter provides detail on the progress to date, outlines the proposed design and highlights some of the key anticipated construction impacts. Download a copy of the Mill Flat Road letter (PDF, 740KB).
29 July 2024
The design stage is now complete. A resource consent application was lodged with Auckland Council in May, and a tender for construction is out. An update was submitted to the Local Board, and an update for the community will go out shortly.
May 2024
A community drop-in session was held on 1 May 2024 to discuss the design to date. (See the April update for details on the design.) Download a summary of this discussion.
April 2024
Mill Flat Road bridge replacement project
On 27 January 2023, the Mill Flat Road bridge was washed away during the Auckland Anniversary Weekend flooding event. As an emergency response, AT commissioned a Bailey Bridge to be constructed at the same location a week later.
Since then, AT has been investigating options for a permanent Mill Flat Road Bridge replacement, securing the necessary funding and undertaking a design process which includes planned intersection safety improvements on the Coatesville-Riverhead Highway.
What is planned
The Mill Flat Road Bridge current design includes:
- a 2-lane replacement bridge with 3-metre-wide general traffic lanes
- a single 1.5-metre-wide footpath on the southern (downstream) side of the bridge
- a slightly widened approach to the bridge on Mill Flat Road, providing greater sightlines
- no vehicle class or weight restriction
- the ability to be submerged and withstand a one-in-100-year flood event without being washed away.
The new bridge will be located slightly upstream of the current bridge to enable continued community access throughout its construction. It will be constructed in two halves, with traffic running on the temporary Bailey Bridge during the first half of the build. Traffic will then run on the first half bridge while the temporary Bailey Bridge is removed and the second half of the new bridge is constructed.
Concept bridge design and typical cross-section
Intersection Improvements - Mill Flat Road / Coatesville-Riverhead Highway
- The current design includes:
- A right-turn bay on Coatesville-Riverhead Highway leading toward Mill Flat Road.
- Slight widening of the road in this area, including retaining walls on the Rangitopuni Stream side, to accommodate the right-turn bay.
- Improved signage and intersection warnings either side of the intersection.
Next steps
- Finalise the detailed design - July 2024
- Award contract for physical works to the successful tenderer by October 2024
- Construction start - late 2024 for 12 to 16 months.
March 2024
A memorandum was provided to the Local Board in March 2024.
January 2024
Geotechnical investigations will be done at the bridge location from 30 January for approximately one week. Traffic management will be in place and delays are expected at times.
13 November 2023
AT presented a progress update to the Coatesville Transport Forum.
17 August 2023
Investigation phase under way to inform the design of the new bridge.
3 May 2023
- Temporary one-way bridge installed
- Project plan in development.
Pinchgut Road, Kaukapakapa
Road status: open under stop/go lane closure
4 December 2024
Slip repair work near 111 Pinchgut Road began on 29 October 2024. We expected work to be finished within one month. But when excavating the slip site, the team discovered rubbish buried within the road base. The work area has been extended to fix the slope, and the rubbish is now removed. This site is expected to be largely complete by the holiday break, with the road reopened to two lanes. More work may need to be done in the New Year.
8 November 2024
Slip repair work near 111 Pinchgut Road began on 29 October and is expected to be completed within one month.
15 October 2024
We have repaired the first of 4 slips on Pinchgut Road. New edge markers are in place to highlight the edge of the road.
Work on the second slip near 111 Pinchgut Road will start on 21 October. The first step will be to build a retaining wall and repair the shoulder. We expect it to take one month to complete.
25 September 2024
We started slip repair work near 171 Pinchgut Road on Monday 23 September. We expect it to take approximately one month to complete. This work will involve the construction of a retaining wall and shoulder repair.
26 June 2024
Four slips remain on Pinchgut Road, with repairs starting soon. This work will follow the work currently being done on West Road.
January 2024
- Minor slip repairs at RP1015 and RP659 complete
- Preliminary site investigations complete, final designs in progress.
3 May 2023
- Two underslips have been identified.
- Preliminary site investigations are complete.
Pine Valley Road, Dairy Flat
Road status: open
18 December 2024
Pine Valley Road reopened today. Thanks for your patience over the last 4 months while we repaired damage from the 2023 storm events. The repairs involved:
- a massive excavation down to install a large 2.5m wide culvert
- 500+ block stone wall to support the damaged road
- stormwater management works.
You can read more about these repair works here in our December Highlights Report.
We're pleased to have this section of road repaired for the community.
4 December 2024
Backfilling is almost up to the road level again and drainage has been installed. The road is now closed with detours in place. This site is expected to be largely complete by the holiday break, with the road reopened to two lanes. More work may need to be done in the New Year.
8 November 2024
The 3-month slip repair work on Pine Valley Road started on 2 September and is progressing very well. We have installed the large box culvert, and the team have commenced backfilling the road area. The road remains closed with detours in place.
15 October 2024
The team dug down to the existing culvert and opened it up at the beginning of October. New prefabricated box blocks form the new culvert. Backfilling is now underway to bring the ground level back up.
17 September 2024
For the latest news from the Downer construction team, read September's Pine Valley Community update (PDF, 655KB).
Two excavators installing the new culvert, rock riprap and concrete blocks on Pine Valley Road.
4 September 2024
Slip repair work started on Monday 2 September 2024. Traffic detour signage is in place, and the team is monitoring traffic as travellers adjust to the road closure.
21 August 2024
Slip repair work is planned to start on Pine Valley Road from Monday 2 September 2024 and will take approximately 3 months to complete.
Pine Valley Road will be closed (residents access only) at the work site near property 257.
A detour will be in place via Kahikatia Flat Road and Dairy Flat Road for 3 months.
The work will involve the construction of a block retaining wall on the southern side, repairs to the roadway and stormwater improvements.
Red Hill Road, Te Arai
Road status: closed, resident access only
15 October 2024
Further design work is underway. We expect repairs to get underway in late 2024 or early 2025.
17 August 2023
- Preliminary site investigations completed
- Final designs completed 8 June 2023
30 May 2023
- Road closed due to most recent storm on 9 May 2023
- Road status - closed, open to residents only
3 May 2023
- Preliminary site investigation completed
- Preliminary design near completion
- Road status – open but down to one lane
26 April 2023
- Preliminary site investigation completed
- Preliminary design near completion
- Road status – open but down to one lane
Ridge Road, Riverhead
Road status: open
8 November 2024
Slip repair works are now complete on Ridge Road and the construction team have disestablished from the area. AT and contractor Downer would like to thank the community in this area for their patience while these extensive repairs were undertaken.
15 October 2024
We expect to finish line marking and installing the final guardrails by the end of October 2024.
25 September 2024
The team are working on the final stage of works. This includes road preparation, chip sealing, line marking and guardrail installation.
4 September 2024
Repairs to slip 1 are well under way, with the retaining wall mostly complete. This month, backfilling will be done and the kerb and channel reinstated.
Repairs to slip 2 started on 26 August 2024. The area has been battered back, with white cloth protecting the exposed material on the battered face. This slip will be repaired using blocks.
21 August 2024
Work on Ridge Road is progressing well. To date, 18 out of 31 piles have been installed and concreted on the first retaining wall.
26 July 2024
Work to construct 2 retaining walls and repair the road shoulder begins Monday 5 August 2024. The work should take approximately 3 months to complete.
Ridge Road will be closed between 690 and 744 Ridge Road. A detour on Wake Road and Coatesville Riverhead Highway will be in place for 3 months. See the following detour map and allow extra time when travelling through the area.
Smyth Road, Warkworth
Road status: closed, residents access only
4 December 2024
Work started on 11 November 2024, with a full road closure in place due to the narrow road. The team are constructing a new retaining wall and repairing the road. VMS boards and social media were used to notify motorists, along with letters for residents.
This site is expected to be largely complete by the holiday break, with the road reopened to two lanes. More work may need to be done in the New Year.
8 November 2024
From Monday 11 November, Downer, on behalf of Auckland Transport (AT) will be repairing slips on Smyth Road near number 157. This will involve the construction of a retaining structure and road repair. A road closure with resident-only access will be in place on Smyth Road between numbers 260 and 157.
We anticipate there will be an increase in noise as we work. We apologise in advance and will do our best to keep this to a minimum where possible.
Takatu Road, Tāwharanui Peninsula
Road status: open, single lane operating
Repairs at Takatu Road include 5 soil-nailed shotcrete walls and one mass-gravity rock buttress to address the 6 slips identified.
4 December 2024
Work on two sites on Takatu Road started on 4 November 2024. The new wall on site 7852 is complete, and the road area will be chip sealed and completed early December. On site 6109, the area was cleared to enable the works. Unforeseen ground conditions now mean that a redesign will be needed. The team are backfilling and making the site safe then will stop working until we have a new design. The road will be reopened to two lanes. We expect work to start again in the New Year.
8 November 2024
We started repairing the next slip on Takatu Road this week on 4 November. Downer, on behalf of AT, are undertaking the slip repair work near 617 Takatu Road. This will involve the construction of a retaining wall and shoulder repair.
A lane closure will be in place with stop/go operating.
23 October 2024
Downer will be repairing a slip near 617 Takatu Road from Tuesday 29 October 2024.
Work is expected to take approximately 6 weeks with a lane closure stop/go in place.
25 September 2024
We have identified two more slips. We have named them RP 7852 and RP 6109. Repairs are in the design stage. We expect to begin works later this year.
21 August 2024
Slip repair works are now complete on Takatu Road and the construction team have disestablished from the area. AT and contractor Downer would like to thank the community in this area for their patience while these extensive repairs were undertaken.
26 July 2024
Rock buttress works and guardrail installation are now complete.
Another slip was discovered on Takatu Road. Working in challenging wet conditions, the team installed 26 soil nails (marked with blue painted dots in the image) to stabilise the slip. In August, they will install mesh and spray shotcrete, as with other slips in the area.
26 June 2024
The team had to work with the tide to install the rock buttress during low tide. Work here is progressing well, and work on these initial slips should be completed soon.
22 April 2024
Working in challenging conditions using abseiling gear and special supports for access, the team have made great progress. Steel mesh has been placed over the slip area of four slips. Shotcrete work is now complete on 4 of the 5 slips that need it.
8 April 2024
Shotcreet has been completed on Slip 2, while soil-nail drilling and installation continues on slips 5 and 6.
18 March 2024
Repairs are being made to six sites and contractors are currently working on four, focusing no grouting and meshwork and soil nailing.
February 2024
December 2023
Construction activities are under way and focus on comprehensive remediation measures which include five soil nailed shotcrete walls and one mass gravity rock buttress to address the identified six slips.
All necessary equipment, including excavators and drilling gear, has been mobilised, vegetation removal is complete and nailing is under way.
20 September 2023
Design work for the slip on Takatu Road is nearing completion. Construction will follow.
17 August 2023
- Final designs expected at the end of August
- Road status – open, but some sections of the road are reduced to one lane
22 June 2023
Final designs under way on 25 June
3 May 2023
- 5 underslips identified
- On track to completion
- Road status – open, but some sections of the road are reduced to one lane.
26 April 2023
- 5 under slips identified
- On track to completion
- Road status – open, but some sections of the road are reduced to one lane.
West Road, Kaukapakapa
Road status: open
20 November 2024
Slip repair works are now complete on West Road. The construction team have stopped working in the area. AT and contractor Downer would like to thank the community in this area for their patience during these extensive repairs.
8 November 2024
Work on this site restarted on 26 September 2024. We have built the retaining wall, backfilled and completed chip sealing work. We are planning the guardrail installation.
15 October 2024
We restarted work on 1 October and expect to finish within the month. We have installed the steel beams and timber lagging. The team are working on backfilling the site. We will build drainage works over the coming weeks.
25 September 2024
The team is awaiting the delivery of UC Steel Beams. We expect the beams to arrive this week and construction to restart on Thursday 26 September. We expect work to take one month.
26 July 2024
Work on West Road started on 1 July 2024, and the first hole was drilled on 11 July. As shown in the following images, the area is very soft clay. The team initially drilled to a depth of 9m and then 11.5m, with no rock found. The team is currently reviewing the design and looking at options on how to proceed.
26 June 2024
Work on West Road will begin soon, with a new retaining structure required to support the road, road repairs and a new culvert planned. This work should take approximately 3 months to complete.
February 2024
Contractors are on site to excavate, trench, and install a culvert and cesspit.
January 2024
Final design expected February 2024.
3 May 2023
Preliminary site investigation complete.
Wishart Road, Helensville
Road status: open
18 December 2024
Our monitoring has found that the ground is still moving, even with the new drainage in place. This means further non-urgent repairs to the road are needed. We're currently confirming the repair plans in this location.
Vector need to straighten a nearby power pole. They'll also move another pole which will need to be relocated because of the road repair work. They'll start from 8 January 2025 and be in touch with neighbours to communicate any effects from the work.
We'll be back touch next year once we've confirmed plans and programme for the repairs next year.
15 October 2024
We have installed drainage. We will actively monitor the site for an initial period of 3 months. If movement is detected, we will need to do further repair work.
25 September 2024
We have established an access track to the site and have started installing drainage.
4 September 2024
Work will start from Wednesday 11 September, taking approximately 4 weeks. The work involves the installation of a drainage system to redirect water from the slip area and surrounds.
Existing traffic management, which includes a lane closure with stop/go signals and temporary speed restrictions, will remain in place. This setup ensures that crews can carry out their work safely.
7 August 2024
We have been monitoring the site for the past year. Design for a solid drainage system to redirect water from the slip area and surrounds is under way, and the work should be carried out later this year. Once the new drainage is in place, we will actively monitor this section of the road for one to 2 years, looking for any movement of concern. If there is movement, we will finalise designs for a full repair at this location.
January 2024
Temporary repair to open road over Christmas completed.
20 July 2023
Final design delayed due to further investigation (movement being measured).
22 June 2023
Under design phase. Final design due 4 July
3 May 2023
- Preliminary site investigation complete.
- Road status – open but reduced to one lane with traffic lights at major slip site.
26 April 2023
- Preliminary site investigation complete
- Road status – open but reduced to one lane, with traffic lights at major slip site.