Huapai Triangle Special Housing Area Huapai Triangle Special Housing Area
We have finished building roading infrastructure at Kumeu and Huapai. The second of 2 related projects, this serves the new Huapai Triangle Special Housing Area (SHA) in the northwest sector of Auckland.
On this page
Project status: Completed
Project zone: West
Project overview
The SHA comprises 1,200 dwellings, including a retirement village. The triangle of land (Huapai Triangle) is bound by the Auckland-Northland Railway to the north (parallel to SH16), Station Road to the northwest and Nobilo Road to the northeast.
We upgraded:
- the connection between SH16 and Station Road at Huapai by shifting the intersection westwards and signalisation
- the existing Station Road intersection the intersection of SH16 and Access Road.
We also added an additional 100m exit lane from Access Road.
Benefits
We have:
- increased capacity for traffic generated by the Huapai Triangle Special Housing Area (SHA) in north-west Auckland
- made the area more accessible
- improved safety at controlled intersections
- improved interchange of traffic between side roads and SH16
- improved traffic flow on SH16
- improved walking and cycling routes
- addressed issues of intersections and corridor capacity, safety, and connectivity.
Project updates
November 2024
We completed all major work on Station Road and the intersection of SH16. Some minor patch work will continue through the end of November. We do not expect this to cause significant disruption. Thank you to the communities of Huapai and Kumeu for your engagement and patience as we worked to deliver these improvements.
For more information, read our works notification (PDF, 1.4MB).
October 2024
Construction crews finished installing line markings on Station Road from 29 to 31 October 2024.
For more information about this work, read our works notification.
The new traffic lights at the intersection of SH16 Main Road and Station Road began operating.
September 2024
Construction crews completed the super weekend works resurfacing SH16 Main Road between Station Road and Tapu Road. They also completed nightworks on SH16 between Trigg Road and Tapu Road.
August 2024
We postponed the planned rail bridge closure of SH16 Main Rd between Station Road and Tapu Road in Huapai scheduled for Sunday 11 August. We took community concerns into account and explored less disruptive alternatives. These included pavement design changes and night repairs.
July 2024
Our crews worked overnight to resurface a section of State Highway 16 between Trigg Road and the railway bridge just before Tapu Road. These works started on the evening of Sunday 28 July 2024. It took place for 5 nights. For more information, see our works notification (PDF, 410KB).
June 2024
Due to construction delays brought on by the recent severe weather, we extended the full road closure that began on 16 May. It was extended until the end of July. For more information, see our updated works notification (PDF, 326KB).
May 2024
A 5-week road closure began on 16 May 2024 to rebuild the 200m stretch of Station Road beginning at SH16 and ending just before Schoolside Road.
For detour maps and more information about the closure, view our works notification (PDF, 323KB).
April 2024
Vector converted 3 overhead power cables into underground lines by the Station Road / SH16 intersection. This work by Vector was separate from AT’s Station Road works currently under way.
February 2024
Nighttime road works took place between 3 March to 7 March 2024 to install gas lines across Station Road.
Late 2023
The work to widen SH16 and upgrade the Station Road intersection began. SH16 remained open during construction and traffic management was in place.
Works on Access Road were completed.
Project details
The principal connection to SH16 for SHA traffic is projected to be via Station Road north to SH16. An alternative route is to the south via Access Road. This intersects SH16 at Kumeu.
The primary purpose of the upgrades for which AT is responsible was to upgrade the capacity of the 2 intersections and their ability to cater for:
- increased volumes of traffic on SH16
- improved safety and better management of traffic between SH16 and Station and Access Roads.
Cabra Developments Ltd have upgraded Station Road between Nobilo Road and the pedestrian crossing near Huapai District School.
Huapai - SH16/Station Road intersection (completed in 2024)
AT and Fulton Hogan completed upgrades for this part of the project in November 2024. The upgrades involved the shifting westwards and signalisation of the existing Station Road intersection. They also included new walking and cycling facilities along Station Road.
To view the Station Road Huapai improvements, download the map (PDF, 776KB)
The full scope of improvements for the intersection of SH16 and Station Road includes:
- upgrading the intersection at SH16 and Station Road
- realigning the Station Road intersection with SH16 approximately 40 metres west of its current position
- signalising the intersection at SH16 and Station Road
- building a short right-hand turn lane on the SH16 eastbound approach into Station Road
- building a short left-hand turn lane on the SH16 westbound approach into Station Road
- building cycling and pedestrian connections from Station Road to Main Road and SH16
- improving safety and connectivity at the Station Road intersection.
To view detailed designs for the Station Road Huapai improvements, download the infrastructure report (PDF, 16.4MB)
Following a safety audit and further consultation, we made changes to the originally proposed design.
We have removed the proposed bus stop in front of 22 Station Road. The position of the southbound bus stop opposite 24 Station Road has not changed.
We reconfigured the proposed carparks along both sides of Station Road to improve safety and reduce the impact on properties. The number of proposed carparks on Station Road will remain the same.
To improve safety, we will be installing rubber speed separators along the cycleway and alongside parking areas between the cycleway and road. Separators force vehicles to slow down as they cross the cycleway to access car parks and driveways.
To read more about the raised island separators and rubber speed humps, download the detailed designs (PDF, 1.14MB)
Kumeu — SH16 and Access Road intersection (completed in 2023)
Auckland Transport and Fulton Hogan completed improvements to the SH16 and Access Road intersection in late 2023.
Improvements to the intersection include:
- extending the double lanes of the SH16 westbound approach and eastbound exit
- a left-turn lane to the SH16 westbound approach
- a new shared path on the southern side of SH16
- advanced stop boxes for cyclists on SH16
- an additional 100m exit lane from Access Road
- a controlled east-west pedestrian and cycle crossing over Access Road.
The Access Road outlet to SH16 was made safer with the addition of:
- a left turn slip lane between the new western kerb and a new traffic island to reduce the distance pedestrians and cyclists are required to travel to cross SH16 (north/south) at this point
- a pedestrian maze on Access Road on the eastern side of the level crossing
- improved warning of the approach of trains.
KiwiRail and SHA developers CABRA Developments Ltd are planning further developments to the level crossing. CABRA Developments Ltd. will fund KiwiRail’s safety upgrades to the level crossing.
Space for widening SH16 was made by shifting the roadway northwards to occupy the planted median that forms the boundary between SH16 and a service lane to its immediate north. This also required the reconfiguring of parking and traffic flows in the service lane.
To view detailed plans for the intersection of SH16 and Access Road, download the design drawings download the design drawings (PDF, 11MB)
More information about the SHA
The Huapai Triangle Special Housing Area Roading Infrastructure Upgrade Project (Huapai SHA Project) responds to a requirement created by the Huapai Triangle Special Housing Area (SHA) of 1200 dwellings.
This SHA was permitted by the Government and Auckland Council in 2013. Signatories to the resulting contract were:
Consenting Authorities:
- Government
- Auckland Council
Developers:
- Todd Holdings Ltd.
- CABRA Developments.
Todd Developments has since withdrawn from the Special Housing Area.
Infrastructure providers/owners:
- AT
- Waka Kotahi NZ Transport Agency
- KiwiRail
History of the SHA
In 2014 the Government entered into a Housing Accord with Auckland Council to build Special Housing Areas (SHAs). The first of these was the Huapai Triangle Special Housing Area which provided for the building of 1200 dwellings in a triangle of land at Huapai, bounded by Station Road, Nobilo Road and the Auckland – Northland Railway.
In 2015, there was an agreement between Auckland Council, NZTA, KiwiRail, AT and the then developers, Todd Property Group and CABRA Developments to upgrade the existing roading infrastructure to support the Huapai SHA development (Todd subsequently withdrew).
An Infrastructure Funding Agreement (IFA) was signed in 2017 with CABRA. This creates a broad time-frame which AT must deliver in stages of the agreed works. At the time of the concord to create the SHA, a plan was agreed for upgrading of roading infrastructure to serve the new SHA
For more information on this project, contact projects@at.govt.nz