North Urban community - road repair updates North Urban community - road repair updates

Damage has been caused to roads by the recent extreme weather events in Tāmaki Makaurau / Auckland.

You can keep updated on the progress of the repair work in your area on this page.

We ask for patience while trying to repair sites all over Auckland.

To report new issues on the AT contact page https://at.govt.nz/about-us/contact-us.

Glenvar Road, Torbay

19 September 2023

Our new target opening date for Glenvar Road is 27 October 2023.

Fulton Hogan have faced a few challenges on this site but are ahead of schedule. We know this route is important to the community so we have been using as many resources as we can access to move the work forward.

When we open the road we will be removing all the traffic management from the detour route. 

Glenvar Road, Upgrading the drainage
This picture shows where we are building a new footpath, which will include safety rails.
The new footpath will connect up to East Coast Road

6 September 2023

Works are progressing on track for the programmed opening of this road in November. The works underway include:

  • Kerbs and drainage on each side of the road
  • Strengthening the base of the road.
  • Renewal of the asphalt road surface 
  • Pedestrian access and safety rails 

Glenvar Road Slip Repair

Glenvar Road

20 July 2023

Enabling soil anchoring works in progress

Glenvar

3 May 2023

  • We are currently finalising our design and plan to begin work onsite in mid-May.
  • Weather permitting, we expect Glenvar Road to be open by the end of November, in time for summer.
  • Please do not cross the barriers – it is not safe to walk or cycle on the closed section of the road.
  • You’ll find more information and updates at Glenvar Road Flood Repairs (at.govt.nz).
  • Road status: Closed in both directions between East Coast Road and Fitzwilliam Drive.

26 April 2023

  • Finalizing the opening of the road, on track for repair.
  • Road status – closed, open to residents only.

 

East Coast Road / Haigh Access

As part of the road maintenance, a significant repair needs to be undertaken on East Coast road, close to Haigh Access.

This work will include a retaining wall, kerb and channel and pavement rehabilitation. To allow this works to be undertaken safely, a steel barrier will be installed, prior to works starting.

Works begin: Monday 18 September

Time to complete: 13 Weeks

Time: 7am to 7pm, Monday to Saturday

  • We will install signage, barriers and road cones the day before the retaining wall works begin.
  • Please park away from the work area during the working hours above. We may need to tow vehicles parked in the work area to a safe position a short distance from the work site. We will make every effort to locate the owner before towing.
  • There may be changes to road layout and access. To keep you and our team safe, please follow the instructions of the onsite traffic control team and plan for some delays.
  • We will park our equipment on within the worksite, behind the barriers, during the works. Please contact us if that causes you any problems.
  • This work involves heavy machinery which can create noise, vibration, and dust. All efforts will be made to minimise these disturbances as much as practically possible.
  • To ensure the safety of you and your whanau, please keep young children and animals well supervised and away from the work area.

Hinemoa Terrace, Birkenhead

20 July 2023

Awaiting Vector and Chorus service relocations and new streetlight layout

3 May 2023

  • Geotechnical testing is complete, and our contractor Fulton Hogan is now working on the final designs and specifications.
  • We’re currently working with Vector to find the best solution for the location of power lines.
  • Road status – closed in both directions.

26 April 2023

  • Finalising design with community board support.
  • Road status – closed, open to residents only.

Paremoremo Road, Paremoremo

6 September 2023

Construction at site 1 is on schedule. All 25 soil anchors are now complete. Timber poles have been installed and secured.  Backfilling will begin soon.

The retaining wall will be completed in the next couple of weeks.

Sites 2 and 4 

The works for these two sites are still in the resourcing stage, we will update when these are finalised. 

Construction at site 3 continues, concrete columns have been completed. 

Below is a photo of the site, works to rebuild the road are underway, and running on schedule.

Paremoremo site 3

P

20 July 2023

Designs are being finalised for 3 further slips. Construction at slip 3 in progress

25 May 2023

  • Weather, permitting we’ll be starting the first of four new retaining walls on 8 May
  • We expect all repairs to be complete by mid-2024
  • Road status: One lane open

Ridge Road, Lucas Heights

6 September 2023

Plans at the slip sites on Ridge Road are still being finalised, working on resolutions to the gas line and power sources. 

 

20 July 2023

Designs have been completed for 2 adjacent sites on Ridge Road. Construction planning is in progress

25 May 2023

  • We are currently undertaking geotechnical testing and initial designs to build several retaining walls to support the road where slips have occurred
  • We will begin works in early 2024 and expect to be finished by Mid 2024
  • Road status: One lane open

Twin Wharf Road, Herald Island

20 July 2023

Preliminary design is being reviewed

3 May 2023

  • We are currently undertaking geotechnical testing and initial designs to build a new retaining wall to replace the previous wall that has collapsed.
  • We plan to begin construction in early 2024 and, weather permitting expect to be finished by mid 2024.
  • Road status – one lane open.

Wade River Road, Stanmore Bay

20 July 2023

Design in progress

25 May 2023

  • We are currently undertaking geotechnical testing and initial designs to build a new retaining wall to replace the damaged one
  • We plan to begin construction in early 2024 and, weather permitting, expect to be finished by mid 2024
  • Road status: One lane open