Aotea flood recovery progress Aotea flood recovery progress

This page has a list of affected roads in Aotea Great Barrier Island.

ROAD NAME WORK STAGE AND DURATION EXPECTED START OF PHYSICAL REPAIR ROAD STATUS  WEIGHT RESTRICTIONS APPLICABLE (3.5 TONNES) NOTES
Aotea Road Waiting on designs April/May 2024 Open   Completed installation of subsoil drains through the slump by the Pinnacles seat. Waiting on design to be finalised to start repairs in April/May 2024
Cape Barrier Road Identify and assess 100% completed Open   Job completed. Traffic is open to the public.
228 Shoal Bay Road Under Geotechnical assessment March 2024 Open - single lane   Road down to one lane. Expect repairs in March 2024.
Whangaparapara Waiting on designs 100% completed Open   Job completed. Traffic is open to the public.