West Auckland flood recovery progress West Auckland flood recovery progress

Extreme weather events in 2023 caused damage to roads throughout Tāmaki Makaurau / Auckland. On this page, you can stay up to date on the progress of repair works in your area. 

West Auckland road updates

Not all sites are listed on this page, as some have already been repaired. Design work on others is still ongoing, and other roads will be added as we work through the programme.

Works may be completed on some roads without being added to this page, depending on the scale of the work and the number of residents affected.

We ask for patience as we work to repair more than 2,000 sites across Auckland.

To report new issues, contact us. Forest Hill Road, Oratia

Forest Hill Road, Oratia

16 February 2026

Works will begin in late March 2026 to repair a slip on Forest Hill Road, Oratia.

There will be a full road closure between 298 and 310 Forest Hill Road. Residents who live within the closed area will be advised by our contractor about access to their property.

Work is expected to take until the end of June 2026.

School buses will be affected by this closure. Ministry of Education bus changes will be notified through the school office.

The AT 056 Bus for Avondale College

Bus stops closed Please use

5324 (126 Forest Hill Road)

5322 (Holdens Road)         

5320 (170 Forest Hill Road)

5318 (198 Forest Hill Road)

5316 (Kellys Road)

5890 (Opp 235 Forest Hill Road)

5320 (170 Forest Hill Road)

5313 (276 Forest Hill Road
5326 (Pine Avenue)

5314 (324 Forest Hill Road)

5940 (West Coast Road)

5465 (Tui Crescent)

5463 (Raroa Terrace)

5461 (Rimu Road)

5459 (Bendalls Lane)

5457 (Kauri Loop Road)

5455 (757 West Coast Road)

5453 (Kauri Loop Road)

5989 (715 West Coast Road)

5451 (Kellys Road)

5449 (Parker Road)

5447 (Carter Road)

5443 (Shaw Road)
5441 (515 West Coast Road)

Huia Road – various sites

11 May 2026

There are 2 slip sites along Huia Road currently in construction.

The first site is 634 Huia Road, Parau. Works started on 16 February 2026 and we expect to finish by June 2026.

The second site is Huia Road, 100m past Kaitarakihi Road. Works started mid-February 2026. This repair is large. We expect to complete it in the last quarter of 2026.

We are working to maintain one-lane access at these sites for traffic.

Ngaio Road, Waima

19 December 2025

This repair is nearly complete and the road is open. In 2026 the team will be back to complete some finishing work on the bank below the retaining wall. This will be completed without full road closure.

Tanekaha Road, Titirangi

11 May 2026

Works started on the slip repair outside 28 Tanekaha Road in March 2026.

We need to build 3 retaining walls to repair this slip.

The first stage of works includes the construction of the first wall. It also includes some temporary road repairs so the machinery can safely work in this location.

We will build the first retaining wall with 39 steel piles and concrete 16m deep along the road edge. The wall will be capped with a concrete beam that will double as a footpath at this location.

Due to the narrow width of the road, and the size of the machinery, this work can only be completed under full road closure during the construction of wall one.

Timetable for road closure

Times Access details
Monday to Friday, 8:30am Road closed for works. On school days, the school bus will be able to go through in the morning before the road is closed.
12pm to 12:30pm Road open for resident access.
12:30pm to 5:30pm Road closed for works. On school days, the school bus will stop on Otitori Bay Road. Students will be escorted through the closed section on foot.
Weekends and overnight, 5:30pm to 8:30am The road will be open. There will be one-lane access under traffic lights.
Emergency access In the event of emergency, we will be able to open the road at short notice to allow emergency vehicles to pass through the site.

Once we’ve done all work that requires a road closure, we will revert to the temporary traffic lights and have one lane open most of the time. We will update the community when changes occur.

We expect the works to take 4 to 6 months to complete.

If you live in this area and would like to be added to an email list for updates, email us at atengagement@at.govt.nz.


Victory Road, Laingholm

3 March 2026

There are 2 slips that will be repaired on Victory Road, Laingholm. We are planning to start work on the repairs on 16 March 2026.

The work will take place between 143 and 159 Victory Road and will take approximately 4 months to complete.

There will be a full road closure in place from Warner Park Avenue to Kauri Point Road.

The closure will be in place from Mondays at 6:30am through to Friday 6:30pm. Over the weekend, and on any public holidays, there will be one lane access under a traffic light system.

Due to the closure the 171 and the school buses will not be able to complete a loop in Laingholm. Please see the bus route maps for the period of the closure.

171 route

Map of 171 route

School buses 074 and 076 morning detours

School buses 074 and 076 morning detours

School buses 074 and 076 afternoon detour

School buses 074 and 076 afternoon detour

School bus 075 afternoon detour

School bus 075 afternoon detour

Wood Bay Road, Titirangi

We are in the final stages of planning for the slip repairs outside 35 Wood Bay Road, Titirangi. 

We are working with service providers to relocate services before we can start works, especially the overhead powerlines. Once we have a start date for the slip repair we will update the community.