North Urban Auckland flood recovery progress North Urban Auckland flood recovery progress
Extreme weather events in Tāmaki Makaurau / Auckland caused damage to roads in 2023.
Over the last 18 months, we’ve made significant progress on repairing storm-damaged roads in the North Urban Auckland area, as shown by the following statistics.
Reported sites and slip repairs as of 28 February 2025
- Total number of sites: 109 (37 major, 72 minor)
- Currently under construction: 8
- Completed sites: 99 (91%)
We have completed:
- 29 out of 37 major slips (78%)
- 70 out of 72 minor slips (97%).
There are 5 major slips currently under construction:
- East Coast Road, Torbay
- Elmore Road, Paremoremo
- Raymond Terrace, Birkenhead
- Twin Wharf Road, Herald Island
- Wade River Road, Whangaparaoa.
The reported number of sites requiring minor to major repairs will change slightly over time as the design and investigation of each slip site develops. We ask for your patience as we repair sites all over Auckland.
To report new issues, please contact us.
The following is a list of recently completed major sites in the North Urban area.
Work has also been completed on 67 minor sites, including hydroseeding with grasses to help stabilise the banks.
Our thanks go to everyone in each of these communities for your patience and understanding as we made necessary repairs and restored safe connections.
- Albany Heights Road, Albany Heights
- Beach Road, Torbay
- Brigham Creek, Whenuapai
- Dairy Flat Highway, Dairy Flat (2 sites)
- Duck Creek Road, Stillwater (2 sites)
- East Coast Road, Redvale (one of two sites)
- Elmore Road, Lucas Heights (2 sites)
- Gills Road, Albany
- Glenvar Road, Torbay
- Hibiscus Coast Highway, Hatfields Beach (1 of 3 sites)
- Hinemoa Terrace, Birkenhead
- Hobbs Road, Whangaparaoa
- Inkster Street, Birkenhead
- John Brian Drive, Redvale (2 sites)
- Kaipatiki Road, Glenfield
- Lonely Track Road, Albany Heights
- Masterton Road, Rothesay Bay
- Mollyhawk Place, Birkenhead
- Paremoremo Road, Paremoremo (4 large slip sites)
- Rahui Road, Greenhithe
- Ridge Road, Lucas Heights (2 sites and resilience work)
- Riverhaven Drive, Wade Heads
- Scott Road, Stillwater
- Sir Peter Blake Parade, Bayswater
- Spur Road, Stillwater
- Tauhinu Road and The Close, Greenhithe
- Tizard Road, Birkenhead
- Twin Wharf Road, Herald Island (2 sites)
- Wade River Road, Wade Heads
Road status: open
7 March 2025
Work started on 7 January and went ahead of schedule with works completed on 14 February 2025. We thank you for your patience while we did these storm repairs. The work included a 33-metre-long timber retaining wall.

13 February 2025
Works started on 7 January and are ahead of schedule. The 33-metre-long timber retaining wall is installed and the team have started on road reinstatement. The road is currently closed in this location but is expected to reopen on Friday 14 February. This is several weeks ahead of schedule because the team's been working so quickly,


5 December 2024
We plan to start slip repair work to Albany Heights Road on 7 January 2025.
Work will include:
- construction of a 33m-long timber retaining wall.
- road pavement repairs
- drainage improvements.
The road will be closed in the work area because of the narrow road. Resident-only access, including visitors and deliveries, will be needed between property numbers 45 and 58. This is to safely carry out the works. Detours will be in place either side of the work site.
Variable message sign (VMS) boards will be near the work site. Residents will be given an update letter in early January before the work starts.
Road status: Open, under restrictions
21 March 2025
Bush Road was damaged by an under slip during the Auckland Anniversary weekend weather event, January 2023. An extensive construction programme is being prepared to repair the slip. Slip repair work is tentatively scheduled to commence beginning of April and will take up to five months to complete.
Prior to slip repairs, we need to first undertake enabling works which includes tree pruning, survey and hydro-excavation to identify any underground services. This is scheduled to commence starting 24 March 2025 for approximately one week.
During the enabling works, Bush Road will remain open, with a reduction in lane width between Albany Expressway and Pinehurst School. The free left turn from Bush Road towards Albany Village will be closed during the work, with a signposted detour in place.
Road status: open
13 February 2025
The Duck Creek Road slip repair work is now complete and the road is fully open in this area. Thank you to neighbours and users of Duck Creek Road for your patience over the last 7-8 months while we constructed three large retaining walls and repaired the road surface.
Fulton Hogan’s maintenance team will be back in the next few weeks to complete regular asphalt maintenance either side of the slip area.
Read an article in OurAuckland (opens in a new window) or watch a video on Youtube (opens in a new window) about these repairs.


18 December 2024
From Friday 20 December the road will be opened to two lanes, with only shoulder closures in place.
Work will resume with road pavement from Tuesday 7 January 2025. Single lane traffic lights will operate again.
Lime stabilising work will start on 8 January on both sides of Duck Creek Road if weather allows. This means commuters will be driving on a milled surface and lime stabilised surface. Lime stabilising can be noisey and dusty. We'll have a watercart operating to reduce the amount of dust. We recommend you wash your vehicle after driving over the lime stabilised surface.
Following lime stabilisation, we'll be laying asphalt. This process is expected to take up to three weeks to complete. When road pavement is finished, we'll install guard rail, landscaping, placing topsoil and tidying up.
We're on track to finish on-schedule in mid to late February 2025.
5 December 2024
Repair work is on schedule. All piles were installed on the last two retaining walls by the end of November. We expect the lagging (timber behind the piles) to be in place early December. The steel barriers will then be removed.
The team will start kerbing and drainage work, alternating sides of the road as they go.
During the holiday break, the road will be opened to two lanes, with only shoulder closures in place. Work will start again on 6 January 2025, with single lane traffic lights operating again.

8 November 2024
The first retaining wall on the south side is now complete. Traffic has switched over to enable work on the southern side walls. We installed piles for the first of 2 retaining walls on this side of the road. The team are now working on the lagging.
16 October 2024
The retaining wall on the southern side of the road is now largely complete. This week the team will be creating a temporary road surface for traffic to run on the other side of the road. We plan to work overnight on Sunday to move the barriers and equipment.
On Monday 21 October, the one-lane drive through area will switch from the north to the south side. Traffic will move to the inland side of the road next to the new retaining wall.
Watch aerial footage from September of the Duck Creek Road site (opens in a new tab).
27 September 2024
We have made good progress on the first retaining wall on the south side. Following investigations on site, the south side retaining wall will be extended a further 40m to stabilise the bank in this area. The team will switch over to working on the north side towards the end of October.
4 September 2024
The first retaining wall on the south side is progressing well. A crane is on site to hold up a power pole while we construct the retaining wall immediately below.
21 August 2024
Over the 6 weeks from 1 July, we have:
- cut back the embankment adjacent to number 307 Duck Creek Road
- installed 60% of the timber piles and 60% of the timber lagging (planks laid behind the piles) that make up the longest of the 3 retaining walls (95m).
In the coming weeks we aim to:
- relocate the nearby power pole and lines which were compromised during the weather event
- construct the road pavement on the newly widened section (adjacent to number 307 Duck Creek Road)
- switch traffic from the north (valley) side of the road to the newly widened south (embankment) side of the road
- commence construction of the smaller of the 2 north (valley) side retaining walls.
1 August 2024
Work is progressing well and is currently on programme, with completion expected in February 2025.
4 July 2024
Duck Creek Road remains open but is reduced to one lane of traffic through the work site.
27 June 2024
On 30 June 2024, work started between 296 and 325 Duck Creek Road, an area that was damaged by an underslip (slump below the road) during the Auckland Anniversary weather event in January 2023. Work includes:
- cutting back the embankment adjacent to 307 Duck Creek Road and creating a temporary widened road
- on the north (valley) side, constructing 2 timber retaining walls measuring 16 metres and 86 metres long
- on the embankment (south) side, constructing a 95-metre-long retaining wall adjacent to 307 Duck Creek Road
- finishing works such as pavement repairs, additional drainage, new kerb and channel, landscaping and fencing.
Duck Creek Road remains open but will be reduced to one lane of traffic through the work site. We will use a mix of temporary traffic management, such as temporary traffic lights, and a lower speed limit.
Road status: open, single lane with traffic lights
21 March 2025
Work on the retaining wall is expected to be completed by the end of March and the team will then progress to pavement and drainage repairs. This site is expected to be completed during April.

7 March 2025
Work is progressing well and on programme.

13 February 2025
Auckland Transport and Fulton Hogan started work on 12 February 2025 near 1201 East Coast Road, Redvale between John Brian Drive and Okura River Road.
East Coast Road was damaged during the Auckland Anniversary weekend weather event in January 2023. Work includes:
- construction of a 45-metre long retaining wall
- road pavement repairs.
East Coast Road will remain open and will be reduced to one lane of traffic through the work site. We will use a mix of temporary traffic signs (like stop/go signs) and traffic lights, and a lower speed limit. We do this to keep traffic moving and keep people who use the roads and footpaths safe. Traffic controllers will help to manage vehicle access. Please follow all signs, light signals and traffic directions.
The road will be widened on the other side of the wall to allow the installation of a steel barrier to separate traffic past the road works.


Road status: open
21 March 2025
Slip repairs on Elmore Road are now complete and the road reopened. AT and Fulton Hogan would like to thank neighbours and motorists for their patience and support during this work.

7 March 2025
Fast progress led to completion of the retaining wall near property #20 on 25 February 2025 and the road reopening in this location. Traffic lights remain to complete the stormwater works near property #60, with this second work site expected to be completed mid-March.


13 February 2025
Auckland Transport and Fulton Hogan are preparing to start slip repairs and drainage improvements. Because of the narrow road area, Elmore Road will be closed in the work area.
Elmore Road was damaged during the Auckland Anniversary weekend weather event, January 2023. Work to repair the under-slip includes:
- construction of a 40m long Concrete block wall
- drainage improvements including storm water crossing.
The road will be fully closed, with no access through, near property number #20 Elmore Road. Detours will operate either side of the work site. Properties #1 and #20 will access via Paremoremo Road. All other properties will need to access via Ridge Road.
A second work site will be located near property #60 Elmore Road. Access past this site will be managed with traffic lights and traffic management personnel.
Please follow all the detour signs, traffic lights and signal to a traffic controller who will be stationed to assist your safe access during working hours.
This work is expected to take 3 weeks to complete, weather permitting.

Road status: open
13 February 2025
Work is now complete on Hibiscus Coast Highway near the intersection with Ocean View Road. Thank you Hatfield’s Beach and passing motorists for your patience!
There will be more work on two sites elsewhere on Hibiscus Coast Highway coming up over the next few months.

5 December 2024
Repair work is going well on this site. All 27 piles were installed by the end of November. The Capping beam will be constructed by mid-December. The steel barriers can be removed when this is done.
The road will be opened to two lanes during the holiday break. Only shoulder closures will be in place. Work will start again from 6 January 2025, with single lane traffic lights operating again.

8 November 2024
We started repair work on 14 October with some minor drainage repairs and a new kerb and channel on the eastern side of the road. The team then switched to the western side of the road, installing steel barriers. The road is operating as a single lane with traffic lights in this location. Over the next 2 months, the team will construct a 53m long reinforced concrete in-ground palisade wall with a capping beam. This will include footpath works.
11 October 2024
From Monday 14 October 2024, we will start repair work. We expect work to take 4 months to complete.
We will reduce Hibiscus Coast Highway to one lane with traffic light stop/go near the intersection with Ocean View Road.
First, we will upgrade drainage on the eastern side of the road. During that time, the single lane restriction will only be in place during work time.
From around 28 October (progress depending), we will install steel barriers. This is to enable works on the western side of the road.
We will then operate stop/go with traffic lights 24 hours a day, 7 days a week, for the remainder of the work.
Hibiscus Coast Highway was damaged by severe weather in early 2023.
We will also undertake some scheduled repairs on the other (eastern) side of the road at the same time.
Work includes:
- additional drainage, including a new kerb and channel on the eastern side of the road
- trimming trees and relocating services as part of enabling works
- constructing a 53m long reinforced concrete in-ground palisade wall with capping beam
- upgrading the footpath on the western side
- finishing works such as road pavement repairs and other improvements.
4 July 2024
Repairs to the slip near the Ocean View Road intersection will begin soon. A new concrete palisade wall will be built, with footpath improvements also planned. We are waiting for Vector and Chorus to give us plans showing poles and wires in the area.
Road status: closed - residents access only
7 March 2025
Retaining walls were completed on Tuesday 4 March and the team have started work to replace the footpath and kerb and channel drainage. Road reinstatement will follow. This next phase of work is expected to take approximately 3 weeks, weather permitting.

13 February 2025
Slip repair work on Raymond Terrace began on Tuesday 11 February. The original start date was delayed for demolition of a private property.
Raymond Terrace was damaged during the Auckland Anniversary weekend weather event, January 2023. Work includes the construction of a 22 pole inground timber wall along the southern road boundary. Also included are drainage facilities, and road pavement and footpath repairs. The area at the entrance to Kauri Glen Reserve will also be reinstated.
During construction, Raymond Terrace pedestrian access in/out of Kauri Glen Reserve is to temporarily close. All other pedestrian access points in and out of Kauri Glen Reserve remain open.

5 December 2024
We plan to begin work to repair the slip in Raymond Terrace from 20 January 2025. The road will be closed in the work area because of the narrow road. Resident-only access, including visitors and deliveries, will be needed. This is needed to safely carry out the works. Detours will operate either side of the work site.
Residents will be given an update letter early January before work starts.
Road status: open
8 November 2024
Stages 1 and 2 are now complete on Twin Wharf Road. We built new pavement and did replacement planting in conjunction with a local environmental group during October. Work on the new staircase will begin over the next few months.
16 October 2024
Pavement work is underway. We are constructing the asphalt surface this week. Planting also gets underway this week in collaboration with the local community.
Watch aerial footage taken during September of the Twin Wharf Road work site (opens in a new tab).
27 September 2024
Stages 1 and 2 are finishing soon along Twin Wharf Road on Herald Island. The final road paving reinstatement is scheduled for mid to late October. Following this, work on the new staircase will begin next to the toilets at the wharf. Topsoil will be placed early in October on the upper bank. We will then start planting with guidance from the local environmental group.
4 September 2024
Stage 1 of the slip remediation work started in May 2024 and is nearly finished.
We have:
- built a retaining wall on the embankment side
- stabilised the bank on the seaward side
- reinstated the footpath and carriageway.
Stage 2 of the slip remediation work started with the construction of a retaining wall adjacent to the temporary stairs. Before work continues, we will remove the temporary stairs.
Pedestrians will instead have to use the newly completed footpath along Twin Wharf Road after 2 September.
For Stage 3 we will construct a permanent stairway near the temporary stairs.
21 August 2024
Work continues on the timber retaining wall on the bank side of the road.
1 August 2024
Work on Twin Wharf Road is progressing well. The retaining wall on the seaward side of the road is now complete, and the team have begun work on pole installation on the bank side.
27 June 2024
In April 2024, enabling works started on Twin Wharf Road, Herald Island, where the road and footpath have slumped towards the water. Work here is expected to take several months to complete, as works will be conducted in stages.
Temporary stairs are in place to provide access while soil nails are being installed to stabilise the bank.
January 2024
Final design is being reviewed.
20 July 2023
Preliminary design is being reviewed.
3 May 2023
- We are doing geotechnical testing and drafting initial designs to build a new retaining wall to replace the wall that collapsed.
- We plan to begin construction in early 2024 and expect to be finished by mid-2024, weather permitting.
Road status: open
21 March 2025
Wade River Road opened on Friday 14 March 2025 after being closed since 7 January 2025. Thanks to the community for your patience and support during this work. Repairs to fix a major under-slip on a narrow part of the road involved the relocation of a power ple, drainage improvements, and the construction of a 105 metre-long timber retaining wall. The road had been reduced to one lance since the early 2023 storm events.

7 March 2025
The retaining wall area has been extended to 103m due to ground conditions. However, work is ahead of schedule and is expected to be completed around mid-March.

13 February 2025
Work started on 7 January and consists of:
- a 75-metre-long timber retaining wall
- drainage improvements
- pavement repair.
Because of the narrow road area, Wade River Road is closed in this area. Detours are in place, with expected completion in April 2025.


5 December 2024
Vector are preparing to work on poles and power lines ahead of the road slip repair work. The work is planned to begin on 7 January 2025.
Work to repair the under-slip will include:
- temporary relocation of overhead power cables
- construction of a 75 m long timber retaining wall
- finishing works such as road pavement repairs and drainage improvements.
Because of the narrow road area, Wade River Road will be closed in the work area. A road closure with resident only access (including visitors and deliveries) will be needed between numbers 126 and 115 Wade River Road. This is to safely carry out the works. Detours will operate either side of the work site.
Variable message sign (VMS) boards will be near the work site and residents will be sent an update letter early January before work starts.

1 August 2024
We are currently finalising the design and price for the repairs. We are working with Vector, as they will need to move power lines and power poles before our work can begin.
January 2024
Design is being finalised.
20 July 2023
Design in progress.
25 May 2023
We are undertaking geotechnical testing and initial designs to build a new retaining wall to replace the damaged one. We plan to begin construction in early 2024 and, weather permitting, expect to be finished by mid-2024.
The following slip repairs are also on our list and currently in the design phase. We will share more information about each location under its own section when we have it. For now, other roads where slip repair work is planned include:
- Huka Road, Birkenhead
- Lannigan Street, Birkdale
Please note: All works are subject to change due to factors such as weather, resourcing and delivery of supplies. Information contained here is a guide for general purposes only.